Return Main Menu

WEEKY PROGRESS REPORT

From 11-October-2024 to 17-October-2024
Project Code: 31Name:New Hope Agrotech-Munshiganj
Client: New Hope Agrotech BD Ltd. Contractor:Sarker Steel Ltd.
Progress as on: 17-October-2024
WBSWork Description
Total QuantityUpto 10-10-24This WeekTotal Done Schedule StartSchedule FinishAvtual Finish
03.5.1 Pile Load Test-PDA-Pile Development 3nos 0% 100% 100% 10-10-24 13-10-24 16-10-24
04.01 Excavation 1982m3 62% 16% 78% 08-10-24 06-11-24 16-10-24
04.02 Pile head breaking 79nos 63% 19% 82% 10-10-24 08-11-24 17-10-24
04.03.1 Pile Cap-Lean Concrete 18nos 29% 38% 67% 17-10-24 11-11-24 16-10-24
04.03.3 Pile Cap-Brick Shuttering 18nos 0% 17% 17% 20-10-24 13-11-24 13-10-24
04.04.1 Tank Base-Lean Concrete 2Nos 20% 60% 80% 07-11-24 08-11-24 16-10-24
04.04.5 Tank Base-Side Brick Shutter 2nos -50% 135% 85% 12-11-24 13-11-24 17-10-24


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Dewatering on 11-10-24Pile head breaking on 11-10-24
Checking before pile cap lean concreting on 12-10-24Pile cap lean concreting on 12-10-24
Due to rain work started late
Pile cap side brick shuttering on 13-10-24Earth excavation manually on 13-10-24
Wooden shore piling 14 nos.
Earth excavation on 14-10-24Shoring on 14-10-24
Wooden pile driving 41 nos.
Inspection before CC at -5200 mm on 15-10-24CC at level -5200 finished on 15-10-24
Excavation, brick-shuttering, steel shut on 16-10-24Pile Cap Lean concreting on 16-10-24
Pile head breaking on 17-10-24Water tank base brick wall shuttering on 17-10-24