Site Photographs |
|
Labor Shed Making on 22-08-24 |
|
Labour Shed Making on 22-08-24 |
|
|
|
Sarker Management Visit on 26-08-24 |
|
Steel Labour on 26-08-24 |
|
|
|
Workshop Sheet Removing on 27-08-24 |
|
Workshop Sheet Removing on 27-08-24 |
|
|
|
Sheet removing on 28-08-24 |
|
Sheet removing on 28-08-24 |
|
|
|
Sheet removing on 29-08-24 |
|
Sheet removing on 29-08-24 |
|
|
|
Steel beam cutting on 30-08-24 |
|
Steel beam removing on 30-08-24 |
|
|
|
Fencing framing on 31-08-24 |
|
Fencing framing on 31-08-24 |
|
|
|
Outside beam removing on 1-09-24 |
|
Inside fencing on 1-09-24 |
|
|
|
Fencing work on 2-09-24 |
|
Floor cutting on 2-09-24 |
|
|
|
Brick wall dismantling on 3-09-24 |
|
Brick wall dismatling on 3-09-24 |
|
|
|
Pile Re-bar mobillized on 4-09-24 |
|
Pile Equipment mobilized on 4-09-24 |
|
|
|
Material shifting by crane on 5-09-24 |
|
Pile re-bar mobilized on 5-09-24 |
|
|
|
Steel Labour on 6-09-24 |
|
Project Status on 6-09-24 |
|
|
|
Floor and Foundation Removal on 7-09-24 |
|
Pile Re-bar work on 7-09-24 |
|
|
|
Floor,foundatn, road,tank cutting,removi on 8-09-24 |
|
Piling equipment maintenance on 8-09-24 |
|
|
|
Old short column found durring excavatio on 9-09-24 |
|
Excavation for pile mud tank on 9-09-24 |
During excavation old pile found |
|
|
Fencing after dismantling on 10-09-24 |
|
Pile mud tank brick work on 10-09-24 |
|
|
|
Ground breaking ceremony on 11-09-24 |
|
Pile mud tank complete on 11-09-24 |
|
|
|
Pile boring on 12-09-24 |
|
Pile concreting on 12-09-24 |
|
|
|
Pile cage length measuring on 13-09-24 |
|
Pile concreting on 13-09-24 |
|
|
|
Pile boring on 14-09-24 |
|
Concrete cube for test on 14-09-24 |
|
|
|
Pile boring on 15-09-24 |
|
Concrete cylinder for test on 15-09-24 |
|
|
|
Pile cage downing on 16-09-24 |
|
Road washing after pile finishing on 16-09-24 |
|
|
|
Pile boring length checking on 17-09-24 |
|
Pile concreting on 17-09-24 |
|
|
|
Pile reboring new location on 18-09-24 |
|
Pile concreting on 18-09-24 |
Pile no.15, Grid 1B relocated to a new location |
Due to existence of old pile |
|
Pile boring length checking on 19-09-24 |
|
Pile boring chisel repairing on 19-09-24 |
|
|
|
During boring old concrete-pipe found on 20-09-24 |
|
After Concrete-pipe removal boring resta on 20-09-24 |
During boring pile no.35 grid-2B |
Old concrete-MS pipe found |
|
During boring Obstacles found on 21-09-24 |
|
Pile concreting on 21-09-24 |
During boring pile no.36, grid-2B |
Obstacles found |
|
Pile boring length checking on 22-09-24 |
|
Pile concreting on 22-09-24 |
|
|
|
Rig shifting to Grid 1A on 23-09-24 |
|
Chisel broken due to obstacle on 23-09-24 |
During boring pile no.18 grid-1A |
Chisel broken due to obstacles |
|
Boring obstacle Old CC breaking on 24-09-24 |
|
Pile-57 concreting completed on 24-09-24 |
During boring pile no.53, grid-3B |
Obstacle Old Concrete found |
|
Pile cap re-bar dia checking on 25-09-24 |
|
Due to electrical line 1.5 m excavation on 25-09-24 |
Due to live electric line Grid-3 |
Excavating all pile point upto 1.5 m |
|
Pile cap re-bar dia checking on 26-09-24 |
|
Bentonite received for pile boring on 26-09-24 |
|
|
|
Excavating for pile boring obstacles on 27-09-24 |
|
Making road for reading concrete truck on 27-09-24 |
|
|
|
Pile boring depth checking on 28-09-24 |
|
Piling rig shifting on 28-09-24 |
|
|
|
