WEEKY PROGRESS REPORT |
From 21-February-2021 to 28-February-2021 | ||||
Project Code: | 32 | Name: | Sikder Center | |
Client: | Multiplex Holding Ltd. | Contractor: | Cityscape International Ltd. |
Progress as on: 28-February-2021 | ||||||||
WBS | Work Description | |||||||
Total Quantity | Upto 21-02-21 | This Week | Total Done | Schedule Start | Schedule Finish | Avtual Finish | ||
04 | 5-7F-Patent Stone Floor | 0% | 100% | 100% | 05-12-20 | 12-12-20 | 28-02-21 | |
15 | 15-19F-Duct Wall Plaster | 0% | 100% | 100% | 02-12-20 | 07-12-20 | 28-02-21 | |
27 | 7F-Safety Tray Removing | 40% | 25% | 65% | 12-12-20 | 15-12-20 | 28-02-21 |
Site Photographs | |
Rubish shifting to BTT, Purbachal on 28-02-21 | Toolbox meeting-Electrical Hazardon 28-02-21 |