Total Duration: |
98 |
days |
Total Working Days: |
37 |
Total Manpower: |
187 |
|
|
Planning Progress = 73.8% |
Acual Progress = 69.3% |
SPI: 0.94 |
Behind Schedule |
Progress as on: 29-April-2023
WBS |
Work Description |
Total Quantity |
Total Done |
Schedule Start
| Schedule Finish |
Actual Start |
Actual Finish |
Lead-Lag(day) |
Not Yet |
1.1 |
Contractor Selection |
1sum |
100% |
07-01-23 |
08-01-23 |
08-01-23 |
08-01-23 |
0 |
|
1.2.1 |
Outer Glass Removal-L-13 |
1sum |
100% |
09-01-23 |
15-01-23 |
21-01-23 |
26-01-23 |
-11 |
|
1.2.2 |
Safety Installation-L-14 |
1sum |
100% |
16-01-23 |
22-01-23 |
21-01-23 |
26-01-23 |
-4 |
|
1.2.3 |
Steel Fabrication Work L-14 |
1sum |
100% |
23-01-23 |
05-02-23 |
26-01-23 |
13-02-23 |
-8 |
|
1.2.4 |
Civil Work L-14 |
1sum |
100% |
06-02-23 |
12-02-23 |
21-01-23 |
13-02-23 |
-1 |
|
1.3.1 |
Outer Glass Removal-L-14 |
1sum |
100% |
13-02-23 |
19-02-23 |
26-01-23 |
31-01-23 |
19 |
|
1.3.2 |
Safety Installation-L-15 |
1sum |
100% |
20-02-23 |
26-02-23 |
26-01-23 |
02-02-23 |
24 |
|
1.3.3 |
Steel Fabrication L-15 |
1sum |
100% |
27-02-23 |
12-03-23 |
13-02-23 |
20-02-23 |
20 |
|
1.3.4 |
Civil work L-15 |
1sum |
100% |
13-03-23 |
19-03-23 |
22-02-23 |
25-02-23 |
22 |
|
2.1.01 |
L-16-Scaffolding and Safety Instal |
1sum |
100% |
20-03-23 |
26-03-23 |
27-02-23 |
18-03-23 |
8 |
|
2.1.02 |
L-16-Podema Board removin |
1sum |
100% |
27-03-23 |
31-03-23 |
20-03-23 |
09-04-23 |
-9 |
|
2.1.03 |
L-16-Old Column Concrete Demolis |
1sum |
100% |
01-04-23 |
05-04-23 |
20-03-23 |
29-03-23 |
7 |
|
2.1.04 |
L-16-Dropwall old concrete dismant |
1sum |
100% |
01-04-23 |
05-04-23 |
29-03-23 |
31-03-23 |
5 |
|
2.1.05 |
L-16-Col Beam Ext-Re-bar Fabricat |
1sum |
100% |
06-04-23 |
10-04-23 |
01-04-23 |
18-04-23 |
-8 |
|
2.1.06 |
L-16-Col Beam Ext-Shutterin |
1sum |
100% |
11-04-23 |
13-04-23 |
05-04-23 |
18-04-23 |
-5 |
|
2.1.07 |
L-16-Col Beam Ext-Concretin |
1sum |
100% |
14-04-23 |
14-04-23 |
05-04-23 |
19-04-23 |
-5 |
|
2.1.08 |
L-16-Drop Wall-Re-bar Work |
1sum |
0% |
02-05-23 |
04-05-23 |
|
|
0 |
|
2.1.09 |
l-16-Drop Wall-Shuttering |
1sum |
5% |
30-04-23 |
06-05-23 |
29-04-23 |
29-04-23 |
7 |
|
2.1.10 |
L-16-Dropwall Concreting |
1sum |
0% |
07-05-23 |
08-05-23 |
|
|
0 |
|
2.2.1 |
L-17-Scaffolding and Safety Install |
1sum |
0% |
15-04-23 |
01-05-23 |
|
|
0 |
Started |
2.2.2 |
L-17-Podema Board removing |
1sum |
0% |
02-05-23 |
06-05-23 |
|
|
0 |
|
2.2.3 |
L-17-Old Concrete Demolish |
1sum |
0% |
07-05-23 |
11-05-23 |
|
|
0 |
|
2.2.4 |
L-17-Col Beam Ext-Re-bar Fabricatn |
1sum |
0% |
12-05-23 |
16-05-23 |
|
|
0 |
|
2.2.5 |
L-17-Col Beam Ext-Shuttering |
1sum |
0% |
17-05-23 |
19-05-23 |
|
|
0 |
|
2.2.6 |
L-17-Col Beam Ext-Concreting |
1sum |
0% |
20-05-23 |
20-05-23 |
|
|
0 |
|
Site Photographs |
|
on 21-01-23 |
|
on 21-01-23 |
|
|
|
Chemical Bolt fixing on 26-01-23 |
|
on 26-01-23 |
|
|
|
on 31-01-23 |
|
on 31-01-23 |
|
|
|
South-side safety tray & net complete on 2-02-23 |
|
I-Joist Lifting on 16th Floor on 2-02-23 |
