TOTAL PROGRES REPORT

From 22-August-2024 to 22-November-2024
Project Code: 31 Name: New Hope Agrotech-Munshiganj
Client: New Hope Agrotech BD Ltd. Contractor: Sarker Steel Ltd.
Progress as on: 22-November-2024
Total Duration: 92 days Total Working Days: 90 Total Manpower: 3649
Planning Progress = 53% Acual Progress = 55% SPI: 1.04 Ahead Schedule
WBS Work Description
Total Quantity Total Done Schedule Start Schedule Finish Actual Start Actual Finish Lead-Lag(day) Not Yet
01 New Hope-Mobilization 0 100% 30-08-24 31-08-24 22-08-24 31-08-24 0
02 Dismatl Ware House,Floor,Wall 0 100% 01-09-24 10-09-24 27-08-24 10-09-24 0
03.1 Pile-Re-bar Mobilization 0 100% 07-09-24 09-09-24 04-09-24 05-09-24 4
03.2 Pile-Equipment Mobilization 0 100% 07-09-24 09-09-24 04-09-24 04-09-24 5
03.3 Mud Tank Construction 0 100% 07-09-24 11-09-24 09-09-24 11-09-24 0
03.4 Pile Boring 79nos 100% 12-09-24 11-10-24 12-09-24 30-09-24 11
03.5.1 Pile Load Test-PDA-Pile Development 3nos 100% 10-10-24 13-10-24 15-10-24 16-10-24 -3
03.5.2 Pile Load Test-PDA 3nos 100% 25-10-24 25-10-24 30-10-24 30-10-24 -5
03.5.3 Pile Integrity-PIT-Test 79nos 100% 23-10-24 25-10-24 20-10-24 25-10-24 0
03.6 Wooden Shore Piling 135nos. 100% 06-10-24 12-10-24 04-10-24 07-10-24 5
04.01 Excavation 1982m3 100% 08-10-24 06-11-24 01-10-24 02-11-24 4
04.02 Pile head breaking 79nos 100% 10-10-24 08-11-24 04-10-24 02-11-24 6
04.03.1 Pile Cap-Lean Concrete 19nos 100% 17-10-24 11-11-24 10-10-24 23-10-24 19
04.03.2 Pile Cap-Re-bar Work 19nos 100% 19-10-24 12-11-24 20-10-24 04-11-24 8
04.03.3 Pile Cap-Brick Shuttering 19nos 100% 20-10-24 13-11-24 13-10-24 03-11-24 10
04.03.4 Pile Cap-Concreting 19nos 100% 22-10-24 15-11-24 21-10-24 04-11-24 11
04.04.1 Raft-Lean Concrete 3Nos 100% 07-11-24 08-11-24 10-10-24 21-10-24 18
04.04.2 Raft-Water Proofing Membrane-SBS 3nos. 100% 08-11-24 11-11-24 22-10-24 25-10-24 17
04.04.3 Raft-Top Mortering 3nos 100% 11-11-24 12-11-24 22-10-24 25-10-24 18
04.04.4 Raft-Re-bar Work 3nos 100% 12-11-24 15-11-24 25-10-24 06-11-24 9
04.04.5 Raft-Side Brick Shuttering 3nos 100% 12-11-24 13-11-24 11-10-24 24-10-24 20
04.04.6 Raft-Side Water Proofing Membrane SBS 3nos 100% 13-11-24 15-11-24 22-10-24 25-10-24 21
04.04.7 Raft-Concreting 3nos 100% 15-11-24 15-11-24 28-10-24 06-11-24 9
04.04.8 Bracing Beam 7 gap 100% 09-11-24 15-11-24 31-10-24 03-11-24 12
04.05 Short Column 21nos 100% 25-10-24 18-11-24 26-10-24 12-11-24 6
04.06 Basement Wall 3nos 100% 30-10-24 18-11-24 27-10-24 16-11-24 2
04.07 Back filling 1982m3 40% 27-10-24 20-11-24 23-10-24 08-11-24 Completed
04.08 Anchor Bolt setting 84nos 100% 09-11-24 18-11-24 10-11-24 18-11-24 0
04.09 Foundation Beam 32gap 100% 07-11-24 21-11-24 07-11-24 18-11-24 3
04.11 Foundation (Tank) Slab 139m2 21% 19-11-24 28-11-24 19-11-24 22-11-24
04.14 Embedded Steel Parts 1740kg 50% 21-11-24 28-11-24 21-11-24 21-11-24
04.15 Tank wall water proofing membrain-SBS 195m2 22% 17-11-24 19-11-24 22-11-24 22-11-24 Completed
05.01 Steel-Shop Drawing 0 100% 15-10-24 14-11-24 06-10-24 19-11-24 -5
05.02 Shop drawing Approval 0 100% 14-11-24 21-11-24 02-11-24 21-11-24 0
05.03.1 Production-1st Floor 55ton 90% 21-11-24 29-11-24 02-11-24 02-11-24


