Total Duration: |
470 |
days |
Total Working Days: |
223 |
Total Manpower: |
8279 |
|
|
Planning Progress = 84.4% |
Acual Progress = 92.9% |
SPI: 1.1 |
Ahead Schedule |
Progress as on: 23-April-2024
WBS |
Work Description |
Total Quantity |
Total Done |
Schedule Start
| Schedule Finish |
Actual Start |
Actual Finish |
Lead-Lag(day) |
Not Yet |
1.1 |
Mobilization-Shed |
1sum |
100% |
09-01-23 |
20-01-23 |
09-01-23 |
22-01-23 |
-2 |
|
1.2 |
Mobilization-Labor |
1sum |
100% |
14-01-23 |
17-01-23 |
14-01-23 |
17-01-23 |
0 |
|
1.3 |
Mobilization-Materials |
1sum |
100% |
21-01-23 |
22-01-23 |
21-01-23 |
21-01-23 |
1 |
|
1.4 |
Mobilization-Equipment |
1sum |
100% |
27-01-23 |
28-01-23 |
29-01-23 |
29-01-23 |
-1 |
|
1.5 |
Electricity Connection |
01 |
100% |
31-01-23 |
06-02-23 |
31-01-23 |
06-02-23 |
0 |
|
1.6 |
Tube-well Sinking |
1no. |
100% |
01-02-23 |
01-02-23 |
01-02-23 |
01-02-23 |
0 |
|
1.7 |
Mud Tank Making |
2nos |
100% |
01-02-23 |
12-02-23 |
02-02-23 |
12-02-23 |
0 |
|
2 |
Pile Layout and Survey |
1sum |
100% |
01-02-23 |
02-02-23 |
01-02-23 |
03-02-23 |
-1 |
|
3.1.1 |
Comp.Bldg-Pile Boring, Concreting |
69nos |
100% |
09-02-23 |
10-03-23 |
09-02-23 |
17-03-23 |
-7 |
|
3.1.2 |
Comp Bldg-Load Test-Integrity Test |
1sum |
100% |
11-04-23 |
13-04-23 |
06-04-23 |
14-04-23 |
-1 |
|
3.1.3.1 |
Comp Bldg-Pile head Breaking |
69nos |
100% |
18-03-23 |
27-03-23 |
16-03-23 |
06-04-23 |
-10 |
|
3.1.3.2 |
Comp Bldg-Pile Cap |
20nos |
100% |
21-03-23 |
30-03-23 |
05-04-23 |
18-04-23 |
-19 |
|
3.1.3.3 |
Comp Bldg-Foundation Beam |
266m |
100% |
31-03-23 |
13-04-23 |
19-04-23 |
16-05-23 |
-33 |
|
3.1.4.1.1 |
Comp Bldg-GF-Column |
20nos |
100% |
24-05-23 |
01-06-23 |
22-05-23 |
02-06-23 |
-1 |
|
3.1.4.1.2.1 |
Comp Bldg-GF-Stair-1st Flight |
1nos |
100% |
28-05-23 |
01-06-23 |
01-06-23 |
05-06-23 |
-4 |
|
3.1.4.1.2.2 |
Comp Bldg-GF-Stair-2nd Flight |
1nos |
100% |
04-06-23 |
10-06-23 |
22-06-23 |
27-06-23 |
-17 |
|
3.1.4.1.3.1 |
Comp-1st Floor Slab-Formwork |
613m2 |
100% |
01-06-23 |
06-06-23 |
01-06-23 |
22-06-23 |
-16 |
|
3.1.4.1.3.2 |
Comp-1st Floor Slab-Re-bar Work |
613m2 |
100% |
07-06-23 |
09-06-23 |
02-06-23 |
22-06-23 |
-13 |
|
3.1.4.1.3.3 |
Comp-1st Floor Slab-Electrical |
613m2 |
100% |
08-06-23 |
09-06-23 |
22-06-23 |
22-06-23 |
-13 |
|
3.1.4.1.3.4 |
Comp-1st Floor Slab Concreting |
613m2 |
100% |
10-06-23 |
10-06-23 |
27-06-23 |
27-06-23 |
-17 |
|
3.1.4.2.1 |
Comp Bldg-1st Floor-Column |
20nos |
100% |
12-06-23 |
18-06-23 |
06-07-23 |
19-07-23 |
-31 |
|
3.1.4.2.2.1 |
Comp-1st Floor-Stair-1st Flight |
1no. |
100% |
12-06-23 |
18-06-23 |
06-07-23 |
16-07-23 |
-28 |
|
3.1.4.2.2.2 |
Comp-1st Floor-Stair-2nd Flight |
1no. |
100% |
20-06-23 |
26-06-23 |
17-07-23 |
04-08-23 |
-39 |
|
3.1.4.2.3.1 |
Comp-2nd Floor Slab-Formwork |
613m2 |
100% |
19-06-23 |
24-06-23 |
16-07-23 |
31-07-23 |
-37 |
|
3.1.4.2.3.2 |
Comp-2nd Floor Slab-Re-bar Work |
613m2 |
100% |
25-06-23 |
26-06-23 |
17-07-23 |
02-08-23 |
-37 |
|
3.1.4.2.3.3 |
Comp-2nd Floor Slab-Electrical Work |
613m2 |
100% |
25-06-23 |
26-06-23 |
04-08-23 |
04-08-23 |
-39 |
|
3.1.4.2.3.4 |
Comp-2nd Floor Slab-Concreting |
613m2 |
100% |
26-06-23 |
26-06-23 |
04-08-23 |
04-08-23 |
-39 |
|
3.1.4.3.1 |
Comp-Top Floor-Column |
4nos |
100% |
08-07-23 |
09-07-23 |
21-08-23 |
27-08-23 |
-49 |
|
3.1.4.3.2 |
Comp-Top Floor Roof Slab |
0m2 |
100% |
10-07-23 |
11-07-23 |
03-09-23 |
16-09-23 |
-67 |
|
3.1.4.3.3 |
Comp Parapet-Brick Wall |
153m2 |
100% |
08-07-23 |
10-07-23 |
14-08-23 |
22-09-23 |
-74 |
|
3.1.5.1.1 |
Comp-GF-Brickwork |
111m3 |
100% |
25-06-23 |
11-07-23 |
21-07-23 |
08-09-23 |
-59 |
|
3.1.5.1.2 |
Comp-GF-Window Grill |
0nos |
100% |
12-07-23 |
14-07-23 |
03-09-23 |
21-09-23 |
-69 |
|
3.1.5.1.3 |
Comp-GF-Plaster work |
1364m2 |
100% |
11-07-23 |
15-07-23 |
18-08-23 |
21-09-23 |
-68 |
|
3.1.5.1.4 |
Comp-Khoa-sand Cushion in Floor |
613m2 |
100% |
11-07-23 |
15-07-23 |
14-08-23 |
25-09-23 |
-72 |
|
3.1.5.1.5 |
Comp-GF-Floor Concreting |
613m2 |
100% |
10-07-23 |
16-07-23 |
16-09-23 |
02-11-23 |
-109 |
|
3.1.5.1.6 |
Comp-GF-Tiles Fitting |
790m2 |
100% |
17-07-23 |
23-07-23 |
25-10-23 |
02-02-24 |
-194 |
|
3.1.5.1.7 |
Comp-GF-Door Shutter-Window fixing |
0nos |
100% |
22-07-23 |
24-07-23 |
02-02-24 |
02-02-24 |
-193 |
|
3.1.5.1.8 |
Comp-GF-False Ceiling |
|
100% |
10-07-23 |
24-07-23 |
02-02-24 |
02-02-24 |
-193 |
|
3.1.5.1.9 |
Comp-GF-Painting |
|
100% |
25-11-23 |
19-12-23 |
02-02-24 |
02-02-24 |
-45 |
|
3.1.5.2.1 |
Comp-1st Floor-Brickwork |
111m3 |
100% |
26-07-23 |
01-08-23 |
22-08-23 |
22-09-23 |
-52 |
|
3.1.5.2.2 |
Comp-1st Floor-Plaster Work |
1364m2 |
100% |
01-08-23 |
05-08-23 |
03-09-23 |
02-02-24 |
-181 |
|
3.1.5.2.3 |
Comp-1st Floor-Tile Fixing |
613m2 |
100% |
04-08-23 |
10-08-23 |
02-02-24 |
02-02-24 |
-176 |
|
3.1.5.2.4 |
Comp-1st Floor-Door Shutter Window fixin |
0nos |
100% |
09-08-23 |
11-08-23 |
02-02-24 |
02-02-24 |
-175 |
|
3.1.5.2.5 |
Comp-1st Floor-False Ceiling |
|
100% |
28-07-23 |
11-08-24 |
02-02-24 |
02-02-24 |
