TOTAL PROGRES REPORT

From 7-October-2023 to 28-January-2024
Project Code: 63 Name: Cityscape Lifestyle
Client: Cityscape Lifestyle Contractor: Cityscape
Progress as on: 28-January-2024
Total Duration: 113 days Total Working Days: 54 Total Manpower: 619
Planning Progress = 79.5% Acual Progress = 41.6% SPI: 0.52 Behind Schedule
WBS Work Description
Total Quantity Total Done Schedule Start Schedule Finish Actual Start Actual Finish Lead-Lag(day) Not Yet
02.1 L-16-Material Removal 0 100% 23-11-23 02-12-23 23-11-23 30-11-23 2
02.2.1 L-15-Wooden Floor Dismantling 140m2 100% 23-12-23 27-12-23 24-12-23 26-12-23 1
02.2.2 L-15-CC with Neat Cement Finish 156m2 100% 24-01-24 27-01-24 24-01-24 28-01-24 -1
02.3 L-15-16-Prodema Fixing 0 1% 28-12-23 26-01-24 28-12-23 28-12-23 29 Completed
03.1.1 L14-Old Kitchen Wall-Shelf dismantl 1sum 100% 09-10-23 12-10-23 09-10-23 15-10-23 -3
03.1.2 L14-Old Kitchen Wall Debris shiftin 1sum 100% 13-10-23 16-10-23 13-10-23 19-10-23 -3
03.1.3 L-14-Kitchen Floor dismantling 16m3 100% 17-10-23 19-10-23 17-10-23 25-10-23 -6
03.1.4 L-14-Old Kitchen Floor debris shift 1sum 100% 20-10-23 22-10-23 19-10-23 28-10-23 -6
03.1.5 L-14-East-South Brickwall dismantli 20m2 100% 17-10-23 17-10-23 17-10-23 17-10-23 0
03.1.6 L-14-Wall Debris shifting 1sum 100% 18-10-23 18-10-23 17-10-23 17-10-23 1
03.10 L-14-Brickwork-South-East 0 30% 28-12-23 31-12-23 28-12-23 28-12-23 3 Completed
03.2 L-14-Stair Case-South-Door Cutting 1nos 100% 14-10-23 16-10-23 14-10-23 17-10-23 -1
03.3.1 L-14-AC Installation 1sum 60% 31-10-23 10-01-24 08-11-23 17-01-24 -7 Completed
03.3.2 L-14-Toilet Plumbing and Tiles 1sum 0% 23-12-23 02-01-24 30-11--1 0 Started
03.3.3 L-14-Counter 0 0% 23-12-23 06-01-24 30-11--1 0 Started
03.3.4 L-14-Neat Cement Finish 0 100% 11-11-23 17-11-23 22-11-23 20-12-23 -33
03.3.5 L-14-Wall Painting 0 0% 23-12-23 27-12-23 30-11--1 0 Started
03.3.6.1 L-14-Ceiling-Design 0 100% 31-10-23 08-11-23 20-12-23 20-12-23 -42
03.3.6.2 L-14-Ceiling-Installation 0 37% 17-11-23 15-01-24 20-12-23 17-01-24 -2 Completed
03.3.7 L-14-Internal Electrif-Floor+Ceilin 0 24% 04-11-23 02-01-24 26-11-23 10-01-24 -8 Completed
03.3.8.1 L-14-Furniture Design 0 0% 23-12-23 28-12-23 30-11--1 0 Started
03.3.8.2 L-14-Furniture making, Installation 0 0% 29-12-23 12-01-24 30-11--1 0 Started
