MONTHLY PROGRESS REPORT

From 1-April-2023 to 29-April-2023
Project Code: 62Name:Cityscape Tower Col Beam Ext-L-14-17
Client: Cityscape Contractor:Cityscape International Ltd.
Progress as on: 29-April-2023
WBSWork Description
Total QuantityUpto 31-03-23This MonthTotal Done Schedule StartSchedule FinishActual Finish
2.1.02 L-16-Podema Board removin 1sum 90% 10% 100% 27-03-23 31-03-23 09-04-23
2.1.05 L-16-Col Beam Ext-Re-bar Fabricat 1sum 0% 100% 100% 06-04-23 10-04-23 18-04-23
2.1.06 L-16-Col Beam Ext-Shutterin 1sum 0% 100% 100% 11-04-23 13-04-23 18-04-23
2.1.07 L-16-Col Beam Ext-Concretin 1sum 0% 100% 100% 14-04-23 14-04-23 19-04-23
2.1.09 l-16-Drop Wall-Shuttering 1sum 0% 5% 5% 30-04-23 06-05-23 29-04-23


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
L-16-Column Stirrups making on 1-04-23L-16-Scaffoldingon 1-04-23
L-16-Column Stirrups making on 2-04-23L-16-Re-bar fixing on 2-04-23
L-16-Column Re-bar on 5-04-23L-16-Column concrete mixingon 5-04-23
L-16-Column Shuttering on 9-04-23L-16-Column Re-bar Workon 9-04-23
L-16-Column shuttering on 11-04-23L-16-Column concreting on 11-04-23
L-16-Column shuttering on 13-04-23L-16-Column concreting on 13-04-23
L-16-Beam bottom shuttering on 15-04-23L-16-Beam Re-bar fabricationon 15-04-23
L-16-Beam shuttering on 18-04-23L-16-Beam shuttering on 18-04-23
L-16-Column curing chemical applying on 19-04-23L-16-Beam concreting complete on 19-04-23
L-16-Beam Shutter removing on 29-04-23L-16-Drop Wall Shutteringon 29-04-23
Work stopped 21-28 Apr due to Eid Vacation