DAILY PROGRES REPORT |
Project: | Cityscape Lifestyle | Project Code: | 63 | Date | 28-January-2024 | ||
Client: | Cityscape Lifestyle | Report | 054 | Day | Sunday | ||
Contractor: | Cityscape International Ltd. | Climate | Sunny | ||||
Temperature | 12-25C |
Manpower | ||
SN | Description | Nos |
---|---|---|
05 | Sikder-Mason-Day shift | 2 |
06 | Sikder-Labor-Day shift | 3 |
TOTAL | 5 |
WBS | Work Description | Progress as on: 28-January-2024 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
02.2.2 | L-15-CC with Neat Cement Finish | 156m2 | 30 | 100 | 24-01-24 | 27-01-24 |
Site Photographs | |
L-15-Toilet Floor CC with NCF | L-15-Floor CC with NCF |
Site Description | |
Site Instruction | |