Return Main Menu

DAILY PROGRES REPORT

Project:New Hope Agrotech-Munshiganj Project Code: 31 Date22-November-2024
Client: New Hope Agrotech BD Ltd. Report193 DayFriday
Contractor:Sarker Steel Ltd. ClimateSunny
Temperature19-29°C
Manpower
SNDescriptionNos
01Sarker-Staff1
02Steel Labor5
03Civil Labour15
07Sarker-Staff Night shift1
08Steel Labor-Night shift5
09Civil Labour-Night shift 15
TOTAL 42
WBSWork Description Progress as on: 22-November-2024
Total QtyToday Done (%)Total Done (%)StartFinish
04.11 Foundation (Tank) Slab 139m2 5 21 19-11-24 28-11-24
04.15 Tank wall water proofing membrain-SBS 195m2 22 22 17-11-24 19-11-24
05.03.1 Production-1st Floor 55ton 85 90 21-11-24 29-11-24
Site Photographs
Tank slab shuttering Tank wall water proofing membrain SBS fi
Site Description
Site Instruction