MONTHLY PROGRESS REPORT

From 1-March-2023 to 18-March-2023
Project Code: 60Name:Coffee Shop-Cityscape Tower GF
Client: Cityscape Contractor:Cityscape International Ltd.
Progress as on: 18-March-2023
WBSWork Description
Total QuantityUpto 28-02-23This MonthTotal Done Schedule StartSchedule FinishActual Finish
01 French Door 3nos 99% 1% 100% 22-12-22 03-01-23 06-03-23
02 Arch Paneling 1sum 99% 1% 100% 22-12-22 25-12-22 06-03-23
03 Coffee and Breakfast Counter 1sum 98% 2% 100% 22-12-22 29-12-22 04-03-23
07 Outside Shed 1sum 80% 20% 100% 22-12-22 01-01-23 18-03-23


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
GF-Coffee Shop inter on 4-03-23GF-Coffee Shop interioron 4-03-23
BBQ Rustic tile fixing on 6-03-23Coffee shop interioron 6-03-23
Coffee shop outside shed sheeting on 9-03-23Coffee shop outside shed sheeting on 9-03-23
Coffee shop interior on 14-03-23Coffee shop interioron 14-03-23
Coffee shop outside BBQ shed on 18-03-23Coffee shop outside shed on 18-03-23