Return Main Menu

TOTAL PROGRES REPORT

From 27-January-2021 to 31-May-2021
Project Code: 56 Name: River Front Satellite City
Client: Sikder Group Contractor:
Progress as on: 31-May-2021
Total Duration: 124 days Total Working Days: 41 Total Manpower: 6176
Planning Progress = 100% Acual Progress = 83.2% SPI: 0.83 Behind Schedule
WBS Work Description
Total Quantity Total Done Schedule Start Schedule Finish Actual Start Actual Finish Lead-Lag(day) Not Yet
01.1 Take-over Site 100% 06-12-20 06-12-20 06-12-20 06-12-20 0
02.01 River-side Walkway-Side Wall 835m 100% 07-12-20 04-02-21 27-01-21 05-02-21 -1
02.02 River-side Walkway-Filling 835m 100% 10-12-20 07-02-21 27-01-21 05-02-21 2
02.03 River-side Walkway-Soling 5007sqm 100% 13-12-20 10-02-21 27-01-21 05-02-21 5
02.04 River-side Walkway-CC 5007sqm 100% 16-12-20 13-02-21 28-01-21 05-02-21 8
02.06 River-side Boundary-Bottom Beam 835m 100% 07-12-20 04-02-21 27-01-21 01-02-21 3
02.07 River-side Boundary-Bot Column 89nos 100% 08-12-20 05-02-21 27-01-21 01-02-21 4
02.08 River-side Boundary-Brick Work 835m 100% 10-12-20 07-02-21 27-01-21 01-02-21 6
02.09 River-side Boundary-Top Beam 835m 100% 12-12-20 09-02-21 27-01-21 01-02-21 8
02.10 River-side Boundary-Top Column 89nos 100% 14-12-20 11-02-21 27-01-21 01-02-21 10
02.11 River-side Boundary-Grill 835m 95% 21-12-20 18-02-21 05-02-21 08-02-21 10 Completed
02.12 River-side Boundary-Column Capital 89nos 100% 21-12-20 18-02-21 27-01-21 01-02-21 17
02.13 River-side Boundary-Bontile Texture 835m 95% 28-12-20 25-02-21 28-01-21 03-04-21 -37 Completed
02.14 River-side Boundary-Grill Enamel Pa 835m 95% 14-02-21 28-02-21 08-02-21 08-03-21 -8 Completed
03.01 40ft Road-Layout 100% 12-12-20 18-12-20 18-12-20 18-12-20 0
03.02 40ft Road-Filling Work 100% 19-12-20 25-02-21 25-02-21 25-02-21 0
03.03 40 feet Road Levelling and Dressing 886m 18% 26-02-21 11-03-21 10-02-21 31-03-21 -20 Completed
04.01 12 ft Inner Road-Filling m 80% 20-12-20 12-02-21 05-02-21 28-02-21 -16 Completed
04.02 12 Ft Inner Road-Soling sqm 60% 21-12-20 13-02-21 27-01-21 08-02-21 5 Completed
04.03 12 ft Inner Road-CC sqm 60% 22-12-20 14-02-21 05-02-21 08-02-21 6 Completed
05.01 Outside Plaster-Building-B 10% 26-01-21 25-02-21 27-01-21 29-01-21 27 Completed
05.06 Outside Plaster-Building-J 60% 11-01-21 09-02-21 28-01-21 28-01-21 12 Completed
05.09 Outside Plaster-Building-M 60% 11-01-21 09-02-21 01-02-21 01-02-21 8 Completed
05.10 Outside Plaster-Building-N 86% 11-01-21 09-02-21 29-01-21 31-05-21 -111 Completed
05.11 Outside Plaster-Building-Q 91% 18-01-21 16-02-21 29-01-21 09-05-21 -82 Completed
05.12 Outside Plaster-Building-R 95% 18-01-21 16-02-21 29-01-21 01-05-21 -74 Completed
06.01.1 Mock-up Flat-GF-Brick Flat Soling 100% 01-01-21 05-01-21 05-01-21 05-01-21 0
06.01.2 Mock-up Flat-Ground Floor-CC 100% 03-01-21 07-01-21 07-01-21 07-01-21 0
06.02 Mock-up Flat-Dismantling Work 100% 01-01-21 21-01-21 27-01-21 27-01-21 -6
06.03 Mock-up Flat-Const Joint & Extensn 100% 27-01-21 31-01-21 29-01-21 05-02-21 -5
06.04.1 Mock-up Flat-Brick Work 95% 17-01-21 31-01-21 29-01-21 05-02-21 -5 Completed
06.04.2 Mock-up Flat-Plaster 87% 07-01-21 10-02-21 18-02-21 25-02-21 -15 Completed
06.06.2 Mock-up Flat-Elect Conceal 85% 15-01-21 31-01-21 29-01-21 08-02-21 -8 Completed
07.01 New Mosque-Pile Work 100% 07-12-20 31-12-20 31-12-20 31-12-20 0
07.02 New Mosque-Excavation n Pile head b 100% 23-12-20 31-01-21 31-01-21 31-01-21 0
07.03 New Mosque-Mat 790m2 100% 20-01-21 08-02-21 08-02-21 08-02-21 0
07.04.1 Mosque-Basement-RW,Column, Stair 100% 09-02-21 09-03-21 09-03-21 09-03-21 0
07.04.2 Mosque-Ground Floor Slab 790m2 100% 10-03-21 21-03-21 21-03-21 21-03-21 0
07.04.3 Mosque-Basement-Plaster Work 5% 10-04-21 09-05-21 14-04-21 14-04-21 25 Completed
07.04.4 Mosque-Basement Tile work 790m2 52% 10-04-21 19-04-21 11-04-21 31-05-21 -42 Completed
07.04.5 Mosque-Basement-Ancillary Works 30% 16-04-21 25-05-21 16-04-21 04-05-21 21 Completed
07.05.1 Mosque-Ground Floor-Column 100% 22-03-21 02-04-21 24-03-21 28-03-21 5
07.05.2 Mosque-Ground Floor-Roof Slab 790m2 100% 03-04-21 09-04-21 27-03-21 06-04-21 3
07.05.3 Mosque-Ground Floor-Stair 6nos 83% 22-03-21 15-04-21 25-03-21 11-04-21 4 Completed
07.05.4 Mosque-Ground Floor-Ancillary works 30% 16-04-21 25-05-21 14-04-21 31-05-21 -6 Completed
07.06.1 Mosque- 20ft Connecting Road-Fillin 5% 01-04-21 14-04-21 31-03-21 31-03-21 14 Completed
07.07.1 Mosque-1st Floor-Column 15% 10-04-21 21-04-21 18-04-21 24-04-21 -3 Completed
08.1 Landing Station-Excavation 5% 22-05-21 04-06-21 22-05-21 22-05-21 13


