Return Main Menu

DAILY PROGRES REPORT

Project:Shimanto Conference Center Project Code: 17 Date31-January-2022
Client: Border Guard Bangladesh Report142 DayMonday
Contractor:Sarker Steel Ltd. ClimateSunny
Temperature11-22°C
Manpower
SNDescriptionNos
01Sarker Staff3
04AC-Newton-Staff1
05AC-Newton-Worker10
TOTAL 14
WBSWork Description Progress as on: 31-January-2022
Total QtyToday Done (%)Total Done (%)StartFinish
1.3.1.1 Brick Work-Ground Floor 1340m2 5 100 01-05-21 18-08-21
1.3.1.3 Brick Work-1st Floor 1210m2 5 100 28-05-21 04-09-21
1.3.2.2 Plaster-Ground Floor 2680m2 5 100 09-05-21 20-08-21
1.3.2.4 Plaster-1st Floor 2420m2 3 95 29-08-21 12-09-21
1.3.2.5 Plaster-1st Floor Mezzanine 1560m2 3 95 10-09-21 16-09-21
1.3.3 Tiles Work 10 70 10-05-21 26-09-21
2.3.1.2 Interior-False Ceiling-1st Floor 0 70 70 16-09-21 15-10-21
2.5.2 Generator 20 80 15-09-21 27-10-21
Site Photographs
Tiles workInterior work
Site Description
Site Instruction