WEEKY PROGRESS REPORT |
From 24-May-2021 to 31-May-2021 | ||||
Project Code: | 56 | Name: | River Front Satellite City | |
Client: | Sikder Group | Contractor: | Cityscape International Ltd. |
Progress as on: 31-May-2021 | ||||||||
WBS | Work Description | |||||||
Total Quantity | Upto 24-05-21 | This Week | Total Done | Schedule Start | Schedule Finish | Avtual Finish | ||
05.10 | Outside Plaster-Building-N | 84% | 2% | 86% | 11-01-21 | 09-02-21 | 31-05-21 | |
07.04.4 | Mosque-Basement Tile work | 790m2 | 47% | 5% | 52% | 10-04-21 | 19-04-21 | 31-05-21 |
07.05.4 | Mosque-Ground Floor-Ancillary works | 25% | 5% | 30% | 16-04-21 | 25-05-21 | 31-05-21 |
Site Photographs | |
on 30-05-21 | on 30-05-21 |
Mosque-Basement-Tile Work on 31-05-21 | Mosque-Ground Floor-Ancillary Workson 31-05-21 |