Return Main Menu

WEEKY PROGRESS REPORT

From 21-January-2024 to 28-January-2024
Project Code: 63Name:Cityscape Lifestyle
Client: Cityscape Lifestyle Contractor:Cityscape International Ltd.
Progress as on: 28-January-2024
WBSWork Description
Total QuantityUpto 21-01-24This WeekTotal Done Schedule StartSchedule FinishAvtual Finish
02.2.2 L-15-CC with Neat Cement Finish 156m2 0% 100% 100% 24-01-24 27-01-24 28-01-24
06.09.2. L-11-Steam-Tile/Marble-work 0 93% 2% 95% 11-12-23 16-12-23 22-01-24
06.09.2. L-11-Steam-Suana-Design Plaster 0% 60% 60% 16-01-24 22-01-24 22-01-24
06.09.6 L-11-Steam n Suana-MEP Works 0 80% 5% 85% 12-12-23 18-12-23 24-01-24
06.09.7 L-11-Steam-Suana-False Ceiling 0 10% 5% 15% 28-12-23 31-12-23 22-01-24


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
L-11-Outside Design Plaster on 22-01-24L-14-False Ceiling and Interioron 22-01-24
Five days progress
L-15-CC with NCF on 24-01-24L-11-Light fittingon 24-01-24
Two days progress
L-14-Floor CC with NCF on 26-01-24L-14-Floor CC with NCFon 26-01-24
Three days progress
L-15-Toilet Floor CC with NCF on 28-01-24L-15-Floor CC with NCF on 28-01-24