MONTHLY PROGRESS REPORT |
From 1-March-2023 to 6-March-2023 | ||||
Project Code: | 61 | Name: | Cityscape Tower Level-15 Bar | |
Client: | Cityscape | Contractor: | Cityscape International Ltd. |
Progress as on: 6-March-2023 | ||||||||
WBS | Work Description | |||||||
Total Quantity | Upto 28-02-23 | This Month | Total Done | Schedule Start | Schedule Finish | Actual Finish | ||
01 | Glass Work | 01 | 85% | 5% | 90% | 22-12-22 | 21-01-23 | 06-03-23 |
Site Photographs | |
L-15-South side glass fixing on 6-03-23 | L-15-South side glass fixing on 6-03-23 |