DAILY PROGRES REPORT

Project:New Hope Agrotech-Munshiganj Project Code: 31 Date17-October-2024
Client: New Hope Agrotech BD Ltd. Report157 DayThursday
Contractor:Sarker Steel Ltd. ClimateSunny
Temperature25-30C
Manpower
SNDescriptionNos
01Sarker-Staff2
02Steel Labor6
03Civil Labour23
TOTAL 31
WBSWork Description Progress as on: 17-October-2024
Total QtyToday Done (%)Total Done (%)StartFinish
04.02 Pile head breaking 79nos 6 82 10-10-24 08-11-24
04.04.5 Tank Base-Side Brick Shutter 2nos 35 85 12-11-24 13-11-24
Site Photographs
Pile head breakingWater tank base brick wall shuttering