|
No Helmet, safety shoe & Hand gloves (right-side) |
|
Shifting from L-17 to 15 on 5-02-23 |
|
Keeping L-15 on 5-02-23 |
|
|
|
Level-14-Steel Work on 8-02-23 |
|
on 8-02-23 |
|
|
|
Lavel-14 Decking Slab complete on 13-02-23 |
|
Level-14 Slab concrete completed on 13-02-23 |
|
|
|
L-15 Anchor bolt drilling on 15-02-23 |
|
L-15 Anchor bolt drilling on 15-02-23 |
|
|
|
L-15-Steel Fabrication on 18-02-23 |
|
L-15-Steel Fabrication on 18-02-23 |
|
|
|
Level-15 Decking Slab fixing on 20-02-23 |
|
L-15 Decking Slab fixing on 20-02-23 |
|
|
|
Old Slab concrete chipping on 22-02-23 |
|
For Re-bar lapping & welding on 22-02-23 |
|
|
|
Level-15-Ext Slab Concreting on 25-02-23 |
|
Level-15-Ext Slab Concreting on 25-02-23 |
|
|
|
L-14-Ext Decking and Beam Painting on 27-02-23 |
|
L-14-Ext Decking and Beam Painting on 27-02-23 |
|
|
|
L-16-Safety Installation on 1-03-23 |
|
L-16-Safety Installation on 1-03-23 |
|
|
|
L-16-Safety installation on 4-03-23 |
|
L-16-Safety installation on 4-03-23 |
|
|
|
L-16-Safety installation on 6-03-23 |
|
L-16-Safety installation on 6-03-23 |
|
|
|
L-16 Safety installation on 9-03-23 |
|
L-16-Safety installation on 9-03-23 |
|
|
|
L-16-West side safety work on 12-03-23 |
|
L-16-West side safety work on 12-03-23 |
|
|
|
L-16-West side safety net hanging on 14-03-23 |
|
L-16-West side safety net hanging on 14-03-23 |
|
|
|
L-16-West side safety net hanging on 15-03-23 |
|
L-16-West side safety net hanging on 15-03-23 |
|
|
|
L-16-Safety installation on 18-03-23 |
|
L-16-Safety installation on 18-03-23 |
|
|
|
L-16 Scaffolding on 20-03-23 |
|
L-16-Scaffolding on 20-03-23 |
|
|
|
L-16-Old concrete removing on 22-03-23 |
|
L-16-Old concrete removing on 22-03-23 |
|
|
|
L-16-Existing Column top dismantling on 27-03-23 |
|
L-16-Existing Column top dismantling on 27-03-23 |
|
|
|
L-16-Dropwall old concrete dismantling on 29-03-23 |
|
L-16-Dropwall old concrete dismantling on 29-03-23 |
|
|
|
L-17-Slab chpping on 30-03-23 |
|
L-17-Slab chpping on 30-03-23 |
|
|
|
L-16-Scaffolding on 31-03-23 |
|
L-16-Scaffolding on 31-03-23 |
|
|
|
L-16-Column Stirrups making on 1-04-23 |
|
L-16-Scaffolding on 1-04-23 |
|
|
|
L-16-Column Stirrups making on 2-04-23 |
|
L-16-Re-bar fixing on 2-04-23 |
|
|
|
L-16-Column Re-bar on 5-04-23 |
|
L-16-Column concrete mixing on 5-04-23 |
|
|
|
L-16-Column Shuttering on 9-04-23 |
|
L-16-Column Re-bar Work on 9-04-23 |
|
|
|
L-16-Column shuttering on 11-04-23 |
|
L-16-Column concreting on 11-04-23 |
|
|
|
L-16-Column shuttering on 13-04-23 |
|
L-16-Column concreting on 13-04-23 |
|
|
|
L-16-Beam bottom shuttering on 15-04-23 |
|
L-16-Beam Re-bar fabrication on 15-04-23 |
|
|
|
L-16-Beam shuttering on 18-04-23 |
|
L-16-Beam shuttering on 18-04-23 |
|
|
|
L-16-Column curing chemical applying on 19-04-23 |
|
L-16-Beam concreting complete on 19-04-23 |
|
|
|
L-16-Beam Shutter removing on 29-04-23 |
|
L-16-Drop Wall Shuttering on 29-04-23 |
Work stopped 21-28 Apr due to Eid Vacation |
|