![]() |
TOTAL PROGRES REPORT |
From 21-January-2023 to 29-April-2023 | ||||
Project Code: | 62 | Name: | Cityscape Tower Col Beam Ext-L-14-17 | |
Client: | Cityscape | Contractor: | Cityscape International Ltd. |
Total Duration: | 98 | days | Total Working Days: | 37 | Total Manpower: | 187 | |||
Planning Progress = 73.8% | Acual Progress = 69.3% | SPI: 0.94 | Behind Schedule | ||||||
WBS | Work Description | ||||||||
Total Quantity | Total Done | Schedule Start | Schedule Finish | Actual Start | Actual Finish | Lead-Lag(day) | Not Yet | ||
1.1 | Contractor Selection | 1sum | 100% | 07-01-23 | 08-01-23 | 08-01-23 | 08-01-23 | 0 | |
1.2.1 | Outer Glass Removal-L-13 | 1sum | 100% | 09-01-23 | 15-01-23 | 21-01-23 | 26-01-23 | -11 | |
1.2.2 | Safety Installation-L-14 | 1sum | 100% | 16-01-23 | 22-01-23 | 21-01-23 | 26-01-23 | -4 | |
1.2.3 | Steel Fabrication Work L-14 | 1sum | 100% | 23-01-23 | 05-02-23 | 26-01-23 | 13-02-23 | -8 | |
1.2.4 | Civil Work L-14 | 1sum | 100% | 06-02-23 | 12-02-23 | 21-01-23 | 13-02-23 | -1 | |
1.3.1 | Outer Glass Removal-L-14 | 1sum | 100% | 13-02-23 | 19-02-23 | 26-01-23 | 31-01-23 | 19 | |
1.3.2 | Safety Installation-L-15 | 1sum | 100% | 20-02-23 | 26-02-23 | 26-01-23 | 02-02-23 | 24 | |
1.3.3 | Steel Fabrication L-15 | 1sum | 100% | 27-02-23 | 12-03-23 | 13-02-23 | 20-02-23 | 20 | |
1.3.4 | Civil work L-15 | 1sum | 100% | 13-03-23 | 19-03-23 | 22-02-23 | 25-02-23 | 22 | |
2.1.01 | L-16-Scaffolding and Safety Instal | 1sum | 100% | 20-03-23 | 26-03-23 | 27-02-23 | 18-03-23 | 8 | |
2.1.02 | L-16-Podema Board removin | 1sum | 100% | 27-03-23 | 31-03-23 | 20-03-23 | 09-04-23 | -9 | |
2.1.03 | L-16-Old Column Concrete Demolis | 1sum | 100% | 01-04-23 | 05-04-23 | 20-03-23 | 29-03-23 | 7 | |
2.1.04 | L-16-Dropwall old concrete dismant | 1sum | 100% | 01-04-23 | 05-04-23 | 29-03-23 | 31-03-23 | 5 | |
2.1.05 | L-16-Col Beam Ext-Re-bar Fabricat | 1sum | 100% | 06-04-23 | 10-04-23 | 01-04-23 | 18-04-23 | -8 | |
2.1.06 | L-16-Col Beam Ext-Shutterin | 1sum | 100% | 11-04-23 | 13-04-23 | 05-04-23 | 18-04-23 | -5 | |
2.1.07 | L-16-Col Beam Ext-Concretin | 1sum | 100% | 14-04-23 | 14-04-23 | 05-04-23 | 19-04-23 | -5 | |
2.1.08 | L-16-Drop Wall-Re-bar Work | 1sum | 0% | 02-05-23 | 04-05-23 | 0 | |||
2.1.09 | l-16-Drop Wall-Shuttering | 1sum | 5% | 30-04-23 | 06-05-23 | 29-04-23 | 29-04-23 | 7 | |
2.1.10 | L-16-Dropwall Concreting | 1sum | 0% | 07-05-23 | 08-05-23 | 0 | |||
2.2.1 | L-17-Scaffolding and Safety Install | 1sum | 0% | 15-04-23 | 01-05-23 | 0 | Started | ||
2.2.2 | L-17-Podema Board removing | 1sum | 0% | 02-05-23 | 06-05-23 | 0 | |||
2.2.3 | L-17-Old Concrete Demolish | 1sum | 0% | 07-05-23 | 11-05-23 | 0 | |||
2.2.4 | L-17-Col Beam Ext-Re-bar Fabricatn | 1sum | 0% | 12-05-23 | 16-05-23 | 0 | |||
2.2.5 | L-17-Col Beam Ext-Shuttering | 1sum | 0% | 17-05-23 | 19-05-23 | 0 | |||
2.2.6 | L-17-Col Beam Ext-Concreting | 1sum | 0% | 20-05-23 | 20-05-23 | 0 |
Site Photographs | |
![]() |
|
on 21-01-23 | |
![]() |
|
on 21-01-23 | |
![]() |
|
Chemical Bolt fixing on 26-01-23 | |
![]() |
|
on 26-01-23 | |
![]() |
|
on 31-01-23 | |
![]() |
|
on 31-01-23 | |
![]() |
|
South-side safety tray & net complete on 2-02-23 | |
![]() |
|
I-Joist Lifting on 16th Floor on 2-02-23 | |
No Helmet, safety shoe & Hand gloves (right-side) | |
![]() |
|
Shifting from L-17 to 15 on 5-02-23 | |
![]() |
|
