WEEKY PROGRESS REPORT |
From 11-October-2024 to 17-October-2024 | ||||
Project Code: | 31 | Name: | New Hope Agrotech-Munshiganj | |
Client: | New Hope Agrotech BD Ltd. | Contractor: | Sarker Steel Ltd. |
Progress as on: 17-October-2024 | ||||||||
WBS | Work Description | |||||||
Total Quantity | Upto 10-10-24 | This Week | Total Done | Schedule Start | Schedule Finish | Avtual Finish | ||
03.5.1 | Pile Load Test-PDA-Pile Development | 3nos | 0% | 100% | 100% | 10-10-24 | 13-10-24 | 16-10-24 |
04.01 | Excavation | 1982m3 | 62% | 16% | 78% | 08-10-24 | 06-11-24 | 16-10-24 |
04.02 | Pile head breaking | 79nos | 63% | 19% | 82% | 10-10-24 | 08-11-24 | 17-10-24 |
04.03.1 | Pile Cap-Lean Concrete | 18nos | 29% | 38% | 67% | 17-10-24 | 11-11-24 | 16-10-24 |
04.03.3 | Pile Cap-Brick Shuttering | 18nos | 0% | 17% | 17% | 20-10-24 | 13-11-24 | 13-10-24 |
04.04.1 | Tank Base-Lean Concrete | 2Nos | 20% | 60% | 80% | 07-11-24 | 08-11-24 | 16-10-24 |
04.04.5 | Tank Base-Side Brick Shutter | 2nos | -50% | 135% | 85% | 12-11-24 | 13-11-24 | 17-10-24 |
Site Photographs | |
Dewatering on 11-10-24 | Pile head breaking on 11-10-24 |
Checking before pile cap lean concreting on 12-10-24 | Pile cap lean concreting on 12-10-24 |
Due to rain work started late | |
Pile cap side brick shuttering on 13-10-24 | Earth excavation manually on 13-10-24 |
Wooden shore piling 14 nos. | |
Earth excavation on 14-10-24 | Shoring on 14-10-24 |
Wooden pile driving 41 nos. | |
Inspection before CC at -5200 mm on 15-10-24 | CC at level -5200 finished on 15-10-24 |
Excavation, brick-shuttering, steel shut on 16-10-24 | Pile Cap Lean concreting on 16-10-24 |
Pile head breaking on 17-10-24 | Water tank base brick wall shuttering on 17-10-24 |