WEEKY PROGRESS REPORT

From 8-June-2021 to 15-June-2021
Project Code: 48Name:BTT Sales Center Purbachal
Client: Power Pac Holdings Ltd Contractor:Cityscape International Ltd.
Progress as on: 15-June-2021
WBSWork Description
Total QuantityUpto 08-06-21This WeekTotal Done Schedule StartSchedule FinishAvtual Finish
3.9 Basement-Wall and Ceiling plaster 2415m2 7% 4% 11% 30-05-21 30-07-21 15-06-21
4.1 Ground Floor-Column 57nos 93% 2% 95% 27-04-21 05-06-21 09-06-21
4.2.1 Ground Floor-Roof Slab Shutter 822m2 40% 9% 49% 03-05-21 20-06-21 15-06-21
4.2.2 Gr.Floor Roof Slab-Re-bar Work 160nos 0% 2% 2% 15-06-21 03-07-21 15-06-21
4.4 Ground Floor-Stair Case 2nos 31% 49% 80% 25-05-21 05-07-21 15-06-21


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Ground Floor Stair Re-bar work on 9-06-211st floor Slab Shutteringon 9-06-21
Honourable RAJUK Charman Visit on 12-06-211st floor Slab Shutteringon 12-06-21
Ground Floor Lift Core Shuttering on 15-06-211st floor Slab Shutteringon 15-06-21