DAILY PROGRES REPORT |
Project: | Coffee Shop-Cityscape Tower GF | Project Code: | 60 | Date | 18-March-2023 | ||
Client: | Cityscape | Report | 018 | Day | Saturday | ||
Contractor: | Cityscape International Ltd. | Climate | Sunny | ||||
Temperature | 23-29C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Coffee-Steel Engr | 1 |
02 | Coffee-Steel Worker | 3 |
TOTAL | 4 |
WBS | Work Description | Progress as on: 18-March-2023 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
07 | Outside Shed | 1sum | 5 | 100 | 22-12-22 | 01-01-23 |
Site Photographs | |
Coffee shop outside BBQ shed | Coffee shop outside shed |
Site Description | |
Site Instruction | |