WEEKY PROGRESS REPORT |
From 22-April-2023 to 29-April-2023 |
Project Code: |
62 | Name: | Cityscape Tower Col Beam Ext-L-14-17 |
Client: | Cityscape | |
Contractor: | Cityscape International Ltd. |
Progress as on: 29-April-2023 |
WBS | Work Description |
Total Quantity | Upto 22-04-23 | This Week | Total Done |
Schedule Start | Schedule Finish | Avtual Finish |
2.1.09 |
l-16-Drop Wall-Shuttering |
1sum |
0% |
5% |
5% |
30-04-23 |
06-05-23 |
29-04-23 |
Site Photographs |
| |
L-16-Beam Shutter removing on 29-04-23 | L-16-Drop Wall Shutteringon 29-04-23 |
Work stopped 21-28 Apr due to Eid Vacation |
|