DAILY PROGRES REPORT |
Project: | New Hope Agrotech-Munshiganj | Project Code: | 31 | Date | 19-January-2025 | ||
Client: | New Hope Agrotech BD Ltd. | Report | 251 | Day | Sunday | ||
Contractor: | Sarker Steel Ltd. | Climate | Sunny | ||||
Temperature | 14-26°C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Sarker-Staff | 2 |
02 | Steel Labor | 31 |
03 | Civil Labour | 6 |
07 | Sarker-Staff Night shift | 2 |
08 | Steel Labor-Night shift | 20 |
TOTAL | 61 |
WBS | Work Description | Progress as on: 19-January-2025 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
05.05.4 | Checkered Plate install-4th Floor | 0 | 2 | 92 | 26-12-24 | 27-12-24 | |
05.06 | Steel Stair, Canopy, Others | 22ton | 2 | 48 | 08-01-25 | 08-03-25 |
Site Photographs | |
Steel bracing fixing | Stair Railing fixing |
Site Description | |
Site Instruction | |