Keeping L-15 on 5-02-23 | |
![]() |
|
Level-14-Steel Work on 8-02-23 | |
![]() |
|
on 8-02-23 | |
![]() |
|
Lavel-14 Decking Slab complete on 13-02-23 | |
![]() |
|
Level-14 Slab concrete completed on 13-02-23 | |
![]() |
|
L-15 Anchor bolt drilling on 15-02-23 | |
![]() |
|
L-15 Anchor bolt drilling on 15-02-23 | |
![]() |
|
L-15-Steel Fabrication on 18-02-23 | |
![]() |
|
L-15-Steel Fabrication on 18-02-23 | |
![]() |
|
Level-15 Decking Slab fixing on 20-02-23 | |
![]() |
|
L-15 Decking Slab fixing on 20-02-23 | |
![]() |
|
Old Slab concrete chipping on 22-02-23 | |
![]() |
|
For Re-bar lapping & welding on 22-02-23 | |
![]() |
|
Level-15-Ext Slab Concreting on 25-02-23 | |
![]() |
|
Level-15-Ext Slab Concreting on 25-02-23 | |
![]() |
|
L-14-Ext Decking and Beam Painting on 27-02-23 | |
![]() |
|
L-14-Ext Decking and Beam Painting on 27-02-23 | |
![]() |
|
L-16-Safety Installation on 1-03-23 | |
![]() |
|
L-16-Safety Installation on 1-03-23 | |
![]() |
|
L-16-Safety installation on 4-03-23 | |
![]() |
|
L-16-Safety installation on 4-03-23 | |
![]() |
|
L-16-Safety installation on 6-03-23 | |
![]() |
|
L-16-Safety installation on 6-03-23 | |
![]() |
|
L-16 Safety installation on 9-03-23 | |
![]() |
|
L-16-Safety installation on 9-03-23 | |
![]() |
|
L-16-West side safety work on 12-03-23 | |
![]() |
|
L-16-West side safety work on 12-03-23 | |
![]() |
|
L-16-West side safety net hanging on 14-03-23 | |
![]() |
|
L-16-West side safety net hanging on 14-03-23 | |
![]() |
|
L-16-West side safety net hanging on 15-03-23 | |
![]() |
|
L-16-West side safety net hanging on 15-03-23 | |
![]() |
|
L-16-Safety installation on 18-03-23 | |
![]() |
|
L-16-Safety installation on 18-03-23 | |
![]() |
|
L-16 Scaffolding on 20-03-23 | |
![]() |
|
L-16-Scaffolding on 20-03-23 | |
![]() |
|
L-16-Old concrete removing on 22-03-23 | |
![]() |
|
L-16-Old concrete removing on 22-03-23 | |
![]() |
|
L-16-Existing Column top dismantling on 27-03-23 | |
![]() |
|
L-16-Existing Column top dismantling on 27-03-23 | |
![]() |
|
L-16-Dropwall old concrete dismantling on 29-03-23 | |
![]() |
|
L-16-Dropwall old concrete dismantling on 29-03-23 | |
![]() |
|
L-17-Slab chpping on 30-03-23 | |
![]() |
|
L-17-Slab chpping on 30-03-23 | |
![]() |
|
L-16-Scaffolding on 31-03-23 | |
![]() |
|
L-16-Scaffolding on 31-03-23 | |
![]() |
|
L-16-Column Stirrups making on 1-04-23 | |
![]() |
|
L-16-Scaffolding on 1-04-23 | |
![]() |
|
L-16-Column Stirrups making on 2-04-23 | |
![]() |
|
L-16-Re-bar fixing on 2-04-23 | |
![]() |
|
L-16-Column Re-bar on 5-04-23 | |
![]() |
|
L-16-Column concrete mixing on 5-04-23 | |
![]() |
|
L-16-Column Shuttering on 9-04-23 | |
![]() |
|
L-16-Column Re-bar Work on 9-04-23 | |
![]() |
|
L-16-Column shuttering on 11-04-23 | |
![]() |
|
L-16-Column concreting on 11-04-23 | |
![]() |
|
L-16-Column shuttering on 13-04-23 | |
![]() |
|
L-16-Column concreting on 13-04-23 | |
![]() |
|
L-16-Beam bottom shuttering on 15-04-23 | |
![]() |
|
L-16-Beam Re-bar fabrication on 15-04-23 | |
![]() |
|
L-16-Beam shuttering on 18-04-23 | |
![]() |
|
L-16-Beam shuttering on 18-04-23 | |
![]() |
|
L-16-Column curing chemical applying on 19-04-23 | |
![]() |
|
L-16-Beam concreting complete on 19-04-23 | |
![]() |
|
L-16-Beam Shutter removing on 29-04-23 | |
![]() |
|
L-16-Drop Wall Shuttering on 29-04-23 | |
Work stopped 21-28 Apr due to Eid Vacation | |