Progress as on: 31-January-2022 |
WBS | Work Description |
Total Quantity | Upto 31-12-21 | This Month | Total Done |
Schedule Start | Schedule Finish | Actual Finish |
1.3.1.1 |
Brick Work-Ground Floor |
1340m2 |
95% |
5% |
100% |
01-05-21 |
18-08-21 |
31-01-22 |
1.3.1.3 |
Brick Work-1st Floor |
1210m2 |
95% |
5% |
100% |
28-05-21 |
04-09-21 |
31-01-22 |
1.3.2.2 |
Plaster-Ground Floor |
2680m2 |
95% |
5% |
100% |
09-05-21 |
20-08-21 |
31-01-22 |
1.3.2.4 |
Plaster-1st Floor |
2420m2 |
92% |
3% |
95% |
29-08-21 |
12-09-21 |
31-01-22 |
1.3.2.5 |
Plaster-1st Floor Mezzanine |
1560m2 |
92% |
3% |
95% |
10-09-21 |
16-09-21 |
31-01-22 |
1.3.3 |
Tiles Work |
|
60% |
10% |
70% |
10-05-21 |
26-09-21 |
31-01-22 |
2.3.1.1 |
Interior-False Ceiling-GF |
|
95% |
5% |
100% |
09-09-21 |
08-10-21 |
05-01-22 |
2.3.1.2 |
Interior-False Ceiling-1st Floor |
0 |
0% |
70% |
70% |
16-09-21 |
15-10-21 |
31-01-22 |
2.5.2 |
Generator |
|
5% |
75% |
80% |
15-09-21 |
27-10-21 |
31-01-22 |
2.7 |
Road and Landscaping |
|
90% |
10% |
100% |
10-08-21 |
18-10-21 |
05-01-22 |
2.8 |
Outside Sanitary and Plumbing Work |
|
85% |
15% |
100% |
22-08-21 |
30-10-21 |
05-01-22 |