DAILY PROGRES REPORT |
Project: | Sikder Center | Project Code: | 32 | Date | 28-February-2021 | ||
Client: | Multiplex Holding Ltd. | Report | 016 | Day | Sunday | ||
Contractor: | Cityscape International Ltd. | Climate | Sunny | ||||
Temperature | 24-33C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Cityscape-SC | 6 |
02 | Elite Force-SC | 3 |
03 | Blue Star-SC | 16 |
04 | Arif Enterprise-Civil Con | 2 |
TOTAL | 27 |
WBS | Work Description | Progress as on: 28-February-2021 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
04 | 5-7F-Patent Stone Floor | 100 | 100 | 05-12-20 | 12-12-20 | ||
15 | 15-19F-Duct Wall Plaster | 100 | 100 | 02-12-20 | 07-12-20 | ||
27 | 7F-Safety Tray Removing | 25 | 65 | 12-12-20 | 15-12-20 |
Site Photographs | |
Rubish shifting to BTT, Purbachal | Toolbox meeting-Electrical Hazard |
Site Description | |
Site Instruction | |