191 |
|
3.1.5.2.6 |
Comp-1st Floor-Painting |
|
100% |
02-12-23 |
26-12-23 |
02-02-24 |
02-02-24 |
-38 |
|
3.1.5.3 |
Comp-Outside Plastering |
m2 |
100% |
28-07-23 |
11-08-23 |
08-10-23 |
02-11-23 |
-83 |
|
3.1.6.1.1 |
Comp-GF-Sanitary Pipe Work |
1sum |
100% |
12-07-23 |
21-12-23 |
19-07-23 |
02-02-24 |
-43 |
|
3.1.6.1.2 |
Comp-GF-Plumbing work |
1sum |
100% |
12-07-23 |
18-07-23 |
31-10-23 |
02-02-24 |
-199 |
|
3.1.6.1.3 |
Comp-GF-Electrical Pipe Work |
1sum |
100% |
12-07-23 |
18-07-23 |
27-07-23 |
23-08-23 |
-36 |
|
3.1.6.1.4 |
Comp-GF-Power Distribution Board |
nos |
100% |
19-07-23 |
25-07-23 |
26-10-23 |
02-02-24 |
-192 |
|
3.1.6.1.5 |
Comp-GF-Cable Tray |
80m |
100% |
19-07-23 |
25-07-23 |
29-09-23 |
29-09-23 |
-66 |
|
3.1.6.1.6 |
Comp-GF-Electric Cable/wiring |
1Sum |
100% |
13-07-23 |
19-07-23 |
13-10-23 |
31-10-23 |
-104 |
|
3.1.6.1.7 |
Comp-GF-Sanitary Fixer installi |
1Sum |
100% |
21-12-23 |
27-12-23 |
02-02-24 |
02-02-24 |
-37 |
|
3.1.6.1.8 |
Comp-GF-Electric switch-socket fix |
1Sum |
100% |
25-12-23 |
27-12-23 |
02-02-24 |
02-02-24 |
-37 |
|
3.1.6.2.1 |
Comp-1st Floor-Sanitary Pipe Work |
1Sum |
100% |
04-08-23 |
08-08-23 |
03-09-23 |
02-02-24 |
-178 |
|
3.1.6.2.2 |
Comp.1st Floor-Plumbing work |
1sum |
100% |
04-08-23 |
08-08-23 |
31-10-23 |
02-02-24 |
-178 |
|
3.1.6.2.3 |
Comp.1st Floor-Electrical Pipe work |
|
100% |
04-08-23 |
08-08-23 |
03-09-23 |
31-10-23 |
-84 |
|
3.1.6.2.4 |
Comp-1st Floor-Power Distribution Board |
nos |
100% |
05-08-23 |
11-08-23 |
26-10-23 |
02-02-24 |
-175 |
|
3.1.6.2.5 |
Comp-1st Floor-Cable Tray |
80m |
100% |
05-08-23 |
11-08-23 |
25-10-23 |
31-10-23 |
-81 |
|
3.1.6.2.6 |
Comp.1st Floor-Electrical Cable/wiring |
1sum |
100% |
07-08-23 |
09-08-23 |
31-10-23 |
31-10-23 |
-83 |
|
3.1.6.2.7 |
Comp.1st Floor-Sanitary fixer installati |
1sum |
100% |
21-12-23 |
27-12-23 |
02-02-24 |
02-02-24 |
-37 |
|
3.1.6.2.8 |
Comp-1st Floor-Elect switch-socket |
1sum |
100% |
25-12-23 |
27-12-23 |
02-02-24 |
02-02-24 |
-37 |
|
3.2.1 |
Canteen Dormitory-Pile Boring, Concretin |
38nos |
100% |
12-03-23 |
26-03-23 |
25-03-23 |
13-04-23 |
-18 |
|
3.2.2 |
Canteen Dormitory-Load Test-Integrity Te |
1sum |
100% |
30-04-23 |
30-04-23 |
19-05-23 |
19-05-23 |
-19 |
|
3.2.3.1 |
Canteen Dormitory-Pilehead Breaking |
38nos |
100% |
01-05-23 |
10-05-23 |
02-05-23 |
23-05-23 |
-13 |
|
3.2.3.2 |
Canteen Dormitory-Pile Cap |
12nos |
100% |
20-05-23 |
29-05-23 |
11-05-23 |
29-05-23 |
0 |
|
3.2.3.3 |
Canteen Dormitory-Short Column |
12nos |
100% |
30-05-23 |
01-06-23 |
01-06-23 |
13-06-23 |
-12 |
|
3.2.3.4 |
Canteen Dormitory-Grade Beam |
164m |
100% |
02-06-23 |
08-06-23 |
01-06-23 |
13-06-23 |
-5 |
|
3.2.4.1.1 |
Canteen Dormitory-GF-Column |
12nos |
100% |
18-06-23 |
26-06-23 |
20-06-23 |
27-06-23 |
-1 |
|
3.2.4.1.2.1 |
Canteen Dormitory-GF-Stair-1st Flight |
1no. |
100% |
09-07-23 |
13-07-23 |
08-07-23 |
02-08-23 |
-20 |
|
3.2.4.1.2.2 |
Canteen Dormitory-GF-Stair-2nd Flight |
1no. |
100% |
20-07-23 |
26-07-23 |
04-08-23 |
10-08-23 |
-15 |
|
3.2.4.1.3.1 |
Canteen Dormitory-1st Floor Slab-Form |
240m2 |
100% |
12-07-23 |
21-07-23 |
21-07-23 |
06-08-23 |
-16 |
|
3.2.4.1.3.2 |
Canteen Dormitory-1st Floor Slab-Re-bar |
240m2 |
100% |
22-07-23 |
25-07-23 |
02-08-23 |
06-08-23 |
-12 |
|
3.2.4.1.3.3 |
Canteen Dormitory-1st Floor Slab-Electri |
240m2 |
100% |
23-07-23 |
25-07-23 |
07-08-23 |
09-08-23 |
-15 |
|
3.2.4.1.3.4 |
Canteen Dormitory-1st Floor Slab-Concret |
240m2 |
100% |
26-07-23 |
26-07-23 |
10-08-23 |
10-08-23 |
-15 |
|
3.2.4.2.1 |
Canteen Dormitory-1st Floor-Column |
12nos. |
100% |
13-08-23 |
19-08-23 |
18-08-23 |
01-09-23 |
-13 |
|
3.2.4.2.2.1 |
Canteen Dormitory-1st Floor-Stair-1st Fl |
1no, |
100% |
13-08-23 |
19-08-23 |
23-08-23 |
30-08-23 |
-11 |
|
3.2.4.2.2.2 |
Canteen Dormitory-1st Floor-Stair-2nd Fl |
1no. |
100% |
26-08-23 |
01-09-23 |
01-09-23 |
16-09-23 |
-15 |
|
3.2.4.2.3.1 |
Canteen Dormitory-2nd Floor-Form Work |
240m2 |
100% |
20-08-23 |
27-08-23 |
03-09-23 |
08-09-23 |
-12 |
|
3.2.4.2.3.2 |
Canteen Dormitory-2nd Floor-Slab-Re-bar |
240m2 |
100% |
28-08-23 |
01-09-23 |
04-09-23 |
09-09-23 |
-8 |
|
3.2.4.2.3.3 |
Canteen Dormitory-2nd Floor Slab-Electri |
240m2 |
100% |
31-08-23 |
01-09-23 |
16-09-23 |
16-09-23 |
-15 |
|
3.2.4.2.3.4 |
Canteen Dormitory-2nd Floor Slab-Concret |
240m2 |
100% |
01-09-23 |
01-09-23 |
16-09-23 |
16-09-23 |
-15 |
|
3.2.4.3.1 |
Dormitory-2nd Floor-Column |
12nos |
100% |
04-09-23 |
02-11-23 |
04-10-23 |
03-11-23 |
-1 |
|
3.2.4.3.2.1 |
Dormitory-2nd Floor-Stair-1st Flight |
1no. |
100% |
27-10-23 |
02-11-23 |
23-12-23 |
23-04-24 |
-173 |
|
3.2.4.3.2.2 |
Dormitory-2nd Floor-Stair-2nd Flight |
1no. |
100% |
04-12-23 |
10-12-23 |
23-12-23 |
23-04-24 |
-135 |
|
3.2.4.3.3.1 |
Dormotory-3rd Floor Slab-Formwork |
240m2 |
100% |
03-11-23 |
10-11-23 |
08-11-23 |
18-12-23 |
-38 |
|
3.2.4.3.3.2 |
Dormitory-3rd Floor Slab-Re-bar Work |
240m2 |
100% |
06-12-23 |
10-12-23 |
18-12-23 |
18-12-23 |
-8 |
|
3.2.4.3.3.3 |
