DAILY PROGRES REPORT |
Project: | Cityscape Tower Col Beam Ext-L-14-17 | Project Code: | 62 | Date | 29-April-2023 | ||
Client: | Cityscape | Report | 037 | Day | Saturday | ||
Contractor: | Cityscape International Ltd. | Climate | Sunny | ||||
Temperature | 26-36C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Col-beam Ext-Mason | 2 |
02 | Col-beam Ext-Helper | 1 |
TOTAL | 3 |
WBS | Work Description | Progress as on: 29-April-2023 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
2.1.09 | l-16-Drop Wall-Shuttering | 1sum | 5 | 5 | 30-04-23 | 06-05-23 |
Site Photographs | |
L-16-Beam Shutter removing | L-16-Drop Wall Shuttering |
Site Description | |
Work stopped 21-28 Apr due to Eid Vacation | |
Site Instruction | |