Return Main Menu

WEEKY PROGRESS REPORT

From 25-January-2022 to 31-January-2022
Project Code: 17Name:Shimanto Conference Center
Client: Border Guard Bangladesh Contractor:Sarker Steel Ltd.
Progress as on: 31-January-2022
WBSWork Description
Total QuantityUpto 24-01-22This WeekTotal Done Schedule StartSchedule FinishAvtual Finish
1.3.1.1 Brick Work-Ground Floor 1340m2 95% 5% 100% 01-05-21 18-08-21 31-01-22
1.3.1.3 Brick Work-1st Floor 1210m2 95% 5% 100% 28-05-21 04-09-21 31-01-22
1.3.2.2 Plaster-Ground Floor 2680m2 95% 5% 100% 09-05-21 20-08-21 31-01-22
1.3.2.4 Plaster-1st Floor 2420m2 92% 3% 95% 29-08-21 12-09-21 31-01-22
1.3.2.5 Plaster-1st Floor Mezzanine 1560m2 92% 3% 95% 10-09-21 16-09-21 31-01-22
1.3.3 Tiles Work 60% 10% 70% 10-05-21 26-09-21 31-01-22
2.3.1.2 Interior-False Ceiling-1st Floor 0 0% 70% 70% 16-09-21 15-10-21 31-01-22
2.5.2 Generator 60% 20% 80% 15-09-21 27-10-21 31-01-22


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Tiles work on 31-01-22Interior work on 31-01-22