WEEKY PROGRESS REPORT |
From 21-January-2024 to 28-January-2024 | ||||
Project Code: | 63 | Name: | Cityscape Lifestyle | |
Client: | Cityscape Lifestyle | Contractor: | Cityscape International Ltd. |
Progress as on: 28-January-2024 | ||||||||
WBS | Work Description | |||||||
Total Quantity | Upto 21-01-24 | This Week | Total Done | Schedule Start | Schedule Finish | Avtual Finish | ||
02.2.2 | L-15-CC with Neat Cement Finish | 156m2 | 0% | 100% | 100% | 24-01-24 | 27-01-24 | 28-01-24 |
06.09.2. | L-11-Steam-Tile/Marble-work | 0 | 93% | 2% | 95% | 11-12-23 | 16-12-23 | 22-01-24 |
06.09.2. | L-11-Steam-Suana-Design Plaster | 0% | 60% | 60% | 16-01-24 | 22-01-24 | 22-01-24 | |
06.09.6 | L-11-Steam n Suana-MEP Works | 0 | 80% | 5% | 85% | 12-12-23 | 18-12-23 | 24-01-24 |
06.09.7 | L-11-Steam-Suana-False Ceiling | 0 | 10% | 5% | 15% | 28-12-23 | 31-12-23 | 22-01-24 |
Site Photographs | |
L-11-Outside Design Plaster on 22-01-24 | L-14-False Ceiling and Interioron 22-01-24 |
Five days progress | |
L-15-CC with NCF on 24-01-24 | L-11-Light fittingon 24-01-24 |
Two days progress | |
L-14-Floor CC with NCF on 26-01-24 | L-14-Floor CC with NCFon 26-01-24 |
Three days progress | |
L-15-Toilet Floor CC with NCF on 28-01-24 | L-15-Floor CC with NCF on 28-01-24 |