DAILY PROGRES REPORT |
Project: | New Hope Agrotech-Munshiganj | Project Code: | 31 | Date | 22-November-2024 | ||
Client: | New Hope Agrotech BD Ltd. | Report | 193 | Day | Friday | ||
Contractor: | Sarker Steel Ltd. | Climate | Sunny | ||||
Temperature | 19-29°C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Sarker-Staff | 1 |
02 | Steel Labor | 5 |
03 | Civil Labour | 15 |
07 | Sarker-Staff Night shift | 1 |
08 | Steel Labor-Night shift | 5 |
09 | Civil Labour-Night shift | 15 |
TOTAL | 42 |
WBS | Work Description | Progress as on: 22-November-2024 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
04.11 | Foundation (Tank) Slab | 139m2 | 5 | 21 | 19-11-24 | 28-11-24 | |
04.15 | Tank wall water proofing membrain-SBS | 195m2 | 22 | 22 | 17-11-24 | 19-11-24 | |
05.03.1 | Production-1st Floor | 55ton | 85 | 90 | 21-11-24 | 29-11-24 |
Site Photographs | |
Tank slab shuttering | Tank wall water proofing membrain SBS fi |
Site Description | |
Site Instruction | |