WBS | Work Description |
Progress as on: 31-January-2022 |
Total Qty | Today Done (%) | Total Done (%) | Start | Finish |
1.3.1.1 |
Brick Work-Ground Floor |
1340m2 |
5 |
100 |
01-05-21 |
18-08-21 |
1.3.1.3 |
Brick Work-1st Floor |
1210m2 |
5 |
100 |
28-05-21 |
04-09-21 |
1.3.2.2 |
Plaster-Ground Floor |
2680m2 |
5 |
100 |
09-05-21 |
20-08-21 |
1.3.2.4 |
Plaster-1st Floor |
2420m2 |
3 |
95 |
29-08-21 |
12-09-21 |
1.3.2.5 |
Plaster-1st Floor Mezzanine |
1560m2 |
3 |
95 |
10-09-21 |
16-09-21 |
1.3.3 |
Tiles Work |
|
10 |
70 |
10-05-21 |
26-09-21 |
2.3.1.2 |
Interior-False Ceiling-1st Floor |
0 |
70 |
70 |
16-09-21 |
15-10-21 |
2.5.2 |
Generator |
|
20 |
80 |
15-09-21 |
27-10-21 |