Total Duration: |
192 |
days |
Total Working Days: |
45 |
Total Manpower: |
2484 |
|
|
Planning Progress = 98% |
Acual Progress = 84.4% |
SPI: 0.86 |
Behind Schedule |
Progress as on: 15-June-2021
WBS |
Work Description |
Total Quantity |
Total Done |
Schedule Start
| Schedule Finish |
Actual Start |
Actual Finish |
Lead-Lag(day) |
Not Yet |
1 |
Drawing-Design |
|
100% |
14-08-20 |
28-08-20 |
28-08-20 |
28-08-20 |
0 |
|
2 |
Mobilization and Layout |
|
100% |
18-08-20 |
24-08-20 |
24-08-20 |
24-08-20 |
0 |
|
3.1 |
Pile Work |
267nos |
100% |
25-08-20 |
30-09-20 |
30-09-20 |
30-09-20 |
0 |
|
3.2.1.1 |
Excavation for Pile Head Breaking |
60nos |
100% |
02-11-20 |
21-11-20 |
21-11-20 |
19-12-20 |
-28 |
|
3.2.1.2 |
Pile Head Breaking |
267nos |
100% |
04-11-20 |
23-01-21 |
23-11-20 |
23-11-20 |
61 |
|
3.2.1.3 |
Excavation for Pile cap |
60nos |
100% |
06-11-20 |
25-11-20 |
25-11-20 |
25-11-20 |
0 |
|
3.2.1.4 |
Pile Cap-Brick Flat Soling |
60nos |
100% |
08-11-20 |
27-11-20 |
27-11-20 |
27-11-20 |
0 |
|
3.2.1.5 |
Pile Cap-CC Work |
60nos |
100% |
09-11-20 |
28-11-20 |
28-11-20 |
28-11-20 |
0 |
|
3.2.1.6 |
Pile Cap Re-bar Work |
60nos |
100% |
17-11-20 |
06-12-20 |
03-12-20 |
05-12-20 |
1 |
|
3.2.1.7 |
Pile Cap-Form Work |
60nos |
100% |
19-11-20 |
08-12-20 |
03-12-20 |
05-12-20 |
3 |
|
3.2.1.8 |
Pile Cap Concreting |
60nos |
100% |
21-11-20 |
10-12-20 |
03-12-20 |
29-12-20 |
-19 |
|
3.2.2.1 |
Lift Core upto Mat-Re-bar Work |
2nos |
100% |
11-12-20 |
20-12-20 |
03-12-20 |
19-12-20 |
1 |
|
3.2.2.2 |
Lift-Core upto Mat-Form Work |
2nos |
100% |
12-12-20 |
21-12-20 |
03-12-20 |
19-12-20 |
2 |
|
3.2.2.3 |
Lift Core upto Mat-Concreting |
2nos |
100% |
13-12-20 |
22-12-20 |
19-12-20 |
19-12-20 |
3 |
|
3.2.3.1 |
Mat-Bed Preparation |
1311sqm |
100% |
28-11-20 |
11-12-20 |
05-12-20 |
29-12-20 |
-18 |
|
3.2.3.2 |
Mat-Brick Flat Soling |
1311sqm |
100% |
05-12-20 |
13-12-20 |
15-12-20 |
29-12-20 |
-16 |
|
3.2.3.3 |
Mat-Lean Concrete |
1311sqm |
100% |
10-12-20 |
14-12-20 |
15-12-20 |
29-12-20 |
-15 |
|
3.2.3.4 |
Mat-Re-bar Fabrication |
|
100% |
15-12-20 |
29-12-20 |
29-12-20 |
05-01-21 |
-7 |
|
3.2.3.5 |
Mat-Form works |
|
100% |
28-12-20 |
03-01-21 |
05-01-21 |
05-01-21 |
-2 |
|
3.2.3.6 |
Mat-Concreting |
1311sqm |
100% |
04-01-21 |
04-01-21 |
05-01-21 |
05-01-21 |
-1 |
|
3.3.1.1 |
South-Retaining Wall-Re-bar Work |
385sqm |
100% |
05-01-21 |
01-02-21 |
28-01-21 |
09-02-21 |
-8 |
|
3.3.1.2 |
South-Retaining Wall-Form Work |
385sqm |
100% |
23-01-21 |
06-02-21 |
28-01-21 |
09-02-21 |
-3 |
|
3.3.1.3 |
South-Retaining Wall-Concreting |
385sqm |
100% |
07-02-21 |
08-02-21 |
28-01-21 |
09-02-21 |
-1 |
|
3.3.2.1 |
North-Retaining Wall-Re-bar Work |
139m2 |
100% |
09-02-21 |
02-03-21 |
17-02-21 |
20-02-21 |
10 |
|
3.3.2.2 |
North-Retaining Wall-Form Work |
139m2 |
100% |
21-02-21 |
07-03-21 |
17-02-21 |
20-02-21 |
15 |
|
3.3.2.3 |
