TOTAL PROGRES REPORT

From 22-December-2022 to 6-March-2023
Project Code: 61 Name: Cityscape Tower Level-15 Bar
Client: Cityscape Contractor: Cityscape International Ltd.
Progress as on: 6-March-2023
Total Duration: 74 days Total Working Days: 15 Total Manpower: 129
Planning Progress = 100% Acual Progress = 54.6% SPI: 0.55 Behind Schedule
WBS Work Description
Total Quantity Total Done Schedule Start Schedule Finish Actual Start Actual Finish Lead-Lag(day) Not Yet
01 Glass Work 01 90% 22-12-22 21-01-23 22-12-22 06-03-23 -44 Completed
02 Carpentry Mock-up 1sum 100% 22-12-22 23-12-22 22-12-22 26-12-22 -3
03 Bar Counter 1sum 50% 22-12-22 06-01-23 22-12-22 26-01-23 -20 Completed
04 Washroom Brickwork 1sum 90% 22-12-22 27-12-22 22-12-22 03-01-23 -7 Completed
05 Floor Finsh-NCF 1sum 100% 26-12-22 31-12-22 03-01-23 12-02-23 -43
06 Wall Paneling 1sum 5% 08-02-23 09-03-23 08-02-23 08-02-23 29


DAILY MANPOWER








CUMMULATIVE ACTUAL WORK PROGRESS








CUMMULATIVE PLAN WORK PROGRESS








CUMMULATIVE WORK PROGRESS








SCHEDULE AHEAD-BEHIND






Site Photographs
Carpentry Mock-up on 22-12-22
Brick work demolition on 22-12-22
on 23-12-22
on 23-12-22
on 26-12-22
on 26-12-22
Glass Work on 31-12-22
Wash Room Brick work on 31-12-22
Interior works on 3-01-23
Floor Finishing-NCF on 3-01-23
Fixing Glass on 9-01-23
Fixing Glass on 9-01-23
on 14-01-23
on 14-01-23
on 17-01-23
on 17-01-23
on 26-01-23
Safety Instruction on 26-01-23
on 31-01-23
on 31-01-23
on 5-02-23
on 5-02-23
Wall Paneling on 8-02-23
Wall Paneling on 8-02-23
L-15-Floor Neat Cement Finishing on 12-02-23
L-15-Floor Neat Cement Finishing on 12-02-23
L-15-North Side Glass Framing on 27-02-23
L-15-North Side Glass Framing on 27-02-23
L-15-South side glass fixing on 6-03-23
L-15-South side glass fixing on 6-03-23