Dormitory-3rd Floor Slab-Electrical Pipe |
240m2 |
100% |
09-12-23 |
10-12-23 |
18-12-23 |
18-12-23 |
-8 |
|
3.2.4.3.3.4 |
Dormitory-3rd Floor Slab-Concreting |
240m2 |
100% |
10-12-23 |
10-12-23 |
23-12-23 |
23-04-24 |
-135 |
|
3.2.5.1.1 |
Canteen Dormitory-GF Brickwork |
111m2 |
100% |
31-07-23 |
16-08-23 |
20-09-23 |
18-10-23 |
-63 |
|
3.2.5.1.2 |
Canteen Dormitory-GF-Door Frame fixing |
0nos |
100% |
11-12-23 |
17-12-23 |
26-02-24 |
26-02-24 |
-71 |
|
3.2.5.1.3 |
Canteen Dormitory-GF-Window Grill Fixing |
0nos |
100% |
11-12-23 |
17-12-23 |
26-02-24 |
26-02-24 |
-71 |
|
3.2.5.1.4 |
Canteen Dormitory-GF-Inside Plastering |
468m2 |
178% |
16-08-23 |
20-08-23 |
27-10-23 |
26-02-24 |
|
|
3.2.5.1.5 |
Canteen Dormitory-GF-Khoa-sand cushion |
240m2 |
140% |
16-08-23 |
20-08-23 |
09-11-23 |
26-02-24 |
|
|
3.2.5.1.6 |
Canteen Dormitory-GF-Concereting |
240m2 |
100% |
16-08-23 |
21-08-23 |
26-02-24 |
26-02-24 |
-189 |
|
3.2.5.1.7 |
Canteen Dormitory-GF-Tiles |
240m2 |
100% |
05-12-23 |
19-12-23 |
26-02-24 |
26-02-24 |
-69 |
|
3.2.5.1.8 |
Canteen Dormitory-GF-Door-Window fixing |
0nos |
100% |
18-12-23 |
20-12-23 |
26-02-24 |
26-02-24 |
-68 |
|
3.2.5.1.9 |
Dormatory-GF-Painting |
|
100% |
06-12-24 |
20-12-24 |
26-02-24 |
26-02-24 |
298 |
|
3.2.5.2.1 |
Canteen Dormitory-1st Floor-Brickwork |
111m2 |
100% |
09-10-23 |
15-10-23 |
06-10-23 |
20-10-23 |
-5 |
|
3.2.5.2.2 |
Canteen Dormitory-1st Floor-Door Frame f |
0nos |
100% |
18-12-23 |
20-10-23 |
26-02-24 |
26-02-24 |
-129 |
|
3.2.5.2.3 |
Canteen Dormitory-1st Floor-Window Grill |
0nos |
100% |
18-12-23 |
20-12-23 |
26-02-24 |
26-02-24 |
-68 |
|
3.2.5.2.4 |
Canteen Dormitory-1st Floor-Plaster work |
0m2 |
100% |
15-10-23 |
21-12-23 |
26-02-24 |
26-02-24 |
-67 |
|
3.2.5.2.5 |
Canteen Dormitory-1st Floor-Tile work |
0m2 |
100% |
20-12-23 |
03-01-24 |
26-02-24 |
26-02-24 |
-54 |
|
3.2.5.2.6 |
Canteen Dormitory-1st Floor-Door-window |
0nos |
100% |
02-01-24 |
04-01-24 |
26-02-24 |
26-02-24 |
-53 |
|
3.2.5.2.7 |
Dormitory-1st Floor-Painting |
|
100% |
21-12-24 |
04-01-24 |
26-02-24 |
26-02-24 |
-53 |
|
3.2.5.2.8 |
Dormitory-1st Floor-False Ceiling-Partit |
sum |
100% |
29-12-23 |
04-01-24 |
23-04-24 |
26-02-24 |
-53 |
|
3.2.5.3.1 |
Dormitory-2nd Floor-Brickwork |
111m2 |
100% |
08-01-24 |
17-01-24 |
23-04-24 |
23-04-24 |
-97 |
|
3.2.5.3.2 |
Dormitory-2nd Floor-Door Frame fixing |
0nos |
100% |
18-01-24 |
20-01-24 |
23-04-24 |
23-04-24 |
-94 |
|
3.2.5.3.3 |
Dormitory-2nd Floor-Window Grill Fixing |
0nos |
100% |
18-01-24 |
20-01-24 |
23-04-24 |
23-04-24 |
-94 |
|
3.2.5.3.4 |
Dormitory-2nd Floor-Inside Plastering |
468m2 |
100% |
12-01-24 |
21-01-24 |
23-04-24 |
23-04-24 |
-93 |
|
3.2.5.3.5 |
Dormitory-2nd Floor-Tiles Fitting |
0m2 |
100% |
20-01-24 |
28-01-24 |
23-04-24 |
23-04-24 |
-86 |
|
3.2.5.3.6 |
Dormitory-2nd Floor-Door-Window fixing |
0nos |
95% |
27-01-24 |
29-01-24 |
23-04-24 |
23-04-24 |
|
Completed |
3.2.5.3.7 |
Dormitory-2nd Floor-Inside Painting |
m2 |
30% |
18-01-24 |
31-01-24 |
23-04-24 |
23-04-24 |
|
Completed |
3.2.5.3.8 |
Dormitory-2nd Floor-False Ceiling-Partit |
|
80% |
25-01-24 |
31-01-24 |
05-04-24 |
05-04-24 |
|
Completed |
3.2.5.4 |
Dormitory-Parapet Brick Wall |
0m2 |
100% |
14-12-23 |
28-12-23 |
26-02-24 |
26-02-24 |
-60 |
|
3.2.5.5 |
Dormitory-Outside Plastering |
0m2 |
100% |
29-12-23 |
22-01-24 |
26-02-24 |
23-04-24 |
-92 |
|
3.2.5.6 |
Dormitory-Waterproof-Rooftop |
|
100% |
08-01-24 |
22-01-24 |
08-04-24 |
08-04-24 |
-77 |
|
3.2.5.7 |
Dormitory-Outside Painting |
m2 |
30% |
12-01-24 |
31-01-24 |
23-04-24 |
23-04-24 |
|
Completed |
3.2.5.8 |
Dormitory-Stair Railing |
|
100% |
25-01-24 |
31-01-24 |
05-04-24 |
23-04-24 |
-83 |
|
3.2.6.1.1 |
Canteen Dormitory-GF-Sanitary Pipe work |
1sum |
100% |
17-08-23 |
23-08-23 |
07-11-23 |
26-02-24 |
-187 |
|
3.2.6.1.2 |
Canteen Dormitory-GF-Plumbing work |
1sum |
100% |
22-12-23 |
28-12-23 |
26-02-24 |
26-02-24 |
-60 |
|
3.2.6.1.3 |
Canteen Dormitory-GF-Electrical Pipe Wor |
1sum |
100% |
17-08-23 |
23-08-23 |
31-10-23 |
31-10-23 |
-69 |
|
3.2.6.1.4 |
Dormitory-GF-Power Distribution Board |
nos |
100% |
22-12-23 |
28-12-23 |
26-02-24 |
26-02-24 |
-60 |
|
3.2.6.1.5 |
Dormitory-GF-Cable Tray |
m |
100% |
20-08-23 |
26-08-23 |
26-02-24 |
26-02-24 |
-184 |
|
3.2.6.1.6 |
Canteen Dormitory-GF-Electrical Cable wi |
1sum |
100% |
22-12-23 |
28-12-23 |
26-02-24 |
26-02-24 |
-60 |
|
3.2.6.1.7 |
Canteen Dormitory-GF-Sanitary Fixer inst |
1sum |
100% |
04-01-24 |
10-01-24 |
26-02-24 |
26-02-24 |
-47 |
|
3.2.6.1.8 |
Canteen Dormitory-GF-Electrical Switch-s |
1sum |
100% |
08-01-24 |
10-01-24 |
26-02-24 |
26-02-24 |
-47 |
|
3.2.6.2.1 |
Dormitory-1st Floor-Sanitary Pipe Work |
1sum |
100% |
16-10-23 |
22-10-23 |
26-02-24 |
26-02-24 |
-127 |
|
3.2.6.2.2 |
Dormitory-1st Floor-Plumbing Work |
1sum |
100% |
29-12-23 |
04-01-24 |
26-02-24 |
26-02-24 |
-53 |
|
3.2.6.2.3 |
Dormitory-1st Floor-Electrical Pipe Work |
1sum |
100% |
29-12-23 |
04-01-24 |
07-11-23 |
26-02-24 |
-53 |
|
3.2.6.2.4 |
Dormitory-1st Floor-Power Distribution B |
