WEEKY PROGRESS REPORT |
From 16-November-2024 to 22-November-2024 | ||||
Project Code: | 31 | Name: | New Hope Agrotech-Munshiganj | |
Client: | New Hope Agrotech BD Ltd. | Contractor: | Sarker Steel Ltd. |
Progress as on: 22-November-2024 | ||||||||
WBS | Work Description | |||||||
Total Quantity | Upto 15-11-24 | This Week | Total Done | Schedule Start | Schedule Finish | Avtual Finish | ||
04.06 | Basement Wall | 3nos | 86% | 14% | 100% | 30-10-24 | 18-11-24 | 16-11-24 |
04.08 | Anchor Bolt setting | 84nos | 81% | 19% | 100% | 09-11-24 | 18-11-24 | 18-11-24 |
04.09 | Foundation Beam | 32gap | 69% | 31% | 100% | 07-11-24 | 21-11-24 | 18-11-24 |
04.11 | Foundation (Tank) Slab | 139m2 | 0% | 21% | 21% | 19-11-24 | 28-11-24 | 22-11-24 |
04.14 | Embedded Steel Parts | 1740kg | 0% | 50% | 50% | 21-11-24 | 28-11-24 | 21-11-24 |
04.15 | Tank wall water proofing membrain-SBS | 195m2 | 0% | 22% | 22% | 17-11-24 | 19-11-24 | 22-11-24 |
05.01 | Steel-Shop Drawing | 0 | 70% | 30% | 100% | 15-10-24 | 14-11-24 | 19-11-24 |
05.02 | Shop drawing Approval | 0 | 50% | 50% | 100% | 14-11-24 | 21-11-24 | 21-11-24 |
05.03.1 | Production-1st Floor | 55ton | 5% | 85% | 90% | 21-11-24 | 29-11-24 | 02-11-24 |
Site Photographs | |
Wall concreting on 16-11-24 | Foundation beam concreting on 16-11-24 |
Foundation beam bottom shuttering on 17-11-24 | Foundation beam rebar work on 17-11-24 |
Anchor bolt setting on 18-11-24 | Foundation beam concreting on 18-11-24 |
Tank slab shuttering on 19-11-24 | Tank slab shuttering on 19-11-24 |
Tank slab shuttering on 20-11-24 | Tank slab shuttering on 20-11-24 |
Embedded steel parts mobilized on 21-11-24 | Tank slab shuttering on 21-11-24 |
Tank slab shuttering on 22-11-24 | Tank wall water proofing membrain SBS fi on 22-11-24 |