Pile no.47 boring length checking on 29-09-24 |
|
Piling rig setting on 29-09-24 |
Pile no.47 of grid 3C length 22m |
Total 6 piles 22 m |
|
Piling rig shifting on 30-09-24 |
|
Pile concreting on 30-09-24 |
All pile completed |
|
|
Earth excavation on 1-10-24 |
|
Re-bar straighting on 1-10-24 |
|
|
|
Earth excavation on 2-10-24 |
|
Old base-column found during excavation on 2-10-24 |
During excavating old foundation with column found |
In Grid-1 in between C and D |
|
Obstacle RCC dismantling on 3-10-24 |
|
Earth excavation on 3-10-24 |
Dismantling RCC foundation found during excavation |
Money and Time wastage |
|
Pile Head breaking on 4-10-24 |
|
Wooden pile driving on 4-10-24 |
Due to rain work stopped |
|
|
Old base breaking on 5-10-24 |
|
Earth excavation on 5-10-24 |
|
|
|
Wooden shore pile driving on 6-10-24 |
|
Earth Excavation on 6-10-24 |
|
|
|
Earth excavation on 7-10-24 |
|
Pile head breaking on 7-10-24 |
|
|
|
Excavated earth dumping on 8-10-24 |
|
Dismantling by hydraulic breaker on 8-10-24 |
Dismantling old foundation 17 m3 |
By Hydraulic hammer |
|
Earth excavation on 9-10-24 |
|
Old base dismantling by hydraulic hammer on 9-10-24 |
Old base dismantling 11 m3 by hydraulic hammer |
|
|
Pile Load Test-PDA-Pile Development on 10-10-24 |
|
Water Reservoir Base CC-Bottom on 10-10-24 |
Old base dismantling 4 m3 by hydraulic hammer |
|
|
Dewatering on 11-10-24 |
|
Pile head breaking on 11-10-24 |
|
|
|
Checking before pile cap lean concreting on 12-10-24 |
|
Pile cap lean concreting on 12-10-24 |
Due to rain work started late |
|
|
Pile cap side brick shuttering on 13-10-24 |
|
Earth excavation manually on 13-10-24 |
Wooden shore piling 14 nos. |
|
|
Earth excavation on 14-10-24 |
|
Shoring on 14-10-24 |
Wooden pile driving 41 nos. |
|
|
Inspection before CC at -5200 mm on 15-10-24 |
|
CC at level -5200 finished on 15-10-24 |
|
|
|
Excavation, brick-shuttering, steel shut on 16-10-24 |
|
Pile Cap Lean concreting on 16-10-24 |
|
|
|
Pile head breaking on 17-10-24 |
|
Water tank base brick wall shuttering on 17-10-24 |
|
|
|
Pile head breaking on 18-10-24 |
|
Pile cap lean concreting on 18-10-24 |
|
|
|
Pile Cap Brick Shuttering on 19-10-24 |
|
Pile Head Breaking on 19-10-24 |
|
|
|
PIT (Pile Integrity) testing on 20-10-24 |
|
Pile cap re-bar work on 20-10-24 |
|
|
|
Pile cap concreting on 21-10-24 |
|
Pile cap lean concreting on 21-10-24 |
|
|
|
Tank base water proofing membrane SBS wo on 22-10-24 |
|
Tank base top mortering on 22-10-24 |
|
|
|
Machine foundation re-bar inspection on 23-10-24 |
|
CC work on 23-10-24 |
|
|
|
Tank base brick wall shuttering on 24-10-24 |
|
Pile head breaking on 24-10-24 |
|
|
|
PIT test on 25-10-24 |
|
Pile cap concreting on 25-10-24 |
|
|
|
Column re-bar work on 26-10-24 |
|
Pile cap re-bar work on 26-10-24 |
|
|
|
Pile cap re-bar work on 27-10-24 |
|
Tank wall shuttering on 27-10-24 |
|
|
|
Raft re-bar inspection before concreting on 28-10-24 |
|
Raft concreting by Pump on 28-10-24 |
|
|
|
Earth excavation on 29-10-24 |
|
Raft re-bar work on 29-10-24 |
|
|
|
PDA test performing on 30-10-24 |
|
Raft re-bar work on 30-10-24 |
|
|
|
Column Shuttering on 31-10-24 |
|
Water proofing admixture adding in concr on 31-10-24 |
|
|
|
Bracing beam- Column shuttering on 1-11-24 |
|
Column concreting on 1-11-24 |
|
|
|
Pile head breaking on 2-11-24 |
|
Bracing beam concreting on 2-11-24 |
