Total Duration: |
239 |
days |
Total Working Days: |
60 |
Total Manpower: |
20318 |
|
|
Planning Progress = 93% |
Acual Progress = 87.1% |
SPI: 0.94 |
Behind Schedule |
Progress as on: 2-September-2021
WBS |
Work Description |
Total Quantity |
Total Done |
Schedule Start
| Schedule Finish |
Actual Start |
Actual Finish |
Lead-Lag(day) |
Not Yet |
01 |
Ground Floor |
|
100% |
11-11-20 |
12-12-20 |
12-12-20 |
12-12-20 |
0 |
|
03 |
2nd Floor |
|
100% |
18-12-20 |
06-01-21 |
06-01-21 |
06-01-21 |
0 |
|
04.1.1 |
3rd Floor-South Tower-Column |
14nos |
100% |
02-01-21 |
08-01-21 |
06-01-21 |
06-01-21 |
2 |
|
04.1.2 |
3rd Floor-South Tower-Lift Core |
2nos |
100% |
02-01-21 |
08-01-21 |
06-01-21 |
06-01-21 |
2 |
|
04.1.3 |
3rd Floor-South Tower-Stair |
2nos |
100% |
09-01-21 |
13-01-21 |
11-01-21 |
11-01-21 |
2 |
|
04.1.4 |
3rd Floor-South Tower-Roof Slab |
958sqm |
100% |
09-01-21 |
13-01-21 |
11-01-21 |
11-01-21 |
2 |
|
04.2.1 |
3rd Floor-North Tower-Column |
11nos |
100% |
07-01-21 |
13-01-21 |
14-01-21 |
14-01-21 |
-1 |
|
04.2.2 |
3rd Floor-North Tower-Lift Core |
2nos |
100% |
07-01-21 |
13-01-21 |
16-01-21 |
16-01-21 |
-3 |
|
04.2.3 |
3rd Floor-North Tower-Stair |
2nos |
100% |
14-01-21 |
18-01-21 |
14-01-21 |
18-01-21 |
0 |
|
04.2.4 |
3rd Floor-North Tower-Roof Slab |
958sqm |
100% |
14-01-21 |
18-01-21 |
14-01-21 |
18-01-21 |
0 |
|
05.1.1 |
4th Floor-South Tower-Column |
14nos |
100% |
14-01-21 |
20-01-21 |
14-01-21 |
14-01-21 |
6 |
|
05.1.2 |
4th Floor-South Tower-Lift Core |
2nos |
100% |
14-01-21 |
20-01-21 |
14-01-21 |
16-01-21 |
4 |
|
05.1.3 |
4th Floor-South Tower-Stair |
2nos |
100% |
21-01-21 |
25-01-21 |
20-01-21 |
21-01-21 |
4 |
|
05.1.4 |
4th Floor-South Tower-Roof Slab |
960sqm |
100% |
21-01-21 |
25-01-21 |
20-01-21 |
21-01-21 |
4 |
|
05.2.1 |
4th Floor-North Tower-Column |
11nos |
100% |
19-01-21 |
25-01-21 |
19-01-21 |
19-01-21 |
6 |
|
05.2.2 |
4th Floor-North Tower-Lift Core |
2nos |
100% |
19-01-21 |
25-01-21 |
20-01-21 |
22-01-21 |
3 |
|
05.2.3 |
4th Floor-North Tower-Stair |
2nos |
100% |
26-01-21 |
30-01-21 |
27-01-21 |
27-01-21 |
3 |
|
05.2.4 |
4th Floor-North Tower-Roof Slab |
960sqm |
100% |
26-01-21 |
30-01-21 |
27-01-21 |
27-01-21 |
3 |
|
06.1.1 |
5th Floor-South Tower-Column |
14nos |
100% |
26-01-21 |
01-02-21 |
22-01-21 |
22-01-21 |
10 |
|
06.1.2 |
5th Floor-South Tower-Lift Core |
2nos |
100% |
26-01-21 |
01-02-21 |
24-01-21 |
24-01-21 |
8 |
|
06.1.3 |
5th Floor-South Tower-Stair |
2nos |
100% |
02-02-21 |
06-02-21 |
01-02-21 |
01-02-21 |
5 |
|
06.1.4 |
5th Floor-South Tower-Roof Slab |
840sqm |
100% |
02-02-21 |
06-02-21 |
01-02-21 |
01-02-21 |
5 |
|
06.2.1 |
5th Floor-North Tower-Column |
11nos |
100% |
31-01-21 |
06-02-21 |
29-01-21 |
29-01-21 |
8 |
|
06.2.2 |
5th Floor-North Tower-Lift Core |
2nos |
100% |
31-01-21 |
06-02-21 |
30-01-21 |
02-02-21 |
4 |
|
06.2.3 |
5th Floor-North Tower-Stair |
2nos |
100% |
07-02-21 |
11-02-21 |
06-02-21 |
06-02-21 |
5 |
|
06.2.4 |
5th Floor-North Tower-Roof Slab |
960sqm |