0 |
100% |
05-01-24 |
07-01-24 |
26-02-24 |
26-02-24 |
-50 |
|
3.2.6.2.5 |
Dormitory-1st Floor-Cable Tray |
1sum |
100% |
01-01-24 |
07-01-24 |
26-02-24 |
26-02-24 |
-50 |
|
3.2.6.2.6 |
Dormitory-1st Floor-Electric Wiring/Cabl |
1sum |
100% |
08-01-24 |
14-01-24 |
26-02-24 |
26-02-24 |
-43 |
|
3.2.6.2.7 |
Dormitory-1st Floor-Sanitary Fixer |
0 |
100% |
05-01-24 |
05-01-24 |
26-02-24 |
26-02-24 |
-52 |
|
3.2.6.2.8 |
Dormitory-1st Floor-Electrical Switch-So |
0 |
100% |
04-01-24 |
05-01-24 |
26-02-24 |
26-02-24 |
-52 |
|
3.2.6.3 |
Dormitory-2nd Floor-Water-Electrical |
0 |
90% |
15-01-24 |
29-01-24 |
23-04-24 |
23-04-24 |
|
Completed |
3.3.1 |
Gate House-Pile Boring, Concreting |
6nos |
100% |
28-03-23 |
29-03-23 |
19-03-23 |
21-03-23 |
8 |
|
3.3.2 |
Gate House-Pile Integrity Test |
1nos |
100% |
17-04-23 |
19-04-23 |
14-04-23 |
14-04-23 |
5 |
|
3.3.3.1 |
Gate House-Pile Cap |
6nos |
100% |
03-05-23 |
07-05-23 |
08-05-23 |
12-05-23 |
-5 |
|
3.3.3.2 |
Gate House-Foundation Beam |
50m |
100% |
08-05-23 |
17-05-23 |
15-05-23 |
18-05-23 |
-1 |
|
3.3.4 |
Gate House-Brick Work |
35m3 |
100% |
28-05-23 |
10-06-23 |
28-05-23 |
20-06-23 |
-10 |
|
3.3.5 |
Gate House-Column |
6nos |
100% |
11-06-23 |
17-06-23 |
06-06-23 |
19-06-23 |
-2 |
|
3.3.6 |
Gate House-Roof Slab |
93m2 |
100% |
18-06-23 |
25-06-23 |
25-06-23 |
11-07-23 |
-16 |
|
3.3.7.1 |
Gate House-Door Frame fixing |
4nos |
100% |
12-08-23 |
14-08-23 |
20-08-23 |
20-08-23 |
-6 |
|
3.3.7.2 |
Gate House-Paster Work |
234m2 |
100% |
11-08-23 |
15-08-23 |
26-07-23 |
20-08-23 |
-5 |
|
3.3.7.3 |
Gate House-Khoa-sand cushion in floor |
93m2 |
100% |
14-08-23 |
16-08-23 |
02-08-23 |
02-08-23 |
14 |
|
3.3.7.4 |
Gate House-Floor concreting |
93m2 |
100% |
17-08-23 |
19-08-23 |
01-09-23 |
01-09-23 |
-13 |
|
3.3.7.5 |
Gate House-Tiles fitting |
93m2 |
100% |
20-08-23 |
24-08-23 |
26-09-23 |
04-10-23 |
-41 |
|
3.3.7.6 |
Gate House-Door Shutter, Window fixing |
11nos |
100% |
25-08-23 |
26-08-23 |
27-10-23 |
03-11-23 |
-69 |
|
3.3.7.7 |
Gate House-Painting |
m2 |
100% |
09-10-23 |
15-10-23 |
08-11-23 |
10-11-23 |
-26 |
|
3.3.8.1 |
Gate House-Electrical Pipe Work |
1sum |
100% |
12-08-23 |
16-08-23 |
19-07-23 |
21-07-23 |
26 |
|
3.3.8.2 |
Gate House-Electric cable/wiring |
0sum |
100% |
23-08-23 |
24-08-23 |
13-10-23 |
13-10-23 |
-50 |
|
3.3.8.3 |
Gate House-Electrical Switch Socket Fixi |
0sum |
100% |
25-08-23 |
26-08-23 |
13-11-23 |
13-11-23 |
-79 |
|
4.1 |
Road--Sub-grade Compaction |
4817m2 |
100% |
11-07-23 |
03-01-24 |
20-07-23 |
05-04-24 |
-93 |
|
4.2 |
Sub-base-Car Road-400m |
4817m2 |
100% |
06-08-23 |
10-01-24 |
22-07-23 |
05-04-24 |
-86 |
|
4.3 |
Road-Sub-base-Pedestrain |
0m2 |
80% |
19-11-23 |
17-01-24 |
23-04-24 |
23-04-24 |
|
Completed |
4.4 |
RCC-Car Road |
4817m2 |
100% |
26-12-23 |
24-01-24 |
15-10-23 |
05-04-24 |
-72 |
|
4.5 |
RCC-Pedstrain |
0m2 |
0% |
02-01-24 |
31-01-24 |
|
30-11--1 |
|
Started |
5.1 |
Outdoor-Electrical-Power Cable |
2916m |
100% |
11-07-23 |
15-12-23 |
04-10-23 |
26-02-24 |
-73 |
|
5.2 |
Outdoor-Water Supply Pipe |
0 |
100% |
16-12-23 |
14-01-24 |
26-02-24 |
26-02-24 |
-43 |
|
5.3 |
Outdoor-Sewerage |
0 |
100% |
16-12-23 |
14-01-24 |
26-02-24 |
26-02-24 |
-43 |
|
6.1 |
Hydropower-Main Workshop |
0 |
90% |
08-12-23 |
28-01-24 |
08-04-24 |
08-04-24 |
|
Completed |
6.2 |
Production Buldg-Hydropower installation |
1sum |
90% |
18-12-23 |
28-01-24 |
08-04-24 |
08-04-24 |
|
Completed |
6.3 |
Hydropower-Boiler Room |
0 |
0% |
08-12-23 |
28-01-24 |
|
30-11--1 |
|
Started |
6.4.1 |
Substation-Roof Slab Electric Pipe Work |
|
100% |
11-10-23 |
13-10-23 |
22-07-23 |
22-07-23 |
83 |
|
6.4.2 |
Sub-station-Wall Electric Pipe Work |
0m |
100% |
16-12-23 |
23-12-23 |
08-04-24 |
08-04-24 |
-107 |
|
6.4.3 |
Electrical Cable/ Wiring |
0m |
100% |
23-12-23 |
22-01-24 |
08-04-24 |
08-04-24 |
-77 |
|
6.4.4 |
Sub-station-Switch Socket Fixing |
1sum |
0% |
15-01-24 |
21-01-24 |
|
30-11--1 |
|
Started |
7 |
NewHope-Handover |
0 |
0% |
31-01-24 |
31-01-24 |
|
30-11--1 |
|
Started |
Site Photographs |
|
Brick un-loading on 9-01-23 |
|
Brick mobilized for shed on 9-01-23 |
|
|
|
Unloading Materials on 14-01-23 |
|
Materials for Shed on 14-01-23 |
|
|
|
Shed making on 17-01-23 |
|
shed making on 17-01-23 |
|
|
|
Re-bar mobilized on 21-01-23 |
|
Re-bar mobilized on 21-01-23 |
|
|
|
Shed completed on 22-01-23 |
|
Shed completed on 22-01-23 |
|
|
|
Piling Rig mobilized on 29-01-23 |
|
Piling Rig Mobilized on 29-01-23 |
|
|
|
Electrical DB Setting on 31-01-23 |
|
Pile Rig Installing on 31-01-23 |
|
|
|
Pile Point Layout and Survey on 1-02-23 |
|
Deep tube well sinking on 1-02-23 |
|
|
|
Exaction for Pile mud tank on 2-02-23 |
|
Pile re-bar spacer block making on 2-02-23 |
|
|
|
Pile Rig setting on 3-02-23 |
|
Excavation for Pile Mud Tank on 3-02-23 |
|
|
|
Brick-work around Pile point on 5-02-23 |
|
Pile Re-bar Work on 5-02-23 |
|
|
|
Electricity Connection on 6-02-23 |
|
Mud Tank making on 6-02-23 |
|
|
|