|
|
|
Wall re-bar work on 3-11-24 |
|
Pile cap concreting on 3-11-24 |
|
|
|
Pile cap Concreting on 4-11-24 |
|
Column concreting on 4-11-24 |
|
|
|
Earth loading for backfilling on 5-11-24 |
|
Column shuttering on 5-11-24 |
|
|
|
Wall shuttering on 6-11-24 |
|
on 6-11-24 |
|
Tank base concreting |
|
Wall shuttering on 7-11-24 |
|
Column re-bar work on 7-11-24 |
|
|
|
Backfilling on 8-11-24 |
|
Foundation beam rebar work on 8-11-24 |
|
|
|
Wall shuttering on 9-11-24 |
|
Foundation beam rebar inspection on 9-11-24 |
|
|
|
Foundation beam rebar work on 10-11-24 |
|
Wall concreting on 10-11-24 |
|
|
|
Foundation beam shuttering on 11-11-24 |
|
Foundation beam rebar work on 11-11-24 |
|
|
|
Foundation beam inspection before concre on 12-11-24 |
|
Foundation beam concreting on 12-11-24 |
|
|
|
Anchor bolt setting on 13-11-24 |
|
Foundation beam concreting on 13-11-24 |
|
|
|
Wall shuttering on 14-11-24 |
|
Wall shuttering on 14-11-24 |
|
|
|
Wall shuttering on 15-11-24 |
|
Foundation beam rebar work on 15-11-24 |
|
|
|
Wall concreting on 16-11-24 |
|
Foundation beam concreting on 16-11-24 |
|
|
|
Foundation beam bottom shuttering on 17-11-24 |
|
Foundation beam rebar work on 17-11-24 |
|
|
|
Anchor bolt setting on 18-11-24 |
|
Foundation beam concreting on 18-11-24 |
|
|
|
Tank slab shuttering on 19-11-24 |
|
Tank slab shuttering on 19-11-24 |
|
|
|
Tank slab shuttering on 20-11-24 |
|
Tank slab shuttering on 20-11-24 |
|
|
|
Embedded steel parts mobilized on 21-11-24 |
|
Tank slab shuttering on 21-11-24 |
|
|
|
Tank slab shuttering on 22-11-24 |
|
Tank wall water proofing membrain SBS fi on 22-11-24 |
|
|
|
Tank wall stylo foam fixing on 23-11-24 |
|
Tank slab re-bar fixing on 23-11-24 |
|
|
|
Tank slab re-bar work on 24-11-24 |
|
MS Angle Fixing on 24-11-24 |
|
|
|
Tank Slab Re-bar work on 25-11-24 |
|
Embedded steel part fixing on 25-11-24 |
|
|
|
Unloading steel Column-beam on 26-11-24 |
|
Tank slab concreting on 26-11-24 |
|
|
|
Crane mobilized for Erection on 27-11-24 |
|
Non- shrink Grouting on 27-11-24 |
|
|
|
Steel column Erection on 28-11-24 |
|
Tank slab re-bar fixing on 28-11-24 |
|
|
|
Cork sheet fixing in Tank wall on 29-11-24 |
|
Tank slab concreting on 29-11-24 |
|
|
|
Loading sand for filling on 30-11-24 |
|
Sand unloading on 30-11-24 |
|
|
|
Sand filling work on 1-12-24 |
|
Steel materials unloading on 1-12-24 |
|
|
|
Steel materials unloading on 2-12-24 |
|
Installing steel beam on 2-12-24 |
|
|
|
Steel member size checking on 3-12-24 |
|
Steel member installation on 3-12-24 |
|
|
|
Steel materials unloading on 4-12-24 |
|
Steel structure installation on 4-12-24 |
|
|
|
Steel materials unloading on 5-12-24 |
|
Steel structure installation on 5-12-24 |
|
|
|
Steel structure installation on 6-12-24 |
|
Steel structure installation on 6-12-24 |
|
|
|
Steel structure installation on 7-12-24 |
|
Steel structure installation on 7-12-24 |
|
|
|
Steel structure installation on 8-12-24 |
|
Steel column vertical alignment checking on 8-12-24 |
|
|
|
Steel materials unloading on 9-12-24 |
|
Steel structure installation on 9-12-24 |
|
|
|
Steel structure installation on 10-12-24 |
|
Steel structure welding on 10-12-24 |
|
|
|
Steel structure installation on 11-12-24 |
|
Nut tightening on 11-12-24 |
|
|
|
Steel materials unloading on 12-12-24 |
|
Steel structure installation on 12-12-24 |
