Progress as on: 28-January-2024 |
WBS | Work Description |
Total Quantity | Upto 31-12-23 | This Month | Total Done |
Schedule Start | Schedule Finish | Actual Finish |
02.2.2 |
L-15-CC with Neat Cement Finish |
156m2 |
0% |
100% |
100% |
24-01-24 |
27-01-24 |
28-01-24 |
03.3.1 |
L-14-AC Installation |
1sum |
57% |
3% |
60% |
31-10-23 |
10-01-24 |
17-01-24 |
03.3.6.2 |
L-14-Ceiling-Installation |
0 |
34% |
3% |
37% |
17-11-23 |
15-01-24 |
17-01-24 |
03.3.7 |
L-14-Internal Electrif-Floor+Ceilin |
0 |
23% |
1% |
24% |
04-11-23 |
02-01-24 |
10-01-24 |
03.4 |
L-14-Marble in Floor |
464m2 |
13% |
6% |
19% |
17-12-23 |
06-01-24 |
17-01-24 |
03.5.2 |
L-14-Outside Partition+Door-make,in |
0 |
10% |
10% |
20% |
23-12-23 |
01-01-24 |
01-01-24 |
06.09.2.3 |
L-11-Steam-Tile/Marble-work |
0 |
90% |
5% |
95% |
11-12-23 |
16-12-23 |
22-01-24 |
06.09.2.6 |
L-11-Steam-Suana-Design Plaster |
|
0% |
60% |
60% |
16-01-24 |
22-01-24 |
22-01-24 |
06.09.6 |
L-11-Steam n Suana-MEP Works |
0 |
45% |
40% |
85% |
12-12-23 |
18-12-23 |
24-01-24 |
06.09.7 |
L-11-Steam-Suana-False Ceiling |
0 |
10% |
5% |
15% |
28-12-23 |
31-12-23 |
22-01-24 |
06.09.8 |
L-11-Suana-Wooden Floor-Wall |
0 |
20% |
75% |
95% |
30-12-23 |
05-01-24 |
06-01-24 |
Site Photographs |
| |
L-11-Steam-Suana-Wooden Wall-Lighting on 1-01-24 | L-14-Floor Marble Mock-upon 1-01-24 |
Two days work |
|
| |
L-11-Suana-Wooden Wall Work on 6-01-24 | L-14-AC Duct installationon 6-01-24 |
Five days work |
|
| |
L-14-AC Duct fabrication on 8-01-24 | L-14-False Ceiling Workon 8-01-24 |
|
|
| |
L-11-Steam-Suana-Marble rectification on 10-01-24 | L-14-Electrical workon 10-01-24 |
Two days work |
|
| |
L-14-AC Ducting on 17-01-24 | L-14-False Ceiling Workon 17-01-24 |
Seven days progress |
|
| |
L-11-Outside Design Plaster on 22-01-24 | L-14-False Ceiling and Interioron 22-01-24 |
Five days progress |
|
| |
L-15-CC with NCF on 24-01-24 | L-11-Light fittingon 24-01-24 |
Two days progress |
|
| |
L-14-Floor CC with NCF on 26-01-24 | L-14-Floor CC with NCFon 26-01-24 |
Three days progress |
|
| |
L-15-Toilet Floor CC with NCF on 28-01-24 | L-15-Floor CC with NCF on 28-01-24 |
|
|