WEEKY PROGRESS REPORT |
From 11-March-2023 to 18-March-2023 | ||||
Project Code: | 60 | Name: | Coffee Shop-Cityscape Tower GF | |
Client: | Cityscape | Contractor: | Cityscape International Ltd. |
Progress as on: 18-March-2023 | ||||||||
WBS | Work Description | |||||||
Total Quantity | Upto 11-03-23 | This Week | Total Done | Schedule Start | Schedule Finish | Avtual Finish | ||
07 | Outside Shed | 1sum | 92% | 8% | 100% | 22-12-22 | 01-01-23 | 18-03-23 |
Site Photographs | |
Coffee shop interior on 14-03-23 | Coffee shop interioron 14-03-23 |
Coffee shop outside BBQ shed on 18-03-23 | Coffee shop outside shed on 18-03-23 |