|
|
|
Client inspecting Steel structure instal on 13-12-24 |
|
Steel structure wedding work on 13-12-24 |
|
|
|
Sub-base work in floor on 14-12-24 |
|
Steel structure installation on 14-12-24 |
|
|
|
Floor slab re-bar work on 15-12-24 |
|
Steel materials unloading on 15-12-24 |
|
|
|
Re- bar inspection before concreting on 16-12-24 |
|
Ground floor concreting on 16-12-24 |
|
|
|
Steel structure installation on 17-12-24 |
|
Steel member welding on 17-12-24 |
|
|
|
Materials delivered on 18-12-24 |
|
Sub-base work on 18-12-24 |
|
|
|
Steel materials unloading on 19-12-24 |
|
Steel structure installation on 19-12-24 |
|
|
|
Steel materials unloading on 20-12-24 |
|
Steel structure installation on 20-12-24 |
|
|
|
Steel Structure installation on 21-12-24 |
|
Ground Floor Concreting on 21-12-24 |
|
|
|
Mechanical troweling on 22-12-24 |
|
Steel structure installation on 22-12-24 |
|
|
|
Steel structure installation on 23-12-24 |
|
Welding work on 23-12-24 |
|
|
|
Shear bolt fixing on decking slab on 24-12-24 |
|
Re-bar fixing on decking slab on 24-12-24 |
|
|
|
Re-bar work on Decking on 25-12-24 |
|
Shear bolt fixing on decking slab on 25-12-24 |
|
|
|
Steel structure erection at 4th floor on 26-12-24 |
|
Concreting on Decking slab 7 on 26-12-24 |
5 |
|
|
Steel structure installation on 27-12-24 |
|
Level-2.5m : Checker plate fixing on 27-12-24 |
|
|
|
Level-7.5 Checkered plate fixing on 28-12-24 |
|
Steel structure welding on 28-12-24 |
|
|
|
Steel structure installation on 29-12-24 |
|
Checkered plate fixing on 29-12-24 |
|
|
|
Steel Structure installation on 30-12-24 |
|
Steel Structure Installation on 30-12-24 |
|
|
|
Sub-base mechanical compaction on 31-12-24 |
|
Polythene laying over sub-base on 31-12-24 |
|
|
|
Ground Floor RCC Slab Concreting on 1-01-25 |
|
Ground Floor RCC Slab Concreting on 1-01-25 |
|
|
|
Ground Floor Concrete Mechanical Troweli on 2-01-25 |
|
Decking Slab Fixing on 2-01-25 |
|
|
|
Re-bar Work on Decking Slab on 3-01-25 |
|
Stair Fixing on 3-01-25 |
|
|
|
Re-bar fixing on Decking slab on 4-01-25 |
|
Ground floor Concreting on 4-01-25 |
|
|
|
Steel structure installation on 5-01-25 |
|
Steel structure installation on 5-01-25 |
|
|
|
Steel structure installation on 6-01-25 |
|
Re-bar fixing on decking slab on 6-01-25 |
|
|
|
Steel structure installation on 7-01-25 |
|
Concreting on Decking Slab-7.5m on 7-01-25 |
|
|
|
Column Joint working on 8-01-25 |
|
Stair case installation on 8-01-25 |
|
|
|
Steel structure installation on 9-01-25 |
|
Stair Railing welding on 9-01-25 |
|
|
|
Civil Labour on 10-01-25 |
|
Steel Worker on 10-01-25 |
|
|
|
Civil Labour on 11-01-25 |
|
Steel Worker on 11-01-25 |
|
|
|
Steel nut-blot tightening on 12-01-25 |
|
Welding steel structure on 12-01-25 |
|
|
|
Steel structure installation on 13-01-25 |
|
Steel bracing installation on 13-01-25 |
|
|
|
Checkered plate lifting on 14-01-25 |
|
Checkered plate fixing on 14-01-25 |
|
|
|
Checkered plate fixing on 15-01-25 |
|
Checkered plate welding on 15-01-25 |
|
|
|
Steel structure installation on 16-01-25 |
|
Steel stair installation on 16-01-25 |
|
|
|
Stair Fixing on 17-01-25 |
|
Checkered plate welding on 17-01-25 |
|
|
|
Stair landing checkered plate fixing on 18-01-25 |
|
Checkered plate welding on 18-01-25 |
|
|
|
Steel bracing fixing on 19-01-25 |
|
Stair Railing fixing on 19-01-25 |
|
|