Mud Tank-1 Competed on 8-02-23 |
|
Inspection before Pile driving on 8-02-23 |
|
|
|
Pile Driving Starting on 9-02-23 |
|
Pile Concreting on 9-02-23 |
|
|
|
Mud Tank-2 Completed on 12-02-23 |
|
Pile Re-bar Work on 12-02-23 |
|
|
|
Pile boring work on 13-02-23 |
|
Ready mix concreting of pile on 13-02-23 |
|
|
|
Pile boring work on 14-02-23 |
|
Ready mix concreting of pile on 14-02-23 |
|
|
|
Pile boring work-CB(5+2) out of 69 nos p on 15-02-23 |
|
Ready mix concreting of pile on 15-02-23 |
|
|
|
Com. Bldg. 9th pile boring on 16-02-23 |
|
Ready mix concreting of pile on 16-02-23 |
|
|
|
Com. Bldg. 12th pile boring on 17-02-23 |
|
Ready mix concreting of pile on 17-02-23 |
|
|
|
Com. Bldg. 14th pile boring on 18-02-23 |
|
Ready mix concreting of pile on 18-02-23 |
|
|
|
Com. Bldg. 15th pile boring on 19-02-23 |
|
Ready mix concreting of pile on 19-02-23 |
|
|
|
Com. Bldg. 17th Pile Boring on 21-02-23 |
|
Ready mix concreting of pile on 21-02-23 |
Yesterday no pile bored due to RMC non-availability |
BBS no operator, Farida plant disturbed |
|
Com. Bldg. 20th Pile Boring on 22-02-23 |
|
Ready mix concreting of pilewort on 22-02-23 |
|
|
|
Com. Bldg. 22nd pile boring on 23-02-23 |
|
Ready mix concreting of pile on 23-02-23 |
|
|
|
Com. Bldg. 24th pile boring on 24-02-23 |
|
Ready mix concreting of pile on 24-02-23 |
|
|
|
Com. Bldg. 27th pile boring on 25-02-23 |
|
Ready mix concreting of pile on 25-02-23 |
|
|
|
Com. Bldg. 30th pile boring on 26-02-23 |
|
Ready mix concreting of pile on 26-02-23 |
|
|
|
Com. Bldg. 33 pile boring on 27-02-23 |
|
Ready mix concreting of pile on 27-02-23 |
|
|
|
Com. Bldg. 36 Pile Boring on 28-02-23 |
|
Ready mix concreting of pile on 28-02-23 |
|
|
|
Com. Bldg. 39 pile boring on 2-03-23 |
|
Ready mix concreting of pile on 2-03-23 |
|
|
|
Com. Bldg. 41 Pile Boring on 3-03-23 |
|
Ready mix concreting of pile on 3-03-23 |
|
|
|
Com. Bldg. 44 pile boring on 5-03-23 |
|
Ready mix concreting of pile on 5-03-23 |
|
|
|
Com. Bldg. 45 Pile Boring on 6-03-23 |
|
Re-bar arrived at site on 6-03-23 |
Today Less pile bored due to winch m/c. Problem. |
|
|
Com. Bldg. 46 Pile Boring on 7-03-23 |
|
Ready mix concreting of pile on 7-03-23 |
|
|
|
Com. Bldg. 49 Pile Boring on 8-03-23 |
|
Ready mix concreting of pile on 8-03-23 |
|
|
|
Com. Bldg. 50 Pile Boring on 9-03-23 |
|
Ready mix concreting of pile on 9-03-23 |
|
|
|
Com. Bldg. 52 Pile Boring on 10-03-23 |
|
Ready mix concreting of pile on 10-03-23 |
|
|
|
Com. Bldg. 55 pile boring on 11-03-23 |
|
Ready mix concreting of pile on 11-03-23 |
|
|
|
Com. Bldg. 57 Pile Boring on 12-03-23 |
|
Ready mix concreting of pile on 12-03-23 |
|
|
|
Com. Bldg. 60 Pile Boring on 13-03-23 |
|
Ready mix concreting of pile on 13-03-23 |
|
|
|
Com. Bldg. 63 Pile Boring on 14-03-23 |
|
Ready mix concreting of pile on 14-03-23 |
|
|
|
Com. Bldg. 66 Pile Boring on 16-03-23 |
|
Ready mix concreting of pile on 16-03-23 |
Yesterday no pile driving due to RMC supplier payment |
|
|
Com. Bldg. 69 Pile Boring on 17-03-23 |
|
Ready mix concreting of pile on 17-03-23 |
|
|
|
Guard House 2nd pile Boring on 19-03-23 |
|
Guard House pile concreting by RMC on 19-03-23 |
|
|
|
Guard House 6th pile Boring on 21-03-23 |
|
Ready mix concreting of pile on 21-03-23 |
|
|
|
Earth cutting for Pile head breaking on 24-03-23 |
|
Pile head breaking on 24-03-23 |
|
|
|
Cantg. Dor. Bldg. 2nd pile boring on 25-03-23 |
|
Ready mix concreting of pile on 25-03-23 |
|
|
|
Dorm. Bldg. 4th pile boring on 26-03-23 |
|
Ready mix concreting of pile on 26-03-23 |
|
|
|
Pile head breaking on 27-03-23 |
|
Pile cap earth cutting on 27-03-23 |
|
|
|
Earth cutting for Pile head breaking on 28-03-23 |
|
Pile head breaking on 28-03-23 |
|
|
|
Dorm. Bldg. 7th pile boring on 29-03-23 |
|
MD Sir went to bogura for NH site visit on 29-03-23 |
|
|
|
Earth cutting and pile head breaking on 30-03-23 |
|
Dorm. Bldg. 10th pile concreting on 30-03-23 |
|
|
|
Dorm. Bldg. 12th pile boring on 31-03-23 |
|
Ready mix concreting of pile on 31-03-23 |
|
|
|
Dorm. Bldg. 14th pile boring on 1-04-23 |
|
Ready mix concreting of pile on 1-04-23 |
|
|
|
Dorm. Bldg. 16th pile boring on 2-04-23 |
|
Ready mix concreting of pile on 2-04-23 |
|
|
|
Dorm. Bldg. 17th pile concreting on 3-04-23 |
|
Pile head finishing for test on 3-04-23 |
|
|
|
Pile cap cc work on 4-04-23 |
|
Pile cap bottom cc casting. on 4-04-23 |
|
|
|
Dorm. Bldg. 19th pile concreting on 5-04-23 |
|
Pile cap CC work on 5-04-23 |
|
|
|
Pile cap cc complete of com. Bldg. on 6-04-23 |
|
Dorm. Bldg. 22nd pile casting on 6-04-23 |
|
|
|
Dorm. Bldg. 26th pile concreting on 7-04-23 |
|
Pile head finishing for test on 7-04-23 |
|
|
|
Dorm. Bldg. 30th pile boring on 8-04-23 |
|
Ready mix concreting of pile on 8-04-23 |
|
|
|
Com. Bldg. Pile Rebar work on 9-04-23 |
|
Dorm. Bldg. 32nd pile concreting on 9-04-23 |
|
|
|
Dorm. Bldg. 34th pile concreting on 10-04-23 |
|
Com. Bldg. Pile cap work on 10-04-23 |
|
|
|
Dorm. Bldg. 37th pile boring on 12-04-23 |
|
