Total Duration: |
16 |
days |
Total Working Days: |
14 |
Total Manpower: |
381 |
|
|
Planning Progress = 86.5% |
Acual Progress = 15.8% |
SPI: 0.18 |
Behind Schedule |
Progress as on: 21-January-2021
WBS |
Work Description |
Total Quantity |
Total Done |
Schedule Start
| Schedule Finish |
Actual Start |
Actual Finish |
Lead-Lag(day) |
Not Yet |
03.02 |
Mobilization-Material for Prelimina |
|
5% |
08-12-20 |
05-02-21 |
13-01-21 |
13-01-21 |
23 |
|
03.03.01 |
Soling n Plaster for PVC Water Tank |
|
80% |
15-01-21 |
22-01-21 |
19-01-21 |
20-01-21 |
2 |
|
03.06.02 |
Mobilization-Mechanics Shed-Frame W |
|
100% |
15-01-21 |
22-01-21 |
12-01-21 |
20-01-21 |
2 |
|
03.07 |
Mobilization-Grass Cutting-Roa |
|
90% |
28-12-20 |
26-01-21 |
05-01-21 |
07-01-21 |
19 |
|
03.08.01 |
Mobilization-Guest House-Layout |
130sqm |
100% |
06-01-21 |
06-01-21 |
06-01-21 |
06-01-21 |
0 |
|
03.08.02 |
Mobilization-Guest House-Excavation |
163cum |
100% |
07-01-21 |
10-01-21 |
07-01-21 |
12-01-21 |
-2 |
|
03.08.03 |
Mobilization-Guest House-Footi |
16nos |
100% |
08-01-21 |
12-01-21 |
12-01-21 |
15-01-21 |
-3 |
|
03.08.04 |
Mobilization-Guest House-Pades |
16nos |
100% |
10-01-21 |
13-01-21 |
16-01-21 |
19-01-21 |
-6 |
|
03.08.05 |
Mobilization-Guest House-Grade Beam |
107m |
65% |
12-01-21 |
17-01-21 |
19-01-21 |
21-01-21 |
-4 |
Completed |
03.08.06 |
Mobilization-Guest House-Floor Work |
130sqm |
0% |
18-01-21 |
20-01-21 |
|
|
0 |
Started |
03.08.07 |
Mobilization-Guest House-Column |
16nos |
0% |
21-01-21 |
24-01-21 |
|
|
0 |
|
03.08.08 |
Mobilization-Guest House-Brick-work |
268sqm |
0% |
24-01-21 |
30-01-21 |
|
|
0 |
|
03.08.09 |
Mobilization-Guest House-Tie Beam |
107m |
0% |
28-01-21 |
01-02-21 |
|
|
0 |
|
03.08.10 |
Mobilization-Guest House-Truss |
130sqm |
0% |
26-01-21 |
31-01-21 |
|
|
0 |
|
03.08.11 |
Mobilization-Guest House-San-ElePip |
1item |
0% |
31-01-21 |
01-02-21 |
|
|
0 |
|
03.08.12 |
Mobilization-Guest House-Grill-DrFm |
23nos |
0% |
30-01-21 |
31-01-21 |
|
|
0 |
|
03.08.13 |
Mobilization-Guest House-Plaster |
536sqm |
0% |
31-01-21 |
03-02-21 |
|
|
0 |
|
03.08.14 |
Mobilization-Guest House-Roof Sheet |
130sqm |
0% |
01-02-21 |
03-02-21 |
|
|
0 |
|
03.08.15 |
Mobilization-Guest House-Tile Work |
130sqm |
0% |
31-01-21 |
03-02-21 |
|
|
0 |
|
03.08.16 |
Mobilization-Guest House-Painting |
536sqm |
0% |
02-02-21 |
05-02-21 |
|
|
0 |
|
03.08.17 |
Mobilization-Guest House-Door-Windo |
23nos |
0% |
04-02-21 |
05-02-21 |
|
|
0 |
|
03.08.18 |
Mobilization-Guest House-San-Ele-Fi |
1item |
0% |
03-02-21 |
05-02-21 |
|
|
0 |
|
Site Photographs |
|
Guest House-Preparation for Layout on 5-01-21 |
|
Guest House-Preparation for Layout on 5-01-21 |
|
|
|
Guest House-Preparation for Layout on 6-01-21 |
|
Guest House-Preparation for Layout on 6-01-21 |
|
|
|
Guest House-Preparation for Layout on 7-01-21 |
|
Guest House-Preparation for Layout on 7-01-21 |
|
|
|
on 8-01-21 |
|
on 8-01-21 |
|
|
|
Guest House-Excavation on 9-01-21 |
|
Brick Carrying on 9-01-21 |
|
|
|
MS rod cutting & binding on 12-01-21 |
|
Plaster work for labour Shed on 12-01-21 |
|
|
|
Footing & column casting work on going on 13-01-21 |
|
Reached water tank at project on 13-01-21 |
|
|
|
Column standing work on going at G.House on 14-01-21 |
|
Footing & column casting work on going a on 14-01-21 |
|
|
|
Column standing work on going at G.House on 15-01-21 |
|
Footing casting work on going at G.House on 15-01-21 |
|
|
|
Shuttering fitting work for short column on 16-01-21 |
|
Short column casting work for guest hous on 16-01-21 |
|
|
|
Shuttering fitting work for short column on 17-01-21 |
|
Short column casting work for guest hous on 17-01-21 |
|
|
|
MS rod cutting & binding work for grade on 19-01-21 |
|
Brick solling work for water tank placei on 19-01-21 |
|
|
|
Soling for PVC Water Tank on 20-01-21 |
|
Mechanics Shed Frame Work on 20-01-21 |
|
|
|
Rod binding work for grade beam at guest on 21-01-21 |
|
Solling joint fillup & plaster work at w on 21-01-21 |
|
|