DAILY MANPOWER








CUMMULATIVE ACTUAL WORK PROGRESS








CUMMULATIVE PLAN WORK PROGRESS








CUMMULATIVE WORK PROGRESS








SCHEDULE AHEAD-BEHIND






Site Photographs
Labor Shed Making on 22-08-24
Labour Shed Making on 22-08-24
Sarker Management Visit on 26-08-24
Steel Labour on 26-08-24
Workshop Sheet Removing on 27-08-24
Workshop Sheet Removing on 27-08-24
Sheet removing on 28-08-24
Sheet removing on 28-08-24
Sheet removing on 29-08-24
Sheet removing on 29-08-24
Steel beam cutting on 30-08-24
Steel beam removing on 30-08-24
Fencing framing on 31-08-24
Fencing framing on 31-08-24
Outside beam removing on 1-09-24
Inside fencing on 1-09-24
Fencing work on 2-09-24
Floor cutting on 2-09-24
Brick wall dismantling on 3-09-24
Brick wall dismatling on 3-09-24
Pile Re-bar mobillized on 4-09-24
Pile Equipment mobilized on 4-09-24
Material shifting by crane on 5-09-24
Pile re-bar mobilized on 5-09-24
Steel Labour on 6-09-24
Project Status on 6-09-24
Floor and Foundation Removal on 7-09-24
Pile Re-bar work on 7-09-24
Floor,foundatn, road,tank cutting,removi on 8-09-24
Piling equipment maintenance on 8-09-24
Old short column found durring excavatio on 9-09-24
Excavation for pile mud tank on 9-09-24
During excavation old pile found
Fencing after dismantling on 10-09-24
Pile mud tank brick work on 10-09-24
Ground breaking ceremony on 11-09-24
Pile mud tank complete on 11-09-24
Pile boring on 12-09-24
Pile concreting on 12-09-24
Pile cage length measuring on 13-09-24
Pile concreting on 13-09-24
Pile boring on 14-09-24
Concrete cube for test on 14-09-24
Pile boring on 15-09-24
Concrete cylinder for test on 15-09-24
Pile cage downing on 16-09-24
Road washing after pile finishing on 16-09-24
Pile boring length checking on 17-09-24
Pile concreting on 17-09-24
Pile reboring new location on 18-09-24
Pile concreting on 18-09-24
Pile no.15, Grid 1B relocated to a new location
Due to existence of old pile
Pile boring length checking on 19-09-24
Pile boring chisel repairing on 19-09-24
During boring old concrete-pipe found on 20-09-24
After Concrete-pipe removal boring resta on 20-09-24
During boring pile no.35 grid-2B
Old concrete-MS pipe found
During boring Obstacles found on 21-09-24
Pile concreting on 21-09-24
During boring pile no.36, grid-2B
Obstacles found
Pile boring length checking on 22-09-24
Pile concreting on 22-09-24
Rig shifting to Grid 1A on 23-09-24
Chisel broken due to obstacle on 23-09-24
During boring pile no.18 grid-1A
Chisel broken due to obstacles
Boring obstacle Old CC breaking on 24-09-24
Pile-57 concreting completed on 24-09-24
During boring pile no.53, grid-3B
Obstacle Old Concrete found
Pile cap re-bar dia checking on 25-09-24
Due to electrical line 1.5 m excavation on 25-09-24
Due to live electric line Grid-3
Excavating all pile point upto 1.5 m
Pile cap re-bar dia checking on 26-09-24
Bentonite received for pile boring on 26-09-24
Excavating for pile boring obstacles on 27-09-24
Making road for reading concrete truck on 27-09-24
Pile boring depth checking on 28-09-24
Piling rig shifting on 28-09-24
Pile no.47 boring length checking on 29-09-24
Piling rig setting on 29-09-24
Pile no.47 of grid 3C length 22m
Total 6 piles 22 m
Piling rig shifting on 30-09-24
Pile concreting on 30-09-24
All pile completed
Earth excavation on 1-10-24
Re-bar straighting on 1-10-24
Earth excavation on 2-10-24
Old base-column found during excavation on 2-10-24
During excavating old foundation with column found
In Grid-1 in between C and D
Obstacle RCC dismantling on 3-10-24
Earth excavation on 3-10-24
Dismantling RCC foundation found during excavation
Money and Time wastage
Pile Head breaking on 4-10-24
Wooden pile driving on 4-10-24
Due to rain work stopped