Ready mix concreting on 12-04-23 |
|
|
|
Com. Bldg. Pile cap casting on 13-04-23 |
|
Dorm. Bldg 38th pile casting on 13-04-23 |
pile test finish |
Dorm. Bldg pile work finish |
|
Pile cap work on 14-04-23 |
|
Pile cap rebar work on 14-04-23 |
|
|
|
Pile Cap rebar binding on 15-04-23 |
|
Pile Cap concreting. on 15-04-23 |
|
|
|
Comp. Bldg. Pile cap casting on 16-04-23 |
|
Pile Cap concreting. on 16-04-23 |
|
|
|
Pile cap casting on 17-04-23 |
|
Com. Bldg. Pile cap casting on 17-04-23 |
|
|
|
Pile cap concreting on 18-04-23 |
|
Com. Bldg. 20th pile cap casting complet on 18-04-23 |
|
|
|
Comp. Bldg. Back filling on 19-04-23 |
|
Back filling and levelling dressing. on 19-04-23 |
|
|
|
C.C work at GB Bottom of comp. Bldg. on 29-04-23 |
|
Comp. Bldg. C.C concreting on 29-04-23 |
19-28 April work stopped due to Eid Vacation |
|
|
Comp. Bldg. CC casting at GB Bottom on 30-04-23 |
|
C.C concreting on 30-04-23 |
|
|
|
Dorm. Bldg. Earth cutting for PH Breakin on 2-05-23 |
|
Comp. Bldg. C.C concreting on 2-05-23 |
Yesterday work stopped due to May day |
|
|
Comp. Bldg. GB Re-bar work on 3-05-23 |
|
GB Re-bar work on 3-05-23 |
|
|
|
Re-bar work for GB of comp. Bldg. on 4-05-23 |
|
GB Re-bar work on 4-05-23 |
|
|
|
Comp. Bldg. GB Re-bar work on 5-05-23 |
|
MD Sir visit to site on 5-05-23 |
|
|
|
Comp. GB Shuttering on 6-05-23 |
|
Earth cutting for dorm. Bldg. on 6-05-23 |
|
|
|
Dorm. Bldg. Pile head breaking on 7-05-23 |
|
Comp. GB Shuttering on 7-05-23 |
|
|
|
Comp. Bldg. GB Shuttering work on 8-05-23 |
|
Gate pile Cap cc work on 8-05-23 |
|
|
|
G.House Pile cap work on 9-05-23 |
|
Pule head finishing for test on 9-05-23 |
|
|
|
Dorm. Bldg. pile head breaking on 10-05-23 |
|
Pile head breaking on 10-05-23 |
|
|
|
Pile cap bottom cc work of Dorm. Bldg on 11-05-23 |
|
Pile cap CC work on 11-05-23 |
|
|
|
Comp. Bldg. GB casting work on 12-05-23 |
|
Gate house pile cap casting on 12-05-23 |
|
|
|
Com. GB Shuttering on 13-05-23 |
|
Re-bar work on 13-05-23 |
|
|
|
Comp. Bldg. GB Shuttering work on 14-05-23 |
|
GB Shuttering work on 14-05-23 |
|
|
|
Dorm Bldg pile head breaking on 15-05-23 |
|
Com Bldg GB Shuttering on 15-05-23 |
|
|
|
Comp. Bldg. GB casting work on 16-05-23 |
|
GB Concreting on 16-05-23 |
|
|
|
Dorm Bldg pile cap bottom cc casting on 17-05-23 |
|
CC Casting on 17-05-23 |
|
|
|
Guard House GB Casting on 18-05-23 |
|
GB Casting on 18-05-23 |
|
|
|
Pile load test on 19-05-23 |
|
Pile integrity test on 19-05-23 |
|
|
|
Civil worker on 21-05-23 |
|
Sand filling on 21-05-23 |
|
|
|
Civil worker on 22-05-23 |
|
Dorm. Bldg. Pile cap rebar binding on 22-05-23 |
|
|
|
Dorm Bldg pile cap rebar binding on 23-05-23 |
|
Pile cap rebar work on 23-05-23 |
|
|
|
Comp. Bldg. Column shuttering on 24-05-23 |
|
Dorm. Bldg. Pile cap rebar binding on 24-05-23 |
|
|
|
Dorm. Bldg pile cap work on 25-05-23 |
|
Comp. Bldg column work on 25-05-23 |
|
|
|
Dorm. Bldg pile cap work on 26-05-23 |
|
Comp. Bldg column shuttering on 26-05-23 |
|
|
|
Dorm. Bldg pile cap casting on 28-05-23 |
|
Comp. Bldg column casting on 28-05-23 |
|
|
|
Dorm.Bldg. pile cap casting on 29-05-23 |
|
Pile Cap concreting. on 29-05-23 |
|
|
|
Comp. Bldg. Column casting on 30-05-23 |
|
Gate house Brick work on 30-05-23 |
|
|
|
Civil worker on 31-05-23 |
|
Comp. Bldg. Column shutter on 31-05-23 |
|
|
|
Comp. Bldg. Slab beam line shuttering on 1-06-23 |
|
Gate house Brick work on 1-06-23 |
|
|
|
Comp. Bldg. Stair shuttering on 2-06-23 |
|
Gate house Brick work on 2-06-23 |
Due to RMC plant disturbed Comp bldg column could not finish yesterday |
|
|
Comp. Bldg. Slab beam line shuttering on 3-06-23 |
|
Dorm. Bldg. GB Bottom CC work on 3-06-23 |
|
|
|
Comp. Bldg. Slab beam line shuttering on 4-06-23 |
|
Dorm. Bldg. Rebar work for GB on 4-06-23 |
|
|
|
Comp. Bldg. Slab beam shuttering on 5-06-23 |
|
1st flight stair casting on 5-06-23 |
|
|
|
Comp. Bldg. Slab and beam shuttering on 6-06-23 |
|
Gate house Brick work on 6-06-23 |
|
|
|
Dorm. Bldg GB Rebar work on 7-06-23 |
|
Comp. Bldg. Slab beam shuttering on 7-06-23 |
|
|
|
Comp. Bldg. Slab and beam shuttering on 8-06-23 |
|
Dorm. GB work on 8-06-23 |
|
|
|
Comp. Bldg. Slab beam shuttering on 9-06-23 |
|
Dorm. Bldg. GB shuttering on 9-06-23 |
|
|
|
Dorm. Bldg GB shutter and rebar work on 10-06-23 |
|
Comp. Bldg. Slab beam shuttering on 10-06-23 |
|
|
|
Comp. Bldg. Slab beam shuttering on 11-06-23 |
|
Comp. Bldg. Rebar work on 11-06-23 |
|
|
|
Comp. Bldg. Slab beam shuttering on 12-06-23 |
|
Dorm. Bldg. GB shuttering on 12-06-23 |
|
|
|
Dorm. Bldg. GB Casting on 13-06-23 |
|
Com. Bldg. Slab shuttering on 13-06-23 |
|
|
|
Comp. Bldg. Slab beam shuttering on 15-06-23 |
|
Gate house work on 15-06-23 |
|
|
|
Comp. Bldg. Slab beam shuttering and Reb on 16-06-23 |
|
Gate house column shuttering work on 16-06-23 |
|
|
|
Gate House column casting on 18-06-23 |
|
Dorm. Bldg. Column casting on 18-06-23 |
|
|
|
Comp. Bldg. Slab beam shuttering and rod on 19-06-23 |
|
Gate house work on 19-06-23 |
|
|
|
