WEEKY PROGRESS REPORT

From 17-April-2024 to 23-April-2024
Project Code: 21Name:New Hope Animal Nutrition Plant Bogura
Client: New Hope Contractor:Sarker Steel Ltd.
Progress as on: 23-April-2024
WBSWork Description
Total QuantityUpto 16-04-24This WeekTotal Done Schedule StartSchedule FinishAvtual Finish
3.2.5.2.8 Dormitory-1st Floor-False Ceiling-Partit sum 0% 100% 100% 29-12-23 04-01-24 26-02-24
3.2.5.3.1 Dormitory-2nd Floor-Brickwork 111m2 0% 100% 100% 08-01-24 17-01-24 23-04-24
3.2.5.3.2 Dormitory-2nd Floor-Door Frame fixing 0nos 0% 100% 100% 18-01-24 20-01-24 23-04-24
3.2.5.3.3 Dormitory-2nd Floor-Window Grill Fixing 0nos 0% 100% 100% 18-01-24 20-01-24 23-04-24
3.2.5.3.4 Dormitory-2nd Floor-Inside Plastering 468m2 0% 100% 100% 12-01-24 21-01-24 23-04-24
3.2.5.3.5 Dormitory-2nd Floor-Tiles Fitting 0m2 0% 100% 100% 20-01-24 28-01-24 23-04-24
3.2.5.3.6 Dormitory-2nd Floor-Door-Window fixing 0nos 0% 95% 95% 27-01-24 29-01-24 23-04-24
3.2.5.3.7 Dormitory-2nd Floor-Inside Painting m2 0% 30% 30% 18-01-24 31-01-24 23-04-24
3.2.5.5 Dormitory-Outside Plastering 0m2 10% 90% 100% 29-12-23 22-01-24 23-04-24
3.2.5.7 Dormitory-Outside Painting m2 0% 30% 30% 12-01-24 31-01-24 23-04-24
3.2.6.3 Dormitory-2nd Floor-Water-Electrical 0 0% 90% 90% 15-01-24 29-01-24 23-04-24
4.3 Road-Sub-base-Pedestrain 0m2 0% 80% 80% 19-11-23 17-01-24 23-04-24


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Dormitory-2nd Floor Painting on 23-04-24Dormitor-2nd Floor-Corridor on 23-04-24
Project closed from 09 to 16 April, 2024 due to Eid-ul Fitre