North-Retaining Wall-Concreting |
139m2 |
100% |
17-03-21 |
18-03-21 |
05-04-21 |
05-04-21 |
-18 |
|
3.4.1.1 |
Basement-South-Column-Re-bar work |
40nos |
100% |
05-01-21 |
01-02-21 |
28-01-21 |
28-01-21 |
4 |
|
3.4.1.2 |
Basement-South-Column-Shuttering |
40nos |
100% |
23-01-21 |
06-02-21 |
28-01-21 |
28-01-21 |
9 |
|
3.4.1.3 |
Basement-South-Column-Concreting |
40nos |
100% |
07-02-21 |
08-02-21 |
28-01-21 |
28-01-21 |
11 |
|
3.4.2 |
Basement-North Column |
21nos |
100% |
09-02-21 |
09-03-21 |
04-03-21 |
05-04-21 |
-27 |
|
3.5 |
Basement-Lft Core and Water Reservo |
289m2 |
100% |
26-02-21 |
09-03-21 |
20-03-21 |
05-04-21 |
-27 |
|
3.6 |
Basement-Stair |
3nos |
100% |
09-02-21 |
22-04-21 |
05-04-21 |
25-04-21 |
-3 |
|
3.7 |
Basement-Ramp |
2nos |
0% |
06-07-21 |
23-07-21 |
|
|
0 |
|
3.8.1.1 |
South-GF-Slab Shuttering |
743m2 |
100% |
16-02-21 |
27-02-21 |
17-02-21 |
15-03-21 |
-16 |
|
3.8.1.2 |
South-GF-Slab Re-bar Work |
743m2 |
100% |
28-02-21 |
09-03-21 |
07-03-21 |
15-03-21 |
-6 |
|
3.8.1.4 |
South-GF-Slab Concreting |
743m2 |
100% |
14-03-21 |
15-03-21 |
15-03-21 |
15-03-21 |
0 |
|
3.8.2 |
North-Ground Floor Slab |
495m2 |
100% |
02-04-21 |
22-04-21 |
10-04-21 |
25-04-21 |
-3 |
|
3.9 |
Basement-Wall and Ceiling plaster |
2415m2 |
11% |
30-05-21 |
30-07-21 |
07-03-21 |
15-06-21 |
45 |
|
4.1 |
Ground Floor-Column |
57nos |
95% |
27-04-21 |
05-06-21 |
28-04-21 |
09-06-21 |
-4 |
Completed |
4.2.1 |
Ground Floor-Roof Slab Shutter |
822m2 |
49% |
03-05-21 |
20-06-21 |
03-05-21 |
15-06-21 |
5 |
|
4.2.2 |
Gr.Floor Roof Slab-Re-bar Work |
160nos |
2% |
15-06-21 |
03-07-21 |
15-06-21 |
15-06-21 |
18 |
|
4.2.3 |
Ground Floor-Roof Slab Concreting |
822m2 |
% |
05-07-21 |
05-07-21 |
|
|
0 |
|
4.3 |
Ground Floor-Lift Core |
2nos |
52% |
25-05-21 |
15-06-21 |
30-05-21 |
07-06-21 |
8 |
|
4.4 |
Ground Floor-Stair Case |
2nos |
80% |
25-05-21 |
05-07-21 |
31-05-21 |
15-06-21 |
20 |
|
Site Photographs |
|
Pile Cap Re-bar Shuttering Work on 5-12-20 |
|
Pile Cap Re-bar Shuttering Work on 5-12-20 |
|
|
|
Pile Cap Concreting on 6-12-20 |
|
Pile Cap Concreting on 6-12-20 |
|
|
|
Mat CC Concreting on 15-12-20 |
|
Footing Curing on 15-12-20 |
|
|
|
Lift Core Concreting on 19-12-20 |
|
Footing Re-bar Placing on 19-12-20 |
|
|
|
Mat Re-bar Work on 29-12-20 |
|
Mat Re-bar Work on 29-12-20 |
|
|
|
Inspection before Mat Concreting on 5-01-21 |
|
Mat Concreting on 5-01-21 |
|
|
|
Retaining wall and Column Concreting on 28-01-21 |
|
Retaining wall and Column Concreting on 28-01-21 |
|
|
|
South Retaining wall 2nd Lift Concretin on 9-02-21 |
|
South Retaining wall 2nd Lift Concretin on 9-02-21 |
|
|
|
on 17-02-21 |
|
on 17-02-21 |
Project Closed 11-15 Feb 2021 due to Honarable Late Z.H. Sikder Death |
|
|
Retaining Wall Shuttering on 18-02-21 |
|
Retaining Wall Shuttering on 18-02-21 |
|
|
|
Retaining Wall Concreting on 20-02-21 |
