DAILY PROGRES REPORT

Project:Cityscape Lifestyle Project Code: 63 Date28-January-2024
Client: Cityscape Lifestyle Report054 DaySunday
Contractor:Cityscape International Ltd. ClimateSunny
Temperature12-25C
Manpower
SNDescriptionNos
05Sikder-Mason-Day shift2
06Sikder-Labor-Day shift3
TOTAL 5
WBSWork Description Progress as on: 28-January-2024
Total QtyToday Done (%)Total Done (%)StartFinish
02.2.2 L-15-CC with Neat Cement Finish 156m2 30 100 24-01-24 27-01-24
Site Photographs
L-15-Toilet Floor CC with NCF L-15-Floor CC with NCF
Site Description
Site Instruction