DAILY PROGRES REPORT |
Project: | New Hope Agrotech-Munshiganj | Project Code: | 31 | Date | 17-October-2024 | ||
Client: | New Hope Agrotech BD Ltd. | Report | 157 | Day | Thursday | ||
Contractor: | Sarker Steel Ltd. | Climate | Sunny | ||||
Temperature | 25-30C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Sarker-Staff | 2 |
02 | Steel Labor | 6 |
03 | Civil Labour | 23 |
TOTAL | 31 |
WBS | Work Description | Progress as on: 17-October-2024 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
04.02 | Pile head breaking | 79nos | 6 | 82 | 10-10-24 | 08-11-24 | |
04.04.5 | Tank Base-Side Brick Shutter | 2nos | 35 | 85 | 12-11-24 | 13-11-24 |
Site Photographs | |
Pile head breaking | Water tank base brick wall shuttering |
Site Description | |
Site Instruction | |