WEEKY PROGRESS REPORT

From 16-November-2024 to 22-November-2024
Project Code: 31Name:New Hope Agrotech-Munshiganj
Client: New Hope Agrotech BD Ltd. Contractor:Sarker Steel Ltd.
Progress as on: 22-November-2024
WBSWork Description
Total QuantityUpto 15-11-24This WeekTotal Done Schedule StartSchedule FinishAvtual Finish
04.06 Basement Wall 3nos 86% 14% 100% 30-10-24 18-11-24 16-11-24
04.08 Anchor Bolt setting 84nos 81% 19% 100% 09-11-24 18-11-24 18-11-24
04.09 Foundation Beam 32gap 69% 31% 100% 07-11-24 21-11-24 18-11-24
04.11 Foundation (Tank) Slab 139m2 0% 21% 21% 19-11-24 28-11-24 22-11-24
04.14 Embedded Steel Parts 1740kg 0% 50% 50% 21-11-24 28-11-24 21-11-24
04.15 Tank wall water proofing membrain-SBS 195m2 0% 22% 22% 17-11-24 19-11-24 22-11-24
05.01 Steel-Shop Drawing 0 70% 30% 100% 15-10-24 14-11-24 19-11-24
05.02 Shop drawing Approval 0 50% 50% 100% 14-11-24 21-11-24 21-11-24
05.03.1 Production-1st Floor 55ton 5% 85% 90% 21-11-24 29-11-24 02-11-24


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Wall concreting on 16-11-24Foundation beam concreting on 16-11-24
Foundation beam bottom shuttering on 17-11-24Foundation beam rebar work on 17-11-24
Anchor bolt setting on 18-11-24Foundation beam concreting on 18-11-24
Tank slab shuttering on 19-11-24Tank slab shuttering on 19-11-24
Tank slab shuttering on 20-11-24Tank slab shuttering on 20-11-24
Embedded steel parts mobilized on 21-11-24Tank slab shuttering on 21-11-24
Tank slab shuttering on 22-11-24Tank wall water proofing membrain SBS fi on 22-11-24