MONTHLY PROGRESS REPORT

From 1-April-2023 to 9-April-2023
Project Code: 59Name:Cityscape Tower-Retrofitting
Client: Cityscape Contractor:Cityscape International Ltd.
Progress as on: 9-April-2023
WBSWork Description
Total QuantityUpto 31-03-23This MonthTotal Done Schedule StartSchedule FinishActual Finish
01.1 Retrofit-Basement-3-Column-Lift 1sum 98% 2% 100% 26-12-22 15-01-23 09-04-23
01.2 Retrofit-Basement-2-Column 1sum 82% 18% 100% 16-01-23 05-02-23 09-04-23
01.3 Retrofit-Basement-1-Column 1sum 96% 1% 97% 06-02-23 25-02-23 09-04-23


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
B-2-Column retrofit shuttering on 2-04-23B2-Column retrofit concreting on 2-04-23
B2-Column retrofit shutter removing on 5-04-23B-2-Column retrofit curingon 5-04-23
B2-Column Retrofit-Shutter removing on 9-04-23B2-Column Retrofit-Curingon 9-04-23