MONTHLY PROGRESS REPORT

From 1-April-2024 to 23-April-2024
Project Code: 21Name:New Hope Animal Nutrition Plant Bogura
Client: New Hope Contractor:Sarker Steel Ltd.
Progress as on: 23-April-2024
WBSWork Description
Total QuantityUpto 31-03-24This MonthTotal Done Schedule StartSchedule FinishActual Finish
3.2.5.2.8 Dormitory-1st Floor-False Ceiling-Partit sum 0% 100% 100% 29-12-23 04-01-24 26-02-24
3.2.5.3.1 Dormitory-2nd Floor-Brickwork 111m2 0% 100% 100% 08-01-24 17-01-24 23-04-24
3.2.5.3.2 Dormitory-2nd Floor-Door Frame fixing 0nos 0% 100% 100% 18-01-24 20-01-24 23-04-24
3.2.5.3.3 Dormitory-2nd Floor-Window Grill Fixing 0nos 0% 100% 100% 18-01-24 20-01-24 23-04-24
3.2.5.3.4 Dormitory-2nd Floor-Inside Plastering 468m2 0% 100% 100% 12-01-24 21-01-24 23-04-24
3.2.5.3.5 Dormitory-2nd Floor-Tiles Fitting 0m2 0% 100% 100% 20-01-24 28-01-24 23-04-24
3.2.5.3.6 Dormitory-2nd Floor-Door-Window fixing 0nos 0% 95% 95% 27-01-24 29-01-24 23-04-24
3.2.5.3.7 Dormitory-2nd Floor-Inside Painting m2 0% 30% 30% 18-01-24 31-01-24 23-04-24
3.2.5.3.8 Dormitory-2nd Floor-False Ceiling-Partit 0% 80% 80% 25-01-24 31-01-24 05-04-24
3.2.5.5 Dormitory-Outside Plastering 0m2 10% 90% 100% 29-12-23 22-01-24 23-04-24
3.2.5.6 Dormitory-Waterproof-Rooftop 0% 100% 100% 08-01-24 22-01-24 08-04-24
3.2.5.7 Dormitory-Outside Painting m2 0% 30% 30% 12-01-24 31-01-24 23-04-24
3.2.5.8 Dormitory-Stair Railing 0% 100% 100% 25-01-24 31-01-24 23-04-24
3.2.6.3 Dormitory-2nd Floor-Water-Electrical 0 0% 90% 90% 15-01-24 29-01-24 23-04-24
4.1 Road--Sub-grade Compaction 4817m2 75% 25% 100% 11-07-23 03-01-24 05-04-24
4.2 Sub-base-Car Road-400m 4817m2 75% 25% 100% 06-08-23 10-01-24 05-04-24
4.3 Road-Sub-base-Pedestrain 0m2 0% 80% 80% 19-11-23 17-01-24 23-04-24
4.4 RCC-Car Road 4817m2 4% 96% 100% 26-12-23 24-01-24 05-04-24
6.1 Hydropower-Main Workshop 0 0% 90% 90% 08-12-23 28-01-24 08-04-24
6.2 Production Buldg-Hydropower installation 1sum 0% 90% 90% 18-12-23 28-01-24 08-04-24
6.4.2 Sub-station-Wall Electric Pipe Work 0m 0% 100% 100% 16-12-23 23-12-23 08-04-24
6.4.3 Electrical Cable/ Wiring 0m 0% 100% 100% 23-12-23 22-01-24 08-04-24


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Road-Re-bar work on 5-04-24Road-RCC on 5-04-24
RCC-Car Road Handover
Electrical Work on 8-04-24Electrical Work on 8-04-24
Dormitory-2nd Floor Painting on 23-04-24Dormitor-2nd Floor-Corridor on 23-04-24
Project closed from 09 to 16 April, 2024 due to Eid-ul Fitre