Progress as on: 23-April-2024 |
WBS | Work Description |
Total Quantity | Upto 16-04-24 | This Week | Total Done |
Schedule Start | Schedule Finish | Avtual Finish |
3.2.5.2.8 |
Dormitory-1st Floor-False Ceiling-Partit |
sum |
0% |
100% |
100% |
29-12-23 |
04-01-24 |
26-02-24 |
3.2.5.3.1 |
Dormitory-2nd Floor-Brickwork |
111m2 |
0% |
100% |
100% |
08-01-24 |
17-01-24 |
23-04-24 |
3.2.5.3.2 |
Dormitory-2nd Floor-Door Frame fixing |
0nos |
0% |
100% |
100% |
18-01-24 |
20-01-24 |
23-04-24 |
3.2.5.3.3 |
Dormitory-2nd Floor-Window Grill Fixing |
0nos |
0% |
100% |
100% |
18-01-24 |
20-01-24 |
23-04-24 |
3.2.5.3.4 |
Dormitory-2nd Floor-Inside Plastering |
468m2 |
0% |
100% |
100% |
12-01-24 |
21-01-24 |
23-04-24 |
3.2.5.3.5 |
Dormitory-2nd Floor-Tiles Fitting |
0m2 |
0% |
100% |
100% |
20-01-24 |
28-01-24 |
23-04-24 |
3.2.5.3.6 |
Dormitory-2nd Floor-Door-Window fixing |
0nos |
0% |
95% |
95% |
27-01-24 |
29-01-24 |
23-04-24 |
3.2.5.3.7 |
Dormitory-2nd Floor-Inside Painting |
m2 |
0% |
30% |
30% |
18-01-24 |
31-01-24 |
23-04-24 |
3.2.5.5 |
Dormitory-Outside Plastering |
0m2 |
10% |
90% |
100% |
29-12-23 |
22-01-24 |
23-04-24 |
3.2.5.7 |
Dormitory-Outside Painting |
m2 |
0% |
30% |
30% |
12-01-24 |
31-01-24 |
23-04-24 |
3.2.6.3 |
Dormitory-2nd Floor-Water-Electrical |
0 |
0% |
90% |
90% |
15-01-24 |
29-01-24 |
23-04-24 |
4.3 |
Road-Sub-base-Pedestrain |
0m2 |
0% |
80% |
80% |
19-11-23 |
17-01-24 |
23-04-24 |