WEEKY PROGRESS REPORT

From 24-May-2021 to 31-May-2021
Project Code: 56Name:River Front Satellite City
Client: Sikder Group Contractor:Cityscape International Ltd.
Progress as on: 31-May-2021
WBSWork Description
Total QuantityUpto 24-05-21This WeekTotal Done Schedule StartSchedule FinishAvtual Finish
05.10 Outside Plaster-Building-N 84% 2% 86% 11-01-21 09-02-21 31-05-21
07.04.4 Mosque-Basement Tile work 790m2 47% 5% 52% 10-04-21 19-04-21 31-05-21
07.05.4 Mosque-Ground Floor-Ancillary works 25% 5% 30% 16-04-21 25-05-21 31-05-21


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
on 30-05-21on 30-05-21
Mosque-Basement-Tile Work on 31-05-21Mosque-Ground Floor-Ancillary Workson 31-05-21