03.3.9 L-14-Fire Sprinklers Pipe installat 0 95% 13-12-23 11-01-24 13-12-23 24-12-23 18 Completed
03.4 L-14-Marble in Floor 464m2 19% 17-12-23 06-01-24 20-12-23 17-01-24 -11 Completed
03.5.1 L-14-Outside Partition+Door-Mockup 0 100% 20-12-23 23-12-23 24-12-23 24-12-23 -1
03.5.2 L-14-Outside Partition+Door-make,in 0 20% 23-12-23 01-01-24 30-12-23 01-01-24 0 Completed
03.6.1 L-14-Outside-Rail-Mockup 0 100% 23-12-23 27-12-23 24-12-23 24-12-23 3
03.6.2 L-14-Outside-Rail-make,install 0 0% 24-12-23 07-01-24 30-11--1 0 Started
03.7.1 L-14-Front Lobby-Mockup 0 0% 23-12-23 27-12-23 30-11--1 0 Started
03.7.2 L-14-Front Lobby-make,install 0 0% 01-01-24 15-01-24 30-11--1 0 Started
03.8.1 L-14-Kitchen-Equipment-Selection 0 0% 23-12-23 25-12-23 30-11--1 0 Started
03.8.2 L-14-Kitchen-Equipment-Installation 0 0% 26-12-23 09-01-24 30-11--1 0 Started
03.9.1 L-14-Bar Light-Selection 0 0% 23-12-23 25-12-23 30-11--1 0 Started
03.9.2 L-14-Bar Light-Insatallation 0 0% 26-12-23 02-01-24 30-11--1 0 Started
06.09.1 L-11-Steam n Suana-Ar.Design 0 100% 25-11-23 27-11-23 27-11-23 27-11-23 0
06.09.2.1 L-11-Steam n Suana-Brick-work 0 100% 28-11-23 07-12-23 28-11-23 07-12-23 0
06.09.2.2 L-11-Steam n Suana-Tile/Marble Sele 0 100% 05-12-23 06-12-23 09-12-23 09-12-23 -3
06.09.2.3 L-11-Steam-Tile/Marble-work 0 95% 11-12-23 16-12-23 13-12-23 22-01-24 -37 Completed
06.09.2.4 L-11-Steam-RCC Seating 0 100% 08-12-23 09-12-23 09-12-23 09-12-23 0
06.09.2.5 L-11-Steam n Suana-Plastering 0 100% 09-12-23 13-12-23 09-12-23 13-12-23 0
06.09.2.6 L-11-Steam-Suana-Design Plaster 60% 16-01-24 22-01-24 22-01-24 22-01-24 0 Completed
06.09.4 L-11-Steam Machine Installation 0 10% 17-12-23 05-01-24 30-12-23 30-12-23 6 Completed
06.09.6 L-11-Steam n Suana-MEP Works 0 85% 12-12-23 18-12-23 09-12-23 24-01-24 -37 Completed
06.09.7 L-11-Steam-Suana-False Ceiling 0 15% 28-12-23 31-12-23 28-12-23 22-01-24 -22 Completed
06.09.8 L-11-Suana-Wooden Floor-Wall 0 95% 30-12-23 05-01-24 30-12-23 06-01-24 -1 Completed
06.10 L-11-Louge Outside Glass Frame 0 50% 24-12-23 30-12-23 26-12-23 28-12-23 2 Completed
12.1.1 L-4-North-East-Vault Dismantling 1sum 100% 05-10-23 12-10-23 07-10-23 14-10-23 -2
12.1.2 L-4-North-East-Vault debris shiftin 1sum 100% 13-10-23 14-10-23 10-10-23 15-10-23 -1


