Return Main Menu

DAILY PROGRES REPORT

Project:Cityscape Tower-Retrofitting Project Code: 59 Date9-April-2023
Client: Cityscape Report033 DaySunday
Contractor:Cityscape International Ltd. ClimateSunny
Temperature26-37C
Manpower
SNDescriptionNos
01Retrofit-Mason1
02Retrofit-Helper2
TOTAL 3
WBSWork Description Progress as on: 9-April-2023
Total QtyToday Done (%)Total Done (%)StartFinish
01.1 Retrofit-Basement-3-Column-Lift 1sum 2 100 26-12-22 15-01-23
01.2 Retrofit-Basement-2-Column 1sum 10 100 16-01-23 05-02-23
01.3 Retrofit-Basement-1-Column 1sum 1 97 06-02-23 25-02-23
Site Photographs
B2-Column Retrofit-Shutter removingB2-Column Retrofit-Curing
Site Description
Site Instruction