DAILY PROGRES REPORT |
Project: | River Front Satellite City | Project Code: | 56 | Date | 31-May-2021 | ||
Client: | Sikder Group | Report | 042 | Day | Monday | ||
Contractor: | Cityscape International Ltd. | Climate | Sunny | ||||
Temperature | 26-29C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Cityscape-RSC | 44 |
03 | CIL-Worker | 3 |
26 | Cityscape Security | 21 |
27 | Mason/ Mistry | 11 |
28 | Mason/ Mistry Helper | 10 |
TOTAL | 89 |
WBS | Work Description | Progress as on: 31-May-2021 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
05.10 | Outside Plaster-Building-N | 1 | 86 | 11-01-21 | 09-02-21 | ||
07.04.4 | Mosque-Basement Tile work | 790m2 | 5 | 52 | 10-04-21 | 19-04-21 | |
07.05.4 | Mosque-Ground Floor-Ancillary works | 5 | 30 | 16-04-21 | 25-05-21 |
Site Photographs | |
Mosque-Basement-Tile Work | Mosque-Ground Floor-Ancillary Works |
Site Description | |
Site Instruction | |