Return Main Menu

MONTHLY PROGRESS REPORT

From 1-March-2025 to 28-March-2025
Project Code: 31Name:New Hope Agrotech-Munshiganj
Client: New Hope Agrotech BD Ltd. Contractor:Sarker Steel Ltd.
Progress as on: 28-March-2025
WBSWork Description
Total QuantityUpto 28-02-25This MonthTotal Done Schedule StartSchedule FinishActual Finish
07.1 AAC Block Work-Exterior 197m2 62% 18% 80% 21-01-25 05-02-25 24-03-25
07.2 AAC Block Work-Interior 195m2 0% 85% 85% 06-02-25 15-02-25 26-03-25
07.3 Plastering-Exterior Wall 416m2 0% 40% 40% 06-02-25 15-02-25 24-03-25
07.4 Plastering-Interior Wall 392m2 0% 30% 30% 16-02-25 25-02-25 22-03-25
07.6 Painting-Interior 392m2 0% 20% 20% 18-03-25 27-03-25 27-03-25
08.1 Electrical Works 1sum 0% 5% 5% 27-01-25 27-03-25 04-03-25
08.2 Water Works 1sum 0% 5% 5% 26-02-25 27-03-25 09-03-25
08.3 Fire Works 1sum 0% 10% 10% 26-02-25 27-03-25 28-03-25


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
AAC block work on 1-03-25Roof top water proofing membrane laying on 1-03-25
Site sheeting on 2-03-25AAC Block work on 2-03-25
AAC block work on 3-03-25Stone- chips for rooftop concreting on 3-03-25
Electrical Light fixing on 4-03-25Roof Top Rail fixing on 4-03-25
Exterior wall plastering on 5-03-25Lifting Roof top rail on 5-03-25
Welding work on 6-03-25Site sheeting on 6-03-25
Inter Plastering on 7-03-25Steel Structure paintimg on 7-03-25
Inside Plastering on 8-03-25Side Sheeting work on 8-03-25
Gutter mobilized on 9-03-25Plastering on 9-03-25
Interior AAC block work on 10-03-25Welding steel structure on 10-03-25
Interior AAC block work on 11-03-25Welding work on 11-03-25
Side sheeting on 12-03-25Welding work on 12-03-25
Side sheeting on 13-03-25Welding work on 13-03-25
Side sheeting on 14-03-25Side sheeting on 14-03-25
AAC block work on 15-03-25Side Sheeting work on 15-03-25
Side sheeting on 16-03-25Welding work on 16-03-25
Window delivered on 17-03-25Welding work on 17-03-25
Interior painting on 18-03-25Site sheeting on 18-03-25
Interior AAC block work on 19-03-25Checkered plate grinding on 19-03-25
Interior plastering on 20-03-25Ground floor re-bar work on 20-03-25
Interior plastering on 21-03-25Side sheeting on 21-03-25
Stair Railing fixing on 22-03-25Welding work on 22-03-25
Interior AAC block work on 23-03-25Interior painting work on 23-03-25
Exterior wall plastering on 24-03-25Roof top concreting on 24-03-25
Interior painting on 25-03-25Site sheeting on 25-03-25
Interior AAC block work on 26-03-25Site sheeting on 26-03-25
Interior painting on 27-03-25Interior painting on 27-03-25
Fire works on 28-03-25Cleaning works on 28-03-25