WEEKY PROGRESS REPORT

From 14-January-2021 to 21-January-2021
Project Code: 49Name:Marriot-Nilgiri at Bandarban
Client: Contractor:Cityscape International Ltd.
Progress as on: 21-January-2021
WBSWork Description
Total QuantityUpto 14-01-21This WeekTotal Done Schedule StartSchedule FinishAvtual Finish
03.03.01 Soling n Plaster for PVC Water Tank 60% 20% 80% 15-01-21 22-01-21 20-01-21
03.06.02 Mobilization-Mechanics Shed-Frame W 30% 70% 100% 15-01-21 22-01-21 20-01-21
03.07 Mobilization-Grass Cutting-Roa 75% 15% 90% 28-12-20 26-01-21 07-01-21
03.08.03 Mobilization-Guest House-Footi 16nos 50% 50% 100% 08-01-21 12-01-21 15-01-21
03.08.04 Mobilization-Guest House-Pades 16nos 0% 100% 100% 10-01-21 13-01-21 19-01-21
03.08.05 Mobilization-Guest House-Grade Beam 107m 0% 65% 65% 12-01-21 17-01-21 21-01-21


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Column standing work on going at G.House on 14-01-21Footing & column casting work on going aon 14-01-21
Column standing work on going at G.House on 15-01-21Footing casting work on going at G.Houseon 15-01-21
Shuttering fitting work for short column on 16-01-21Short column casting work for guest houson 16-01-21
Shuttering fitting work for short column on 17-01-21Short column casting work for guest houson 17-01-21
MS rod cutting & binding work for grade on 19-01-21Brick solling work for water tank placeion 19-01-21
Soling for PVC Water Tank on 20-01-21Mechanics Shed Frame Workon 20-01-21
Rod binding work for grade beam at guest on 21-01-21Solling joint fillup & plaster work at won 21-01-21