Return Main Menu

MONTHLY PROGRESS REPORT

From 1-November-2024 to 20-November-2024
Project Code: 31Name:New Hope Agrotech-Munshiganj
Client: New Hope Agrotech BD Ltd. Contractor:Sarker Steel Ltd.
Progress as on: 20-November-2024
WBSWork Description
Total QuantityUpto 31-10-24This MonthTotal Done Schedule StartSchedule FinishActual Finish
04.01 Excavation 1982m3 98% 2% 100% 08-10-24 06-11-24 02-11-24
04.02 Pile head breaking 79nos 96% 4% 100% 10-10-24 08-11-24 02-11-24
04.03.2 Pile Cap-Re-bar Work 19nos 63% 37% 100% 19-10-24 12-11-24 04-11-24
04.03.3 Pile Cap-Brick Shuttering 19nos 89% 11% 100% 20-10-24 13-11-24 03-11-24
04.03.4 Pile Cap-Concreting 19nos 79% 21% 100% 22-10-24 15-11-24 04-11-24
04.04.4 Raft-Re-bar Work 3nos 82% 18% 100% 12-11-24 15-11-24 06-11-24
04.04.7 Raft-Concreting 3nos 66% 34% 100% 15-11-24 15-11-24 06-11-24
04.04.8 Bracing Beam 7 gap 16% 84% 100% 09-11-24 15-11-24 03-11-24
04.05 Short Column 21nos 11% 89% 100% 25-10-24 18-11-24 12-11-24
04.06 Basement Wall 3nos 10% 90% 100% 30-10-24 18-11-24 16-11-24
04.07 Back filling 1982m3 7% 23% 30% 27-10-24 20-11-24 08-11-24
04.08 Anchor Bolt setting 84nos 0% 100% 100% 09-11-24 18-11-24 18-11-24
04.09 Foundation Beam 32gap 0% 100% 100% 07-11-24 21-11-24 18-11-24
04.11 Foundation (Tank) Slab 139m2 0% 12% 12% 19-11-24 28-11-24 20-11-24
05.02 Shop drawing Approval 0 0% 50% 50% 14-11-24 21-11-24 02-11-24
05.03.1 Production-1st Floor 0 0% 5% 5% 21-11-24 29-11-24 02-11-24


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Bracing beam- Column shuttering on 1-11-24Column concreting on 1-11-24
Pile head breaking on 2-11-24Bracing beam concreting on 2-11-24
Wall re-bar work on 3-11-24Pile cap concreting on 3-11-24
Pile cap Concreting on 4-11-24Column concreting on 4-11-24
Earth loading for backfilling on 5-11-24Column shuttering on 5-11-24
Wall shuttering on 6-11-24 on 6-11-24
Tank base concreting
Wall shuttering on 7-11-24Column re-bar work on 7-11-24
Backfilling on 8-11-24Foundation beam rebar work on 8-11-24
Wall shuttering on 9-11-24Foundation beam rebar inspection on 9-11-24
Foundation beam rebar work on 10-11-24Wall concreting on 10-11-24
Foundation beam shuttering on 11-11-24Foundation beam rebar work on 11-11-24
Foundation beam inspection before concre on 12-11-24Foundation beam concreting on 12-11-24
Anchor bolt setting on 13-11-24Foundation beam concreting on 13-11-24
Wall shuttering on 14-11-24Wall shuttering on 14-11-24
Wall shuttering on 15-11-24Foundation beam rebar work on 15-11-24
Wall concreting on 16-11-24Foundation beam concreting on 16-11-24
Foundation beam bottom shuttering on 17-11-24Foundation beam rebar work on 17-11-24
Anchor bolt setting on 18-11-24Foundation beam concreting on 18-11-24
Tank slab shuttering on 19-11-24Tank slab shuttering on 19-11-24
Tank slab shuttering on 20-11-24Tank slab shuttering on 20-11-24