Old base breaking on 5-10-24
Earth excavation on 5-10-24
Wooden shore pile driving on 6-10-24
Earth Excavation on 6-10-24
Earth excavation on 7-10-24
Pile head breaking on 7-10-24
Excavated earth dumping on 8-10-24
Dismantling by hydraulic breaker on 8-10-24
Dismantling old foundation 17 m3
By Hydraulic hammer
Earth excavation on 9-10-24
Old base dismantling by hydraulic hammer on 9-10-24
Old base dismantling 11 m3 by hydraulic hammer
Pile Load Test-PDA-Pile Development on 10-10-24
Water Reservoir Base CC-Bottom on 10-10-24
Old base dismantling 4 m3 by hydraulic hammer
Dewatering on 11-10-24
Pile head breaking on 11-10-24
Checking before pile cap lean concreting on 12-10-24
Pile cap lean concreting on 12-10-24
Due to rain work started late
Pile cap side brick shuttering on 13-10-24
Earth excavation manually on 13-10-24
Wooden shore piling 14 nos.
Earth excavation on 14-10-24
Shoring on 14-10-24
Wooden pile driving 41 nos.
Inspection before CC at -5200 mm on 15-10-24
CC at level -5200 finished on 15-10-24
Excavation, brick-shuttering, steel shut on 16-10-24
Pile Cap Lean concreting on 16-10-24
Pile head breaking on 17-10-24
Water tank base brick wall shuttering on 17-10-24
Pile head breaking on 18-10-24
Pile cap lean concreting on 18-10-24
Pile Cap Brick Shuttering on 19-10-24
Pile Head Breaking on 19-10-24
PIT (Pile Integrity) testing on 20-10-24
Pile cap re-bar work on 20-10-24
Pile cap concreting on 21-10-24
Pile cap lean concreting on 21-10-24
Tank base water proofing membrane SBS wo on 22-10-24
Tank base top mortering on 22-10-24
Machine foundation re-bar inspection on 23-10-24
CC work on 23-10-24
Tank base brick wall shuttering on 24-10-24
Pile head breaking on 24-10-24
PIT test on 25-10-24
Pile cap concreting on 25-10-24
Column re-bar work on 26-10-24
Pile cap re-bar work on 26-10-24
Pile cap re-bar work on 27-10-24
Tank wall shuttering on 27-10-24
Raft re-bar inspection before concreting on 28-10-24
Raft concreting by Pump on 28-10-24
Earth excavation on 29-10-24
Raft re-bar work on 29-10-24
PDA test performing on 30-10-24
Raft re-bar work on 30-10-24
Column Shuttering on 31-10-24
Water proofing admixture adding in concr on 31-10-24
Bracing beam- Column shuttering on 1-11-24
Column concreting on 1-11-24
Pile head breaking on 2-11-24
Bracing beam concreting on 2-11-24
Wall re-bar work on 3-11-24
Pile cap concreting on 3-11-24
Pile cap Concreting on 4-11-24
Column concreting on 4-11-24
Earth loading for backfilling on 5-11-24
Column shuttering on 5-11-24
Wall shuttering on 6-11-24
on 6-11-24
Tank base concreting
Wall shuttering on 7-11-24
Column re-bar work on 7-11-24
Backfilling on 8-11-24
Foundation beam rebar work on 8-11-24
Wall shuttering on 9-11-24
Foundation beam rebar inspection on 9-11-24
Foundation beam rebar work on 10-11-24
Wall concreting on 10-11-24
Foundation beam shuttering on 11-11-24
Foundation beam rebar work on 11-11-24
Foundation beam inspection before concre on 12-11-24
Foundation beam concreting on 12-11-24
Anchor bolt setting on 13-11-24
Foundation beam concreting on 13-11-24
Wall shuttering on 14-11-24
Wall shuttering on 14-11-24
Wall shuttering on 15-11-24
Foundation beam rebar work on 15-11-24
Wall concreting on 16-11-24
Foundation beam concreting on 16-11-24
Foundation beam bottom shuttering on 17-11-24
Foundation beam rebar work on 17-11-24
Anchor bolt setting on 18-11-24
Foundation beam concreting on 18-11-24
Tank slab shuttering on 19-11-24
Tank slab shuttering on 19-11-24
Tank slab shuttering on 20-11-24
Tank slab shuttering on 20-11-24
Embedded steel parts mobilized on 21-11-24
Tank slab shuttering on 21-11-24
Tank slab shuttering on 22-11-24
Tank wall water proofing membrain SBS fi on 22-11-24