Progress as on: 19-January-2025 |
WBS | Work Description |
Total Quantity | Upto 31-12-24 | This Month | Total Done |
Schedule Start | Schedule Finish | Actual Finish |
04.12 |
Sub-base |
372m2 |
80% |
20% |
100% |
22-11-24 |
26-11-24 |
04-01-25 |
04.13 |
Ground Floor Slab |
372m2 |
30% |
70% |
100% |
26-11-24 |
28-11-24 |
04-01-25 |
05.03.4 |
Delivery-4th Floor |
46ton |
84% |
16% |
100% |
12-12-24 |
20-12-24 |
03-01-25 |
05.04.2 |
Steel Frame Install-2nd Floor |
54kg |
99% |
1% |
100% |
06-12-24 |
12-12-24 |
01-01-25 |
05.04.3 |
Steel Frame Install-3rd Floor |
46ton |
87% |
13% |
100% |
13-12-24 |
19-12-24 |
04-01-25 |
05.04.4 |
Steel Frame Install-4th Floor |
0 |
70% |
30% |
100% |
20-12-24 |
25-12-24 |
13-01-25 |
05.05.1 |
Decking Slab install-1st Floor Roof |
0 |
90% |
10% |
100% |
06-12-24 |
08-12-24 |
07-01-25 |
05.05.2 |
Checkered Plate install-2nd Floor Roof |
0 |
0% |
100% |
100% |
13-12-24 |
15-12-24 |
14-01-25 |
05.05.3 |
Decking Slab install-3rd Floor Roof |
0 |
0% |
100% |
100% |
20-12-24 |
22-12-24 |
03-01-25 |
05.05.4 |
Checkered Plate install-4th Floor |
0 |
0% |
92% |
92% |
26-12-24 |
27-12-24 |
19-01-25 |
05.06 |
Steel Stair, Canopy, Others |
22ton |
5% |
43% |
48% |
08-01-25 |
08-03-25 |
19-01-25 |
06.02 |
RCC Roof Slab-3rd Floor |
0 |
0% |
100% |
100% |
23-12-24 |
24-12-24 |
06-01-25 |
Site Photographs |
| |
Ground Floor RCC Slab Concreting on 1-01-25 | Ground Floor RCC Slab Concreting on 1-01-25 |
|
|
| |
Ground Floor Concrete Mechanical Troweli on 2-01-25 | Decking Slab Fixing on 2-01-25 |
|
|
| |
Re-bar Work on Decking Slab on 3-01-25 | Stair Fixing on 3-01-25 |
|
|
| |
Re-bar fixing on Decking slab on 4-01-25 | Ground floor Concreting on 4-01-25 |
|
|
| |
Steel structure installation on 5-01-25 | Steel structure installation on 5-01-25 |
|
|
| |
Steel structure installation on 6-01-25 | Re-bar fixing on decking slab on 6-01-25 |
|
|
| |
Steel structure installation on 7-01-25 | Concreting on Decking Slab-7.5m on 7-01-25 |
|
|
| |
Column Joint working on 8-01-25 | Stair case installation on 8-01-25 |
|
|
| |
Steel structure installation on 9-01-25 | Stair Railing welding on 9-01-25 |
|
|
| |
Civil Labour on 10-01-25 | Steel Worker on 10-01-25 |
|
|
| |
Civil Labour on 11-01-25 | Steel Worker on 11-01-25 |
|
|
| |
Steel nut-blot tightening on 12-01-25 | Welding steel structure on 12-01-25 |
|
|
| |
Steel structure installation on 13-01-25 | Steel bracing installation on 13-01-25 |
|
|
| |
Checkered plate lifting on 14-01-25 | Checkered plate fixing on 14-01-25 |
|
|
| |
Checkered plate fixing on 15-01-25 | Checkered plate welding on 15-01-25 |
|
|
| |
Steel structure installation on 16-01-25 | Steel stair installation on 16-01-25 |
|
|
| |
Stair Fixing on 17-01-25 | Checkered plate welding on 17-01-25 |
|
|
| |
Stair landing checkered plate fixing on 18-01-25 | Checkered plate welding on 18-01-25 |
|
|
| |
Steel bracing fixing on 19-01-25 | Stair Railing fixing on 19-01-25 |
|
|