Comp. Bldg. Slab shuttering and Rod bind on 20-06-23 |
|
Dorm. Bldg. Column casting on 20-06-23 |
|
|
|
Comp. Bldg. Slab Ready for Concrete on 22-06-23 |
|
Comp. Bldg. Slab shutter and Rebar work on 22-06-23 |
|
|
|
Dorm. Bldg. Column Casting on 23-06-23 |
|
Gate House Lintel casting on 23-06-23 |
|
|
|
Gate House Slab shuttering and rod bindi on 25-06-23 |
|
Gate House work on 25-06-23 |
|
|
|
Com. Bldg. 1st floor slab casting on 27-06-23 |
|
Comp. Bldg. Slab casting complete on 27-06-23 |
|
|
|
Comp. Bldg. 1st floor column Rebar work on 4-07-23 |
|
Gate House work on 4-07-23 |
Project was closed 6 days due to Eid vacation |
|
|
Comp Bldg-1st floor Column Re-bar work on 6-07-23 |
|
Comp Bldg-1st floor Column Re-bar work on 6-07-23 |
|
|
|
Comp. Bldg. 1st floor column work on 7-07-23 |
|
Comp. Bldg. 1st floor column rebar work on 7-07-23 |
|
|
|
Civil Manpower on 8-07-23 |
|
shutter opening on 8-07-23 |
|
|
|
Civil worker on 9-07-23 |
|
Shuttering work on 9-07-23 |
|
|
|
Gate House Slab casting on 11-07-23 |
|
Gate House Slab Casting complete on 11-07-23 |
|
|
|
Comp. Bldg. Slab shutter opening on 12-07-23 |
|
Comp. Bldg. 1st floor column casting on 12-07-23 |
|
|
|
Comp. Bldg. 1st floor column work on 13-07-23 |
|
Comp. Bldg 1st floor column casting on 13-07-23 |
|
|
|
Comp. Bldg. 1st floor column work on 14-07-23 |
|
Comp. Bldg 1st floor roof slab work on 14-07-23 |
|
|
|
Comp. Bldg. 1st flight stair casting on 16-07-23 |
|
Comp. Bldg 2nd floor shuttering on 16-07-23 |
|
|
|
Comp. Bldg. Slab beam shuttering on 17-07-23 |
|
Comp. Bldg. 2nd floor Slab beam shutteri on 17-07-23 |
|
|
|
Comp. Bldg. 2nd Floor Slab beam shutteri on 18-07-23 |
|
Dorm. Bldg. Sand filling on 18-07-23 |
|
|
|
Materials arrive at site for road on 19-07-23 |
|
Comp. Bldg. 2nd floor slab shuttering wo on 19-07-23 |
|
|
|
Dorm. Bldg. Floor levelling work on 20-07-23 |
|
Comp. Bldg. 2nd Slab beam shuttering on 20-07-23 |
|
|
|
Comp. Bldg. 2nd Floor Slab beam shutteri on 21-07-23 |
|
Comp. Bldg. GF Brick work on 21-07-23 |
|
|
|
Sub-station-Electrical Pipe Work on 22-07-23 |
|
Road Sub-base work on 22-07-23 |
Substation Roof Slab Electrical pipe work delayed due to BBS not completed slab shuttering and re-bar work |
|
|
Civil Manpower on 23-07-23 |
|
Road Sub-base work on 23-07-23 |
|
|
|
Dorm. Bldg. 1st floor shuttering work on 24-07-23 |
|
Comp. Bldg GF Brick work on 24-07-23 |
|
|
|
Comp. Bldg. on 25-07-23 |
|
Dormitory Bldg. on 25-07-23 |
|
|
|
Dorm. Bldg. 1st flight stair on 26-07-23 |
|
Comp. Bldg. 2nd floor work on 26-07-23 |
|
|
|
Foundation brick work at scale station on 27-07-23 |
|
Dorm. Bldg shuttering work on 27-07-23 |
|
|
|
Comp. Bldg. 2nd Floor rebar work on 28-07-23 |
|
Dorm. Bldg shuttering work on 28-07-23 |
|
|
|
Comp. Bldg Rebar work on 31-07-23 |
|
Road work on 31-07-23 |
Gate House Handover |
|
|
Rebar binding of Scale on 2-08-23 |
|
Tie column work at brick wall on 2-08-23 |
|
|
|
Comp. 2nd floor slab concreting on 4-08-23 |
|
Comp. Bldg. concreting work complete on 4-08-23 |
Casting start on 04-08-2023 5:30PM and finish on 05-08-2023 5:02AM |
|
|
Comp.Bldg GF Brick work on 6-08-23 |
|
Dormitory 1st Floor Re-bar work on 6-08-23 |
|
|
|
Comp-GF-Brick Work on 7-08-23 |
|
Due to Rain no work on 7-08-23 |
Due to Rain no work afternoon and night |
|
|
No work due to rain on 8-08-23 |
|
Dormitory Slab Electrical Pipe Laying on 8-08-23 |
No work due to rain |
|
|
Dormitory Slab Electric Pipe Laying on 9-08-23 |
|
Comp.Bldg.GF Brick work on 9-08-23 |
Dormitory Slab Concreting not possible due to rain |
|
|
Dormitory GF Stair 2nd flight concrete c on 10-08-23 |
|
Dormitory 1st Floor Slab concrete comple on 10-08-23 |
|
|
|
Weighing bridge re-bar work on 11-08-23 |
|
Road Sub-base work on 11-08-23 |
|
|
|
Comp-Parapet Brick-work on 14-08-23 |
|
Sub-base-Khoa unloading on 14-08-23 |
|
|
|
Comp-GF Column Concreting on 16-08-23 |
|
Road-Excavation-box cutting on 16-08-23 |
Project was closed on 15 Aug due to National Mourning day. |
|
|
Sub-base Compaction on 17-08-23 |
|
Comp-Parapet Brick-work on 17-08-23 |
|
|
|
Comp-GF Brickwork on 18-08-23 |
|
Road-Sub-basework on 18-08-23 |
|
|
|
Comp-1st Floor-Shutter Removing on 20-08-23 |
|
Gate House-Door Frame Fixing on 20-08-23 |
|
|
|
Material stock for Road Sub-base on 21-08-23 |
|
Road-Sub-base work on 21-08-23 |
|
|
|
Comp-1st Floor-Brickwork on 22-08-23 |
|
Road-Box cutting on 22-08-23 |
|
|
|
Weighing Bridge Concreting on 23-08-23 |
|
Dormatory Column Concreting on 23-08-23 |
|
|
|
Comp. Bldg. 1st floor brick wall on 24-08-23 |
|
Road work on 24-08-23 |
|
|
|
Dormitory column casting on 25-08-23 |
|
Column casting work on 25-08-23 |
|
|
|
Comp. Bldg plaster work on 26-08-23 |
|
Dormitory bldg. Column casting on 26-08-23 |
|
|
|
Comp. Bldg Column casting on 27-08-23 |
|
Comp. Bldg. GF plaster work on 27-08-23 |
|
|
|
Comp. Bldg. Sanitary work on 29-08-23 |
|
Dorm. Bldg. 2nd floor shuttering on 29-08-23 |
|
|
|
Dorm. Bldg. 1st flight stair casting on 30-08-23 |
