DAILY PROGRES REPORT

Project:Sikder Center Project Code: 32 Date28-February-2021
Client: Multiplex Holding Ltd. Report016 DaySunday
Contractor:Cityscape International Ltd. ClimateSunny
Temperature24-33C
Manpower
SNDescriptionNos
01Cityscape-SC6
02Elite Force-SC3
03Blue Star-SC16
04Arif Enterprise-Civil Con2
TOTAL 27
WBSWork Description Progress as on: 28-February-2021
Total QtyToday Done (%)Total Done (%)StartFinish
04 5-7F-Patent Stone Floor 100 100 05-12-20 12-12-20
15 15-19F-Duct Wall Plaster 100 100 02-12-20 07-12-20
27 7F-Safety Tray Removing 25 65 12-12-20 15-12-20
Site Photographs
Rubish shifting to BTT, Purbachal Toolbox meeting-Electrical Hazard
Site Description
Site Instruction