WEEKY PROGRESS REPORT

From 11-March-2023 to 18-March-2023
Project Code: 60Name:Coffee Shop-Cityscape Tower GF
Client: Cityscape Contractor:Cityscape International Ltd.
Progress as on: 18-March-2023
WBSWork Description
Total QuantityUpto 11-03-23This WeekTotal Done Schedule StartSchedule FinishAvtual Finish
07 Outside Shed 1sum 92% 8% 100% 22-12-22 01-01-23 18-03-23


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Coffee shop interior on 14-03-23Coffee shop interioron 14-03-23
Coffee shop outside BBQ shed on 18-03-23Coffee shop outside shed on 18-03-23