DAILY PROGRES REPORT |
Project: | Cityscape Tower Level-15 Bar | Project Code: | 61 | Date | 6-March-2023 | ||
Client: | Cityscape | Report | 015 | Day | Monday | ||
Contractor: | Cityscape International Ltd. | Climate | Sunny | ||||
Temperature | 22-33C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Glass Engr | 1 |
02 | Glass Worker | 9 |
TOTAL | 10 |
WBS | Work Description | Progress as on: 6-March-2023 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
01 | Glass Work | 01 | 5 | 90 | 22-12-22 | 21-01-23 |
Site Photographs | |
L-15-South side glass fixing | L-15-South side glass fixing |
Site Description | |
Site Instruction | |