Labor Shed Making on 22-08-24 |
|
Labour Shed Making on 22-08-24 |
|
|
|
Sarker Management Visit on 26-08-24 |
|
Steel Labour on 26-08-24 |
|
|
|
Workshop Sheet Removing on 27-08-24 |
|
Workshop Sheet Removing on 27-08-24 |
|
|
|
Sheet removing on 28-08-24 |
|
Sheet removing on 28-08-24 |
|
|
|
Sheet removing on 29-08-24 |
|
Sheet removing on 29-08-24 |
|
|
|
Steel beam cutting on 30-08-24 |
|
Steel beam removing on 30-08-24 |
|
|
|
Fencing framing on 31-08-24 |
|
Fencing framing on 31-08-24 |
|
|
|
Outside beam removing on 1-09-24 |
|
Inside fencing on 1-09-24 |
|
|
|
Fencing work on 2-09-24 |
|
Floor cutting on 2-09-24 |
|
|
|
Brick wall dismantling on 3-09-24 |
|
Brick wall dismatling on 3-09-24 |
|
|
|
Pile Re-bar mobillized on 4-09-24 |
|
Pile Equipment mobilized on 4-09-24 |
|
|
|
Material shifting by crane on 5-09-24 |
|
Pile re-bar mobilized on 5-09-24 |
|
|
|
Steel Labour on 6-09-24 |
|
Project Status on 6-09-24 |
|
|
|
Floor and Foundation Removal on 7-09-24 |
|
Pile Re-bar work on 7-09-24 |
|
|
|
Floor,foundatn, road,tank cutting,removi on 8-09-24 |
|
Piling equipment maintenance on 8-09-24 |
|
|
|
Old short column found durring excavatio on 9-09-24 |
|
Excavation for pile mud tank on 9-09-24 |
During excavation old pile found |
|
|
Fencing after dismantling on 10-09-24 |
|
Pile mud tank brick work on 10-09-24 |
|
|
|
Ground breaking ceremony on 11-09-24 |
|
Pile mud tank complete on 11-09-24 |
|
|
|
Pile boring on 12-09-24 |
|
Pile concreting on 12-09-24 |
|
|
|
Pile cage length measuring on 13-09-24 |
|
Pile concreting on 13-09-24 |
|
|
|
Pile boring on 14-09-24 |
|
Concrete cube for test on 14-09-24 |
|
|
|
Pile boring on 15-09-24 |
|
Concrete cylinder for test on 15-09-24 |
|
|
|
Pile cage downing on 16-09-24 |
|
Road washing after pile finishing on 16-09-24 |
|
|
|
Pile boring length checking on 17-09-24 |
|
Pile concreting on 17-09-24 |
|
|
|
Pile reboring new location on 18-09-24 |
|
Pile concreting on 18-09-24 |
Pile no.15, Grid 1B relocated to a new location |
Due to existence of old pile |
|
Pile boring length checking on 19-09-24 |
|
Pile boring chisel repairing on 19-09-24 |
|
|
|
During boring old concrete-pipe found on 20-09-24 |
|
After Concrete-pipe removal boring resta on 20-09-24 |
During boring pile no.35 grid-2B |
Old concrete-MS pipe found |
|
During boring Obstacles found on 21-09-24 |
|
Pile concreting on 21-09-24 |
During boring pile no.36, grid-2B |
Obstacles found |
|
Pile boring length checking on 22-09-24 |
|
Pile concreting on 22-09-24 |
|
|
|
Rig shifting to Grid 1A on 23-09-24 |
|
Chisel broken due to obstacle on 23-09-24 |
During boring pile no.18 grid-1A |
Chisel broken due to obstacles |
|
Boring obstacle Old CC breaking on 24-09-24 |
|
Pile-57 concreting completed on 24-09-24 |
During boring pile no.53, grid-3B |
Obstacle Old Concrete found |
|
Pile cap re-bar dia checking on 25-09-24 |
|
Due to electrical line 1.5 m excavation on 25-09-24 |
Due to live electric line Grid-3 |
Excavating all pile point upto 1.5 m |
|
Pile cap re-bar dia checking on 26-09-24 |
|
Bentonite received for pile boring on 26-09-24 |
|
|
|
Excavating for pile boring obstacles on 27-09-24 |
|
Making road for reading concrete truck on 27-09-24 |
|
|
|
Pile boring depth checking on 28-09-24 |
|
Piling rig shifting on 28-09-24 |
|
|
|
Pile no.47 boring length checking on 29-09-24 |
|
Piling rig setting on 29-09-24 |
Pile no.47 of grid 3C length 22m |
Total 6 piles 22 m |
|
Piling rig shifting on 30-09-24 |
|
Pile concreting on 30-09-24 |
All pile completed |
|
|
Earth excavation on 1-10-24 |
|
Re-bar straighting on 1-10-24 |
|
|
|
Earth excavation on 2-10-24 |
|
Old base-column found during excavation on 2-10-24 |
During excavating old foundation with column found |
In Grid-1 in between C and D |
|
Obstacle RCC dismantling on 3-10-24 |
|
Earth excavation on 3-10-24 |
Dismantling RCC foundation found during excavation |
Money and Time wastage |
|
Pile Head breaking on 4-10-24 |
|
Wooden pile driving on 4-10-24 |
Due to rain work stopped |
|
|
Old base breaking on 5-10-24 |
|
Earth excavation on 5-10-24 |
|
|
|
Wooden shore pile driving on 6-10-24 |
|
Earth Excavation on 6-10-24 |
|
|
|
Earth excavation on 7-10-24 |
|
Pile head breaking on 7-10-24 |
|
|
|
Excavated earth dumping on 8-10-24 |
|
Dismantling by hydraulic breaker on 8-10-24 |
Dismantling old foundation 17 m3 |
By Hydraulic hammer |
|
Earth excavation on 9-10-24 |
|
Old base dismantling by hydraulic hammer on 9-10-24 |
Old base dismantling 11 m3 by hydraulic hammer |
|
|
Pile Load Test-PDA-Pile Development on 10-10-24 |
|
Water Reservoir Base CC-Bottom on 10-10-24 |
Old base dismantling 4 m3 by hydraulic hammer |
|
|
Dewatering on 11-10-24 |
|
Pile head breaking on 11-10-24 |
|
|
|
Checking before pile cap lean concreting on 12-10-24 |
|
Pile cap lean concreting on 12-10-24 |
Due to rain work started late |
|
|
Pile cap side brick shuttering on 13-10-24 |
|
Earth excavation manually on 13-10-24 |
Wooden shore piling 14 nos. |
|
|
Earth excavation on 14-10-24 |
|
Shoring on 14-10-24 |
Wooden pile driving 41 nos. |
|
|
Inspection before CC at -5200 mm on 15-10-24 |
|
CC at level -5200 finished on 15-10-24 |
|
|
|
Excavation, brick-shuttering, steel shut on 16-10-24 |
|
Pile Cap Lean concreting on 16-10-24 |
|
|
|
Pile head breaking on 17-10-24 |
|
Water tank base brick wall shuttering on 17-10-24 |
|
|