MONTHLY PROGRESS REPORT |
From 1-March-2023 to 18-March-2023 | ||||
Project Code: | 60 | Name: | Coffee Shop-Cityscape Tower GF | |
Client: | Cityscape | Contractor: | Cityscape International Ltd. |
Progress as on: 18-March-2023 | ||||||||
WBS | Work Description | |||||||
Total Quantity | Upto 28-02-23 | This Month | Total Done | Schedule Start | Schedule Finish | Actual Finish | ||
01 | French Door | 3nos | 99% | 1% | 100% | 22-12-22 | 03-01-23 | 06-03-23 |
02 | Arch Paneling | 1sum | 99% | 1% | 100% | 22-12-22 | 25-12-22 | 06-03-23 |
03 | Coffee and Breakfast Counter | 1sum | 98% | 2% | 100% | 22-12-22 | 29-12-22 | 04-03-23 |
07 | Outside Shed | 1sum | 80% | 20% | 100% | 22-12-22 | 01-01-23 | 18-03-23 |
Site Photographs | |
GF-Coffee Shop inter on 4-03-23 | GF-Coffee Shop interioron 4-03-23 |
BBQ Rustic tile fixing on 6-03-23 | Coffee shop interioron 6-03-23 |
Coffee shop outside shed sheeting on 9-03-23 | Coffee shop outside shed sheeting on 9-03-23 |
Coffee shop interior on 14-03-23 | Coffee shop interioron 14-03-23 |
Coffee shop outside BBQ shed on 18-03-23 | Coffee shop outside shed on 18-03-23 |