DAILY PROGRES REPORT |
Project: | BTT Sales Center Purbachal | Project Code: | 48 | Date | 15-June-2021 | ||
Client: | Power Pac Holdings Ltd | Report | 047 | Day | Tuesday | ||
Contractor: | Cityscape International Ltd. | Climate | Sunny | ||||
Temperature | 26-32C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Cityscape-BTT | 14 |
02 | Elite Force-BTT | 6 |
03 | Blue Star-BTT | 13 |
04 | Civil-Lavlu | 12 |
08 | Civil-Abul | 10 |
TOTAL | 55 |
WBS | Work Description | Progress as on: 15-June-2021 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
3.9 | Basement-Wall and Ceiling plaster | 2415m2 | 2 | 11 | 30-05-21 | 30-07-21 | |
4.2.1 | Ground Floor-Roof Slab Shutter | 822m2 | 4 | 49 | 03-05-21 | 20-06-21 | |
4.2.2 | Gr.Floor Roof Slab-Re-bar Work | 160nos | 2 | 2 | 15-06-21 | 03-07-21 | |
4.4 | Ground Floor-Stair Case | 2nos | 41 | 80 | 25-05-21 | 05-07-21 |
Site Photographs | |
Ground Floor Lift Core Shuttering | 1st floor Slab Shuttering |
Site Description | |
Site Instruction | |