DAILY PROGRES REPORT

Project:Marriot-Nilgiri at Bandarban Project Code: 49 Date21-January-2021
Client: Report041 DayThursday
Contractor:Cityscape International Ltd. ClimateCloudy
Temperature13-27C
Manpower
SNDescriptionNos
01Cityscape-MN7
02Civil-Mason10
03Civil-Helper14
04Welding Mistry1
05Welding Helper1
TOTAL 33
WBSWork Description Progress as on: 21-January-2021
Total QtyToday Done (%)Total Done (%)StartFinish
03.08.05 Mobilization-Guest House-Grade Beam 107m 50 65 12-01-21 17-01-21
Site Photographs
Rod binding work for grade beam at guestSolling joint fillup & plaster work at w
Site Description
Site Instruction