Progress as on: 31-May-2021 |
WBS | Work Description |
Total Quantity | Upto 30-04-21 | This Month | Total Done |
Schedule Start | Schedule Finish | Actual Finish |
05.10 |
Outside Plaster-Building-N |
|
84% |
2% |
86% |
11-01-21 |
09-02-21 |
31-05-21 |
05.11 |
Outside Plaster-Building-Q |
|
90% |
1% |
91% |
18-01-21 |
16-02-21 |
09-05-21 |
05.12 |
Outside Plaster-Building-R |
|
94% |
1% |
95% |
18-01-21 |
16-02-21 |
01-05-21 |
07.04.4 |
Mosque-Basement Tile work |
790m2 |
47% |
5% |
52% |
10-04-21 |
19-04-21 |
31-05-21 |
07.04.5 |
Mosque-Basement-Ancillary Works |
|
20% |
10% |
30% |
16-04-21 |
25-05-21 |
04-05-21 |
07.05.4 |
Mosque-Ground Floor-Ancillary works |
|
15% |
15% |
30% |
16-04-21 |
25-05-21 |
31-05-21 |
08.1 |
Landing Station-Excavation |
|
0% |
5% |
5% |
22-05-21 |
04-06-21 |
22-05-21 |
Site Photographs |
| |
Drop Wall Shuttering on 1-05-21 | Out-side Plaster Workon 1-05-21 |
|
|
| |
Out-side Plastering on 2-05-21 | Mosque-Gr./1st Floor-Ancillary Workson 2-05-21 |
|
|
| |
Mosque-Gr/1st Floor-Anciliary works on 4-05-21 | Out-side Plaster Workon 4-05-21 |
|
|
| |
Bulding-Q-Out-side Plastering on 9-05-21 | Bulding-Q-Out-side Plasteringon 9-05-21 |
|
|
| |
Landing Station-Excavation on 22-05-21 | Landing Station-Excavationon 22-05-21 |
Project Closed 10-21 May due to Eid-ul Fitre Vacation |
|
| |
on 30-05-21 | on 30-05-21 |
|
|
| |
Mosque-Basement-Tile Work on 31-05-21 | Mosque-Ground Floor-Ancillary Workson 31-05-21 |
|
|