Total Duration: |
10 |
days |
Total Working Days: |
3 |
Total Manpower: |
96 |
|
|
Planning Progress = 100% |
Acual Progress = 152% |
SPI: 1.52 |
Ahead Schedule |
Progress as on: 10-July-2024
WBS |
Work Description |
Total Quantity |
Total Done |
Schedule Start
| Schedule Finish |
Actual Start |
Actual Finish |
Lead-Lag(day) |
Not Yet |
1.01.1 |
GF-Sheet Repair-Vendor Selection |
0 |
100% |
25-06-24 |
01-07-24 |
09-07-24 |
09-07-24 |
-8 |
|
1.02 |
Happiness-Tea Zone Decoration |
0 |
90% |
25-06-24 |
26-06-24 |
30-06-24 |
09-07-24 |
-13 |
Completed |
2.01 |
4th Floor-Ceiling Decoration |
0 |
100% |
25-06-24 |
30-06-24 |
30-06-24 |
30-06-24 |
0 |
|
2.02 |
4th Floor-Floor Raising Concrete |
0 |
100% |
09-07-24 |
10-07-24 |
09-07-24 |
10-07-24 |
0 |
|
3.02 |
11 Flr-Suana-Tile remove,Kota Tile |
0 |
50% |
01-07-24 |
03-07-24 |
09-07-24 |
09-07-24 |
-6 |
Completed |
4.01 |
14th Floor-Kitchen Gas Line |
0 |
100% |
25-08-24 |
26-06-24 |
30-06-24 |
30-06-24 |
-4 |
|
4.02 |
14th Floor-Kitchen Tile Work |
0 |
100% |
27-06-24 |
30-06-24 |
30-06-24 |
09-07-24 |
-9 |
|
4.04 |
14 Flr-Counter-Top-Back work |
0 |
30% |
08-07-24 |
12-07-24 |
09-07-24 |
09-07-24 |
3 |
|
4.05 |
14th Floor-Lounge Partition Work |
0 |
10% |
09-07-24 |
15-07-24 |
09-07-24 |
09-07-24 |
6 |
|
5.07 |
15th Floor-Double Height Grill |
0 |
90% |
25-06-24 |
01-07-24 |
30-06-24 |
30-06-24 |
1 |
Completed |
5.09.1 |
15th Floor-Prodema Fix-Col-L-16-Sou |
0 |
110% |
25-06-24 |
26-06-24 |
30-06-24 |
09-07-24 |
-13 |
|
5.09.2 |
L-15-Safety Grill Remove-South |
0 |
100% |
26-06-24 |
27-06-24 |
09-07-24 |
09-07-24 |
-12 |
|
5.09.5 |
Prodema Fix-Col-L-16-North |
0 |
40% |
29-06-24 |
30-06-24 |
09-07-24 |
09-07-24 |
-9 |
Completed |
6.01 |
17th Floor-Lift Core Top Shed Work |
0 |
100% |
27-06-24 |
30-06-24 |
09-07-24 |
09-07-24 |
-9 |
|