|
Retaining wall Concreting on 20-02-21 |
|
|
|
Toolbox Meeting on 25-02-21 |
|
Ground Floor Slab Shuttering on 25-02-21 |
|
|
|
Tool Box Meeting on 4-03-21 |
|
Night Shift Working on 4-03-21 |
|
|
|
GF Slab Re-bar Inspection on 7-03-21 |
|
Basement West Wall Plastering on 7-03-21 |
|
|
|
GF Slab Shuttering at Night Shift on 8-03-21 |
|
GF Slab Re-bar Work at Night Shift on 8-03-21 |
|
|
|
Ground Floor Slab Re-bar Work on 10-03-21 |
|
GF Slab Shuttering at Night Shift on 10-03-21 |
|
|
|
GF North-Slab 8000 sft Concreting on 15-03-21 |
|
GF Slab Concreting complete at night on 15-03-21 |
|
|
|
on 20-03-21 |
|
on 20-03-21 |
|
|
|
on 27-03-21 |
|
on 27-03-21 |
|
|
|
on 29-03-21 |
|
on 29-03-21 |
|
|
|
on 31-03-21 |
|
on 31-03-21 |
|
|
|
Ground Floor Column Re-bar Work on 1-04-21 |
|
Beam Shutter Making on 1-04-21 |
|
|
|
on 4-04-21 |
|
on 4-04-21 |
|
|
|
Lift Core Wall Concreting on 5-04-21 |
|
Water Reservoir Wall Concreting on 5-04-21 |
|
|
|
Coulmn Shuttering on 10-04-21 |
|
Ground Floor Slab Shuttering on 10-04-21 |
|
|
|
Inspection before GF Slab Concreting on 25-04-21 |
|
Ground Floor Slab Concreting on 25-04-21 |
|
|
|
Toolbox Meeting on 28-04-21 |
|
G.M. Construction Visit on 28-04-21 |
|
|
|
Column Shutteeing on 30-04-21 |
|
Beam Shuttering on 30-04-21 |
|
|
|
Column Concreting on 3-05-21 |
|
Beam Shuttering on 3-05-21 |
|
|
|
Column Re-bar Work on 4-05-21 |
|
Column Shuttering Work on 4-05-21 |
|
|
|
Column Re-bar Work on 8-05-21 |
|
Column Shuttering Work on 8-05-21 |
|
|
|
Column Shuttering on 9-05-21 |
|
Column Curing on 9-05-21 |
|
|
|
Tool Box Meeting on 12-05-21 |
|
Ground Floor-Column Shuttering Work on 12-05-21 |
|
|
|
Tool Box Meeting on 20-05-21 |
|
Ground Floor Re-bar Work on 20-05-21 |
Project closed 13-19 May due to Eid-ul Fitre Vacation |
|
|
Ground Floor-Column Concreting on 23-05-21 |
|
Ground Floor-Column Concreting on 23-05-21 |
|
|
|
Ground Floor-Column Concreting on 25-05-21 |
|
Ground Floor-Lift Core-Re-bar Work on 25-05-21 |
|
|
|
Ground Floor-Column Concreting on 26-05-21 |
|
Ground Floor-Roof Beam Shuttering on 26-05-21 |
|
|
|
Ground Floor-Lift Wall Shuttering on 30-05-21 |
|
Ground Floor-Column Concreting on 30-05-21 |
|
|
|
Ground Floor Stiar Concreting on 31-05-21 |
|
Ground Floor Roof Slab Shuttering on 31-05-21 |
|
|
|
1st Floor Slab Shuttering on 3-06-21 |
|
1st Floor Slab Shutter Levelling on 3-06-21 |
|
|
|
Ground Floor Column Concreting on 6-06-21 |
|
1st Floor Beam Shuttering on 6-06-21 |
|
|
|
Ground floor Lift Core Shuttering on 7-06-21 |
|
Ground Floor Construction on 7-06-21 |
|
|
|
Ground Floor Stair Re-bar work on 9-06-21 |
|
1st floor Slab Shuttering on 9-06-21 |
|
|
|
Honourable RAJUK Charman Visit on 12-06-21 |
|
1st floor Slab Shuttering on 12-06-21 |
|
|
|
Ground Floor Lift Core Shuttering on 15-06-21 |
|
1st floor Slab Shuttering on 15-06-21 |
|
|