DAILY MANPOWER








CUMMULATIVE ACTUAL WORK PROGRESS








CUMMULATIVE PLAN WORK PROGRESS








CUMMULATIVE WORK PROGRESS








SCHEDULE AHEAD-BEHIND






Site Photographs
Inner Road CC Work on 27-01-21
Scaffoloding for Outside Plaster-Buildin on 27-01-21
Building-J outside plastering on 28-01-21
Riverside walkway CC work on 28-01-21
Building- outside plastering on 29-01-21
Scaffolding for outside plastering Build on 29-01-21
Riverside Bontile Rectification & Lighti on 1-02-21
Lanscape Lighting on 1-02-21
Boundary Grill Painting on 5-02-21
Out-side Plaster Work on 5-02-21
Riverside Boundary Fencing on 8-02-21
Building Outside Painting on 8-02-21
40 ft Road Levelling and dressing on 10-02-21
River Side Boundary Fencing on 10-02-21
on 18-02-21
on 18-02-21
Project was closed 11-17 Feb 2021 due to Honourable Z.H. Sikder death
Mock-up-Exterior Sand Stone Fixing on 25-02-21
Electrical Conduit Consealing on 25-02-21
40 ft Road Dressing and Levelling on 28-02-21
12 ft Road Filling on 28-02-21
40 ft Road Dressing and Levelling on 1-03-21
Building Outside Plastering on 1-03-21
Building Outside Plastering on 8-03-21
Riverside Boundary Fencing on 8-03-21
Breifing instruction before Concreting on 21-03-21
Mosque Ground Floor Slab Concreting on 21-03-21
Cityscape Security Training on 24-03-21
Mosque GF Column 2nd Lift Re-bar Work on 24-03-21
Mosque-GF Column Work on 25-03-21
Mosque-GF-Stair Case Foundation Work on 25-03-21
Mosque 1st Floor Slab Shuttering on 27-03-21
Mosque Ground Floor Stair Concreting on 27-03-21
Mosque 1st Floor Slab Shuttering on 28-03-21
Mosque Ground Floor Stair Concreting on 28-03-21
Mosque-20ft Connecting Road-Filling on 31-03-21
Mosque-Night Shift Work on 31-03-21
Mosque 1st Floor Slab Re-bar Work on 3-04-21
Mosque Building in Construction on 3-04-21
Mosque 1st Floor Slab Concreting on 6-04-21
Mosque 1st Floor Slab Concreting on 6-04-21
Mosque-Esatside Stair Case on 11-04-21
Mosque-Basement Tiles Work on 11-04-21
on 12-04-21
Mosque-Basement-Tile Work on 12-04-21
Mosque under Construction on 13-04-21
Mosque-Basement-Tile Work on 13-04-21
Mosque-Basment Plaster Work on 14-04-21
Mosque-Ground Floor Ancilary Works on 14-04-21
Out-side Plastering on 15-04-21
Mosque in Construction on 15-04-21
Mosque-Basement-Tile Work on 16-04-21
Mosque-Basement-Ancliary Work on 16-04-21
Out-side Plastering on 17-04-21
Mosque-Basement-Ancliary Work on 17-04-21
Out-side Plastering on 19-04-21
Mosque-1st Floor Column Re-bar Work on 19-04-21
Out-side Plastering on 20-04-21
Out-side Plaster Work on 20-04-21
Out-side Plastering on 22-04-21
Mosque-Ground Floor-Roof Slab de-shutter on 22-04-21
Mosque-Gr.Floor Roof De-shuttering on 24-04-21
Mosque Building in Construction on 24-04-21
Mosque-Stair Case on 25-04-21
1st Floor Roof-De-shuttering on 25-04-21
Mosque-1st Floor-Column Shuttering on 26-04-21
Mosque-Basement-Ancliary Work on 26-04-21
Out-side Plastering on 28-04-21
Drop Wall Shuttering on 28-04-21
Drop Wall Shuttering on 1-05-21
Out-side Plaster Work on 1-05-21
Out-side Plastering on 2-05-21
Mosque-Gr./1st Floor-Ancillary Works on 2-05-21
Mosque-Gr/1st Floor-Anciliary works on 4-05-21
Out-side Plaster Work on 4-05-21
Bulding-Q-Out-side Plastering on 9-05-21
Bulding-Q-Out-side Plastering on 9-05-21
Landing Station-Excavation on 22-05-21
Landing Station-Excavation on 22-05-21
Project Closed 10-21 May due to Eid-ul Fitre Vacation
on 30-05-21
on 30-05-21
Mosque-Basement-Tile Work on 31-05-21
Mosque-Ground Floor-Ancillary Works on 31-05-21