DAILY PROGRES REPORT

Project:New Hope Agrotech-Munshiganj Project Code: 31 Date19-January-2025
Client: New Hope Agrotech BD Ltd. Report251 DaySunday
Contractor:Sarker Steel Ltd. ClimateSunny
Temperature14-26°C
Manpower
SNDescriptionNos
01Sarker-Staff2
02Steel Labor31
03Civil Labour6
07Sarker-Staff Night shift2
08Steel Labor-Night shift20
TOTAL 61
WBSWork Description Progress as on: 19-January-2025
Total QtyToday Done (%)Total Done (%)StartFinish
05.05.4 Checkered Plate install-4th Floor 0 2 92 26-12-24 27-12-24
05.06 Steel Stair, Canopy, Others 22ton 2 48 08-01-25 08-03-25