Return Main Menu

DAILY PROGRES REPORT

Project:River Front Satellite City Project Code: 56 Date31-May-2021
Client: Sikder Group Report042 DayMonday
Contractor:Cityscape International Ltd. ClimateSunny
Temperature26-29C
Manpower
SNDescriptionNos
01Cityscape-RSC44
03CIL-Worker3
26Cityscape Security21
27Mason/ Mistry11
28Mason/ Mistry Helper10
TOTAL 89
WBSWork Description Progress as on: 31-May-2021
Total QtyToday Done (%)Total Done (%)StartFinish
05.10 Outside Plaster-Building-N 1 86 11-01-21 09-02-21
07.04.4 Mosque-Basement Tile work 790m2 5 52 10-04-21 19-04-21
07.05.4 Mosque-Ground Floor-Ancillary works 5 30 16-04-21 25-05-21
Site Photographs
Mosque-Basement-Tile WorkMosque-Ground Floor-Ancillary Works
Site Description
Site Instruction