MONTHLY PROGRESS REPORT

From 1-February-2021 to 28-February-2021
Project Code: 32Name:Sikder Center
Client: Multiplex Holding Ltd. Contractor:Cityscape International Ltd.
Progress as on: 28-February-2021
WBSWork Description
Total QuantityUpto 31-01-21This MonthTotal Done Schedule StartSchedule FinishActual Finish
04 5-7F-Patent Stone Floor 0% 100% 100% 05-12-20 12-12-20 28-02-21
15 15-19F-Duct Wall Plaster 0% 100% 100% 02-12-20 07-12-20 28-02-21
21 4-12F-Tolilet Counter Slab RCC 0% 100% 100% 05-12-20 15-12-20 05-02-21
24 4-8F-Est Plaster-Partial North 40% 60% 100% 08-12-20 15-12-20 10-02-21
26 13F-Safety Tray Removing 80% 20% 100% 02-12-20 15-12-20 01-02-21
27 7F-Safety Tray Removing 40% 25% 65% 12-12-20 15-12-20 28-02-21


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Toolbox Meeting-Work at Height on 1-02-2113F-External Safety Tray Removingon 1-02-21
Front Side Opening Soon on 5-02-21Round Stair Skirting Plaster finished foon 5-02-21
Duct upstand Blockwork on 10-02-2111F Toilet Conterslab Shutter Level Markon 10-02-21
Rubish shifting to BTT, Purbachal on 28-02-21Toolbox meeting-Electrical Hazardon 28-02-21