Return Main Menu

DAILY PROGRES REPORT

Project:BTT Sales Center Purbachal Project Code: 48 Date15-June-2021
Client: Power Pac Holdings Ltd Report047 DayTuesday
Contractor:Cityscape International Ltd. ClimateSunny
Temperature26-32C
Manpower
SNDescriptionNos
01Cityscape-BTT14
02Elite Force-BTT6
03Blue Star-BTT13
04Civil-Lavlu12
08Civil-Abul10
TOTAL 55
WBSWork Description Progress as on: 15-June-2021
Total QtyToday Done (%)Total Done (%)StartFinish
3.9 Basement-Wall and Ceiling plaster 2415m2 2 11 30-05-21 30-07-21
4.2.1 Ground Floor-Roof Slab Shutter 822m2 4 49 03-05-21 20-06-21
4.2.2 Gr.Floor Roof Slab-Re-bar Work 160nos 2 2 15-06-21 03-07-21
4.4 Ground Floor-Stair Case 2nos 41 80 25-05-21 05-07-21
Site Photographs
Ground Floor Lift Core Shuttering1st floor Slab Shuttering
Site Description
Site Instruction