DAILY PROGRES REPORT |
Project: | Cityscape Lifestyle-2 | Project Code: | 64 | Date | 10-July-2024 | ||
Client: | Report | 003 | Day | Wednesday | |||
Contractor: | Cityscape International Ltd. | Climate | Sunny | ||||
Temperature | 28-33C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Cityscape-Staff | 4 |
04 | Sumon-Mason | 7 |
07 | Bikash-Carpenter-1 | 4 |
08 | Razzak-Carpenter | 6 |
09 | Nantu-Carpenter | 5 |
10 | Cityscape-Labor-1 | 3 |
TOTAL | 29 |
WBS | Work Description | Progress as on: 10-July-2024 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
2.02 | 4th Floor-Floor Raising Concrete | 0 | 70 | 100 | 09-07-24 | 10-07-24 |
Site Photographs | |
4th Flr-Floor Raining Concreting Complet | 11th Floor Interior Work |
Site Description | |
4th Flr-Floor Raining Concreting Complete | |
Site Instruction | |