Return Main Menu

TOTAL PROGRES REPORT

From 5-January-2021 to 21-January-2021
Project Code: 49 Name: Marriot-Nilgiri at Bandarban
Client: Contractor:
Progress as on: 21-January-2021
Total Duration: 16 days Total Working Days: 14 Total Manpower: 381
Planning Progress = 86.5% Acual Progress = 15.8% SPI: 0.18 Behind Schedule
WBS Work Description
Total Quantity Total Done Schedule Start Schedule Finish Actual Start Actual Finish Lead-Lag(day) Not Yet
03.02 Mobilization-Material for Prelimina 5% 08-12-20 05-02-21 13-01-21 13-01-21 23
03.03.01 Soling n Plaster for PVC Water Tank 80% 15-01-21 22-01-21 19-01-21 20-01-21 2
03.06.02 Mobilization-Mechanics Shed-Frame W 100% 15-01-21 22-01-21 12-01-21 20-01-21 2
03.07 Mobilization-Grass Cutting-Roa 90% 28-12-20 26-01-21 05-01-21 07-01-21 19
03.08.01 Mobilization-Guest House-Layout 130sqm 100% 06-01-21 06-01-21 06-01-21 06-01-21 0
03.08.02 Mobilization-Guest House-Excavation 163cum 100% 07-01-21 10-01-21 07-01-21 12-01-21 -2
03.08.03 Mobilization-Guest House-Footi 16nos 100% 08-01-21 12-01-21 12-01-21 15-01-21 -3
03.08.04 Mobilization-Guest House-Pades 16nos 100% 10-01-21 13-01-21 16-01-21 19-01-21 -6
03.08.05 Mobilization-Guest House-Grade Beam 107m 65% 12-01-21 17-01-21 19-01-21 21-01-21 -4 Completed
03.08.06 Mobilization-Guest House-Floor Work 130sqm 0% 18-01-21 20-01-21 0 Started
03.08.07 Mobilization-Guest House-Column 16nos 0% 21-01-21 24-01-21 0
03.08.08 Mobilization-Guest House-Brick-work 268sqm 0% 24-01-21 30-01-21 0
03.08.09 Mobilization-Guest House-Tie Beam 107m 0% 28-01-21 01-02-21 0
03.08.10 Mobilization-Guest House-Truss 130sqm 0% 26-01-21 31-01-21 0
03.08.11 Mobilization-Guest House-San-ElePip 1item 0% 31-01-21 01-02-21 0
03.08.12 Mobilization-Guest House-Grill-DrFm 23nos 0% 30-01-21 31-01-21 0
03.08.13 Mobilization-Guest House-Plaster 536sqm 0% 31-01-21 03-02-21 0
03.08.14 Mobilization-Guest House-Roof Sheet 130sqm 0% 01-02-21 03-02-21 0
03.08.15 Mobilization-Guest House-Tile Work 130sqm 0% 31-01-21 03-02-21 0
03.08.16 Mobilization-Guest House-Painting 536sqm 0% 02-02-21 05-02-21 0
03.08.17 Mobilization-Guest House-Door-Windo 23nos 0% 04-02-21 05-02-21 0
03.08.18 Mobilization-Guest House-San-Ele-Fi 1item 0% 03-02-21 05-02-21 0


DAILY MANPOWER








CUMMULATIVE ACTUAL WORK PROGRESS








CUMMULATIVE PLAN WORK PROGRESS








CUMMULATIVE WORK PROGRESS








SCHEDULE AHEAD-BEHIND






Site Photographs
Guest House-Preparation for Layout on 5-01-21
Guest House-Preparation for Layout on 5-01-21
Guest House-Preparation for Layout on 6-01-21
Guest House-Preparation for Layout on 6-01-21
Guest House-Preparation for Layout on 7-01-21
Guest House-Preparation for Layout on 7-01-21
on 8-01-21
on 8-01-21
Guest House-Excavation on 9-01-21
Brick Carrying on 9-01-21
MS rod cutting & binding on 12-01-21
Plaster work for labour Shed on 12-01-21
Footing & column casting work on going on 13-01-21
Reached water tank at project on 13-01-21
Column standing work on going at G.House on 14-01-21
Footing & column casting work on going a on 14-01-21
Column standing work on going at G.House on 15-01-21
Footing casting work on going at G.House on 15-01-21
Shuttering fitting work for short column on 16-01-21
Short column casting work for guest hous on 16-01-21
Shuttering fitting work for short column on 17-01-21
Short column casting work for guest hous on 17-01-21
MS rod cutting & binding work for grade on 19-01-21
Brick solling work for water tank placei on 19-01-21
Soling for PVC Water Tank on 20-01-21
Mechanics Shed Frame Work on 20-01-21
Rod binding work for grade beam at guest on 21-01-21
Solling joint fillup & plaster work at w on 21-01-21