Progress as on: 10-July-2024 |
WBS | Work Description |
Total Quantity | Upto 03-07-24 | This Week | Total Done |
Schedule Start | Schedule Finish | Avtual Finish |
1.01.1 |
GF-Sheet Repair-Vendor Selection |
0 |
0% |
100% |
100% |
25-06-24 |
01-07-24 |
09-07-24 |
1.02 |
Happiness-Tea Zone Decoration |
0 |
70% |
20% |
90% |
25-06-24 |
26-06-24 |
09-07-24 |
2.02 |
4th Floor-Floor Raising Concrete |
0 |
0% |
100% |
100% |
09-07-24 |
10-07-24 |
10-07-24 |
3.02 |
11 Flr-Suana-Tile remove,Kota Tile |
0 |
0% |
50% |
50% |
01-07-24 |
03-07-24 |
09-07-24 |
4.02 |
14th Floor-Kitchen Tile Work |
0 |
90% |
10% |
100% |
27-06-24 |
30-06-24 |
09-07-24 |
4.04 |
14 Flr-Counter-Top-Back work |
0 |
0% |
30% |
30% |
08-07-24 |
12-07-24 |
09-07-24 |
4.05 |
14th Floor-Lounge Partition Work |
0 |
0% |
10% |
10% |
09-07-24 |
15-07-24 |
09-07-24 |
5.09.1 |
15th Floor-Prodema Fix-Col-L-16-Sou |
0 |
80% |
30% |
110% |
25-06-24 |
26-06-24 |
09-07-24 |
5.09.2 |
L-15-Safety Grill Remove-South |
0 |
0% |
100% |
100% |
26-06-24 |
27-06-24 |
09-07-24 |
5.09.5 |
Prodema Fix-Col-L-16-North |
0 |
0% |
40% |
40% |
29-06-24 |
30-06-24 |
09-07-24 |
6.01 |
17th Floor-Lift Core Top Shed Work |
0 |
0% |
100% |
100% |
27-06-24 |
30-06-24 |
09-07-24 |