DAILY MANPOWER








CUMMULATIVE ACTUAL WORK PROGRESS








CUMMULATIVE PLAN WORK PROGRESS








CUMMULATIVE WORK PROGRESS








SCHEDULE AHEAD-BEHIND






Site Photographs
L-4-North Vault dismanling on 7-10-23
L-4-North Vault dismantling on 7-10-23
L-4-North-East Vault dismantling on 8-10-23
L-4-North-East Vault dismantling on 8-10-23
L-4-North Vault dismanling on 9-10-23
L-14-Old Kitchen wall dismantling on 9-10-23
Proper Safety (PPE) must maintain
Safety Induction to Labour on 10-10-23
L-14-Fin glass broken during dismantling on 10-10-23
Dismantle carefully avoiding any damage
L-14-Old Kitchen wall dismantling on 11-10-23
L-4-North Vault dismanling on 11-10-23
L-4-North Vault dismanling on 13-10-23
L-14-Old Kitchen wall dismantling on 13-10-23
L-4-North-East Vault demolition complete on 14-10-23
L-14-Stair Case-S-Door Cutting Start on 14-10-23
L14-Starcase-South-Door Cutting on 15-10-23
L14-Old Kitchen Wall-shelf demolition co on 15-10-23
L-14-Kitchen Area on 16-10-23
L-14-Dismatled Brick on 16-10-23
Dismantled brick to be used in another work
L-14-Litchen Floor dismantling on 17-10-23
L-14-East-South Wall dismantling on 17-10-23
Proper PPE must be maintained
L-14-Kitchen Floor dismantling on 18-10-23
L-14-Kithen Floor Area on 18-10-23
Proper PPE must be maintained
L-14-Kitcjen-Floor Dismantling on 19-10-23
L-14-Kitchen Floor Debris shifting on 19-10-23
Proper Safety (PPE) must maintain
L-14-Kitchen Floor Debris Removing on 23-10-23
L-14-Kitchen Area on 23-10-23
L-14-Kitchen Area on 24-10-23
L-14-Kitchen Area on 24-10-23
L-14-Old Kitchen Floor Dismantling on 25-10-23
L-14-Old Kitchen Area on 25-10-23
L-14-Old Kitchen Area on 26-10-23
L-14-Old Kitchen Area Debris removing on 26-10-23
L-14-Old Kitchen Area on 28-10-23
L-14-Old Kitchen Area on 28-10-23
Safety Induction on 8-11-23
L-14-Old AC Duct Removing on 8-11-23
Tool-box Meeting on 9-11-23
L-14-Old AC duct removing on 9-11-23
L-14-AC installation on 14-11-23
L-14-AC installation on 14-11-23
L-14-AC Installation on 15-11-23
L-14-AC Installation on 15-11-23
L-14-AC Installation on 19-11-23
L-14-AC Installation on 19-11-23
L-14-AC Installation on 22-11-23
L-14-NCF Mock-up on 22-11-23
L-16-Materials Removal on 23-11-23
L-14-NCF Material procured on 23-11-23
L-16-Materials Removal on 25-11-23
L-16-Materials Removal on 25-11-23
L-14-AC Duct fabrication on 26-11-23
L-14-Electrical Pipe Laying on 26-11-23
L-14-AC Installation on 27-11-23
L-14-Electrical Pipe Laying on 27-11-23
L-14-Electrical Pile laying on 28-11-23
L-11-Steam n Suana-Brickwork on 28-11-23
L-16-Materials Removal on 29-11-23
L-11-Steam n Suana-Brickwork on 29-11-23
L-14-NCF Work start at night on 30-11-23
L-14-Floor NCF Work on 30-11-23
L-11-Steam-Suana-Brick-work on 2-12-23
L-11-Steam-Suana-Brick-work on 2-12-23
L-11-Steam-Suana-Brick-work on 3-12-23
L-11-Steam-Suana-Brick-work on 3-12-23
L-11-Steam-Suana-Brick-work on 4-12-23
L-11-Steam-Suana-Brick-work on 4-12-23
L-11-Steam-Suana-Brickwork on 7-12-23
L-11-Steam-Suana-Brickwork on 7-12-23
Three days progress
L-11-Steam-Suana-MEP Works on 9-12-23
L-11-Steam-Seating RCC work on 9-12-23
Two days work
L-11-Steam-Suana-Plumbing work on 10-12-23
L-11-Steam-Suana-Plastering on 10-12-23
L-11-Steam-Suana-Plumbing work on 11-12-23
L-11-Steam n Suana-Plastering on 11-12-23
L-11-Steam-Suana-Plastering on 12-12-23
L-11-Steam-Suana-Plastering on 12-12-23
L-11-Steam-Marble moulding on 13-12-23
L-11-Steam-Wall tile fixing on 13-12-23
L-11-Steam-Tile Work on 17-12-23
L-11-Steam-Tile/Marble Work on 17-12-23
Three days work
L-11-Steam-Suana-Marble fixing on 20-12-23
L-11-Electrical wiring on 20-12-23
Three days work
L-14-False Ceiling work on 24-12-23
L-15-Wooden Floor dismantling on 24-12-23
Three days work
L-11-Steam-Suana-Marble Polishing on 26-12-23
L-15-Wooden Floor dismantling on 26-12-23
Two days work
L-11-Steam-Suana-False Ceiling on 28-12-23
L-11-Lounge Outside Glass Frame on 28-12-23
Two days work
L-11-Steam machine installation on 30-12-23
L-11-Suana Wooden wall on 30-12-23
L-11-Steam-Suana-Wooden Wall-Lighting on 1-01-24
L-14-Floor Marble Mock-up on 1-01-24
Two days work
L-11-Suana-Wooden Wall Work on 6-01-24
L-14-AC Duct installation on 6-01-24
Five days work
L-14-AC Duct fabrication on 8-01-24
L-14-False Ceiling Work on 8-01-24
L-11-Steam-Suana-Marble rectification on 10-01-24
L-14-Electrical work on 10-01-24
Two days work
L-14-AC Ducting on 17-01-24
L-14-False Ceiling Work on 17-01-24
Seven days progress
L-11-Outside Design Plaster on 22-01-24
L-14-False Ceiling and Interior on 22-01-24
Five days progress
L-15-CC with NCF on 24-01-24
L-11-Light fitting on 24-01-24
Two days progress
L-14-Floor CC with NCF on 26-01-24
L-14-Floor CC with NCF on 26-01-24
Three days progress
L-15-Toilet Floor CC with NCF on 28-01-24
L-15-Floor CC with NCF on 28-01-24