DAILY PROGRES REPORT |
Project: | Cityscape Tower-Retrofitting | Project Code: | 59 | Date | 9-April-2023 | ||
Client: | Cityscape | Report | 033 | Day | Sunday | ||
Contractor: | Cityscape International Ltd. | Climate | Sunny | ||||
Temperature | 26-37C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Retrofit-Mason | 1 |
02 | Retrofit-Helper | 2 |
TOTAL | 3 |
WBS | Work Description | Progress as on: 9-April-2023 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
01.1 | Retrofit-Basement-3-Column-Lift | 1sum | 2 | 100 | 26-12-22 | 15-01-23 | |
01.2 | Retrofit-Basement-2-Column | 1sum | 10 | 100 | 16-01-23 | 05-02-23 | |
01.3 | Retrofit-Basement-1-Column | 1sum | 1 | 97 | 06-02-23 | 25-02-23 |
Site Photographs | |
B2-Column Retrofit-Shutter removing | B2-Column Retrofit-Curing |
Site Description | |
Site Instruction | |