Return Main Menu

MONTHLY PROGRESS REPORT

From 1-January-2022 to 31-January-2022
Project Code: 17Name:Shimanto Conference Center
Client: Border Guard Bangladesh Contractor:Sarker Steel Ltd.
Progress as on: 31-January-2022
WBSWork Description
Total QuantityUpto 31-12-21This MonthTotal Done Schedule StartSchedule FinishActual Finish
1.3.1.1 Brick Work-Ground Floor 1340m2 95% 5% 100% 01-05-21 18-08-21 31-01-22
1.3.1.3 Brick Work-1st Floor 1210m2 95% 5% 100% 28-05-21 04-09-21 31-01-22
1.3.2.2 Plaster-Ground Floor 2680m2 95% 5% 100% 09-05-21 20-08-21 31-01-22
1.3.2.4 Plaster-1st Floor 2420m2 92% 3% 95% 29-08-21 12-09-21 31-01-22
1.3.2.5 Plaster-1st Floor Mezzanine 1560m2 92% 3% 95% 10-09-21 16-09-21 31-01-22
1.3.3 Tiles Work 60% 10% 70% 10-05-21 26-09-21 31-01-22
2.3.1.1 Interior-False Ceiling-GF 95% 5% 100% 09-09-21 08-10-21 05-01-22
2.3.1.2 Interior-False Ceiling-1st Floor 0 0% 70% 70% 16-09-21 15-10-21 31-01-22
2.5.2 Generator 5% 75% 80% 15-09-21 27-10-21 31-01-22
2.7 Road and Landscaping 90% 10% 100% 10-08-21 18-10-21 05-01-22
2.8 Outside Sanitary and Plumbing Work 85% 15% 100% 22-08-21 30-10-21 05-01-22


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
First floor ceiling work on 5-01-22Interior ceiling on 5-01-22
Work stopped 19-26 Dec 2021 due to Inauguration Ceremony
Tiles work on 31-01-22Interior work on 31-01-22