|
Road Sub-base work on 30-08-23 |
|
|
|
Gate House floor casting on 1-09-23 |
|
Road Sub-base work on 1-09-23 |
|
|
|
Dorm. Bldg. 2nd floor shuttering work on 3-09-23 |
|
Road work on 3-09-23 |
|
|
|
Comp. Bldg. 1st floor brick wall on 4-09-23 |
|
Dorm. Bldg. 2nd floor Shuttering work on 4-09-23 |
|
|
|
Dorm. Bldg. 2nd floor shuttering work on 6-09-23 |
|
Anchor bolt fitting at scale on 6-09-23 |
|
|
|
Dorm. Bldg. 2nd floor Rebar work on 7-09-23 |
|
Comp. Bldg 1st floor sanitary work on 7-09-23 |
|
|
|
Dorm. Bldg. 2nd floor rebar work on 8-09-23 |
|
Road Sub-base work on 8-09-23 |
|
|
|
Dorm. Bldg. 2nd floor rebar work on 9-09-23 |
|
Comp. Bldg. FF Brick work on 9-09-23 |
|
|
|
Comp. Bldg. 2nd Floor work on 10-09-23 |
|
Comp. Bldg. FF Brick work on 10-09-23 |
|
|
|
Comp. Bldg. Plaster work on 11-09-23 |
|
Comp. Bldg floor GF compaction on 11-09-23 |
|
|
|
Dorm. Bldg. 1st floor brick work on 13-09-23 |
|
Road work on 13-09-23 |
|
|
|
Comp. Bldg work on 15-09-23 |
|
Comp. GF Cushion concreting on 15-09-23 |
|
|
|
Dorm. Bldg. 2nd floor concreting work on 16-09-23 |
|
Comp. Bldg. Roof top concreting work on 16-09-23 |
|
|
|
Comp. Bldg FF plastr wok on 19-09-23 |
|
GF cushion wok on 19-09-23 |
|
|
|
Comp. Bldg. Plaster work on 20-09-23 |
|
Dormitory GF-Brick Work on 20-09-23 |
|
|
|
Dorm. Bldg GF Brick work on 21-09-23 |
|
Comp. Bldg 1st fplaster work on 21-09-23 |
|
|
|
Dorm. Bldg GF Brick work on 22-09-23 |
|
Dorm. Brick work on 22-09-23 |
|
|
|
Dorm.Bldg. GF brick work on 23-09-23 |
|
Dorm.Bldg brick work on 23-09-23 |
|
|
|
Dorm.Bldg. GF brick work on 25-09-23 |
|
Dorm. Bldg Brick work on 25-09-23 |
|
|
|
Gats house tiles work on 26-09-23 |
|
Weight scale concretiing on 26-09-23 |
|
|
|
Comp. Bldg outside scaffolding on 28-09-23 |
|
Earth cutting power cable laying on 28-09-23 |
|
|
|
Comp. GF concreting on 29-09-23 |
|
Comp. Bldg. GF casting on 29-09-23 |
|
|
|
Earth cutting Electric line on 1-10-23 |
|
Comp. Roof top parapet work on 1-10-23 |
|
|
|
Dorm. Stair room column shuttering on 4-10-23 |
|
Dorm. 1st floor brick work on 4-10-23 |
|
|
|
Dorm. Bldg. on 6-10-23 |
|
Dorm. Bldg. 1st floor brick work on 6-10-23 |
|
|
|
Dorm. 1st floor brick work on 7-10-23 |
|
Dorm. Bldg Brick work on 7-10-23 |
|
|
|
Comp. Bldg. Prepared for Out side plaste on 8-10-23 |
|
Dorm. Bldg. Roof top column casting on 8-10-23 |
|
|
|
Comp. Bldg. Outside plaster work on 9-10-23 |
|
Comp. Bldg. GF casting on 9-10-23 |
|
|
|
Dorm. Bldg. Brick work on 10-10-23 |
|
Comp. Bldg. Outside plaster work on 10-10-23 |
|
|
|
Comp. Bldg. Outside plaster work on 11-10-23 |
|
Road work on 11-10-23 |
|
|
|
Comp. Bldg. Outside plaster work on 13-10-23 |
|
Dorm. Bldg. Roof top Column work on 13-10-23 |
|
|
|
Road work on 14-10-23 |
|
Comp. Bldg. Outside plaster work on 14-10-23 |
|
|
|
Comp. Bldg. Outside plaster work on 15-10-23 |
|
Road work on 15-10-23 |
|
|
|
Comp. Bldg. Outside plaster work on 16-10-23 |
|
Comp. Bldg. GF casting on 16-10-23 |
|
|
|
Comp. Bldg. Outside plaster work on 18-10-23 |
|
Road casting work on 18-10-23 |
|
|
|
Comp. Building-Outside Plastering on 20-10-23 |
|
Comp. Building-Outside Plastering on 20-10-23 |
|
|
|
Dorm. Bldg. 2nd floor column work on 25-10-23 |
|
Ceiling plaster on 25-10-23 |
|
|
|
Comp. Bldg. Door shutter work on 26-10-23 |
|
Comp. Bldg. on 26-10-23 |
|
|
|
Dormitory-GF-Ceiling Plastering on 27-10-23 |
|
Electrical Cable Received on 27-10-23 |
|
|
|
Gate House door fixed on 31-10-23 |
|
PPR Pipe Received on 31-10-23 |
|
|
|
Dorm. Bldg. Ceiling Plaster on 1-11-23 |
|
Comp. Bldg. GF Tiles work on 1-11-23 |
|
|
|
Dorm. Bldg. 2nd floor concreting work on 2-11-23 |
|
Dorm. Bldg. Plaster work on 2-11-23 |
|
|
|
Dorm. Bldg. 2nd floor column work on 3-11-23 |
|
Power cable laying work on 3-11-23 |
|
|
|
Dorm. Bldg. 2nd floor shuttering work on 6-11-23 |
|
Sanitary group cutting on 6-11-23 |
|
|
|
Gate House Thai work on 7-11-23 |
|
Dormitory canopy on 7-11-23 |
|
|
|
Dorm. Bldg. 3rd floor slab shuttering on 8-11-23 |
|
Gate roof top water proofing casting on 8-11-23 |
|
|
|
Dorm. Bldg. 3rd floor shuttering work on 9-11-23 |
|
Dorm. Bldg. GF sand khoa cushion on 9-11-23 |
|
|
|
Dorm. Bldg. GF Concreting on 10-11-23 |
|
Gate House Painting on 10-11-23 |
|
|
|
Dormitory-3rd Floor Slab Re-bar Work on 18-12-23 |
|
Dormitory-3rd Floor Slab Electrical Pipe on 18-12-23 |
|
|
|
Dormitory-3rd Floor Slab Concreting on 23-12-23 |
|
Dormitory-3rd Floor Slab Concreting on 23-12-23 |
|
|
|
Comp.Bldg. Front View on 2-02-24 |
|
Comp.Bldg. Roof Top on 2-02-24 |
Comprehensive Building Handover |
|
|
Dormitory-Outside on 26-02-24 |
|
Dormitory-Inside-Toilet Area on 26-02-24 |
Dormitory-two story handover |
|
|
Road-Re-bar work on 5-04-24 |
|
Road-RCC on 5-04-24 |
RCC-Car Road Handover |
|
|
Electrical Work on 8-04-24 |
|
Electrical Work on 8-04-24 |
|
|
|
Dormitory-2nd Floor Painting on 23-04-24 |
|
Dormitor-2nd Floor-Corridor on 23-04-24 |
Project closed from 09 to 16 April, 2024 due to Eid-ul Fitre |
|