Project: | Marriot-Nilgiri at Bandarban | Project Code: | 49 | Date | 21-January-2021 | ||
Client: | Report | 041 | Day | Thursday | |||
Contractor: | Cityscape International Ltd. | Climate | Cloudy | ||||
Temperature | 13-27C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Cityscape-MN | 7 |
02 | Civil-Mason | 10 |
03 | Civil-Helper | 14 |
04 | Welding Mistry | 1 |
05 | Welding Helper | 1 |
TOTAL | 33 |
WBS | Work Description | Progress as on: 21-January-2021 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
03.08.05 | Mobilization-Guest House-Grade Beam | 107m | 50 | 65 | 12-01-21 | 17-01-21 |
Site Photographs | |
Rod binding work for grade beam at guest | Solling joint fillup & plaster work at w |
Site Description | |