100% |
07-02-21 |
11-02-21 |
06-02-21 |
06-02-21 |
5 |
|
07.1.1 |
6th Floor-South Tower-Column |
14nos |
100% |
07-02-21 |
13-02-21 |
03-02-21 |
03-02-21 |
10 |
|
07.1.2 |
6th Floor-South Tower-Lift Core |
2nos |
100% |
07-02-21 |
13-02-21 |
04-02-21 |
06-02-21 |
7 |
|
07.1.3 |
6th Floor-South Tower-Stair |
2nos |
100% |
14-02-21 |
18-02-21 |
16-02-21 |
16-02-21 |
2 |
|
07.1.4 |
6th Floor-South Tower-Roof Slab |
963sqm |
100% |
14-02-21 |
18-02-21 |
16-02-21 |
16-02-21 |
2 |
|
07.2.1 |
6th Floor-North Tower-Column |
11nos |
100% |
12-02-21 |
18-02-21 |
08-02-21 |
08-02-21 |
10 |
|
07.2.2 |
6th Floor-North Tower-Lift Core |
2nos |
100% |
12-02-21 |
18-02-21 |
15-02-21 |
18-02-21 |
0 |
|
07.2.3 |
6th Floor-North Tower-Stair |
2nos |
100% |
19-02-21 |
23-02-21 |
22-02-21 |
23-02-21 |
0 |
|
07.2.4 |
6th Floor-North Tower-Roof Slab |
960sqm |
100% |
19-02-21 |
23-02-21 |
22-02-21 |
23-02-21 |
0 |
|
08.1.1 |
7th Floor-South Tower-Column |
14nos |
100% |
19-02-21 |
25-02-21 |
19-02-21 |
19-02-21 |
6 |
|
08.1.2 |
7th Floor-South Tower-Lift Core |
2nos |
100% |
19-02-21 |
25-02-21 |
19-02-21 |
22-02-21 |
3 |
|
08.1.3 |
7th Floor-South Tower-Stair Case |
2nos |
100% |
26-02-21 |
02-03-21 |
01-03-21 |
01-03-21 |
1 |
|
08.1.4 |
7th Floor-South Tower-Roof Slab |
950sqm |
100% |
26-02-21 |
02-03-21 |
01-03-21 |
01-03-21 |
1 |
|
08.2.1 |
7th Floor-North Tower-Column |
11nos |
100% |
24-02-21 |
02-03-21 |
25-02-21 |
25-02-21 |
5 |
|
08.2.2 |
7th Floor-North Tower-Lift Core |
2nos |
100% |
24-02-21 |
02-03-21 |
26-02-21 |
02-03-21 |
0 |
|
08.2.3 |
7th Floor-North Tower-Stair Case |
2nos |
100% |
03-03-21 |
07-03-21 |
08-03-21 |
08-03-21 |
-1 |
|
08.2.4 |
7th Floor-North Tower-Slab |
960m2 |
100% |
03-03-21 |
07-03-21 |
08-03-21 |
08-03-21 |
-1 |
|
09.1.1 |
8th Floor-South Tower-Column |
14nos |
100% |
03-03-21 |
09-03-21 |
05-03-21 |
05-03-21 |
4 |
|
09.1.2 |
8th Floor-South Tower-Lift Core |
2nos |
100% |
03-03-21 |
09-03-21 |
08-03-21 |
11-03-21 |
-2 |
|
09.1.3 |
8th Floor-South Tower-Stair Case |
2nos |
100% |
10-03-21 |
14-03-21 |
17-03-21 |
17-03-21 |
-3 |
|
09.1.4 |
8th Floor-South Tower-Roof Slab |
963m2 |
100% |
10-03-21 |
14-03-21 |
17-03-21 |
17-03-21 |
-3 |
|
09.2.1 |
8th Floor-North Tower-Column |
11nos |
100% |
08-03-21 |
14-03-21 |
12-03-21 |
12-03-21 |
2 |
|
09.2.2 |
8th Floor-North Tower-Lift Core |
2nos |
100% |
08-03-21 |
14-03-21 |
14-03-21 |
20-03-21 |
-6 |
|
09.2.3 |
8th Floor-North Tower-Stair Case |
2nos |
100% |
15-03-21 |
19-03-21 |
05-04-21 |
05-04-21 |
-17 |
|
09.2.4 |
8th Floor-North Tower-Roof Slab |
958m2 |
100% |
15-03-21 |
19-03-21 |
05-04-21 |
05-04-21 |
-17 |
|
10.1.1 |
9th Floor-South Tower-Column |
14nos |
100% |
15-03-21 |
21-03-21 |
28-03-21 |
31-03-21 |
-10 |
|
10.1.2 |
9th Floor-South Tower-Lift Core |
2nos |
100% |
15-03-21 |
21-03-21 |
28-03-21 |
06-04-21 |
-16 |
|
10.1.3 |
9th Floor-South Tower-Stair |
2nos |
100% |
22-03-21 |
26-03-21 |
13-04-21 |
13-04-21 |
-18 |
|
10.1.4 |
9th Floor-South Tower-Roof Slab |
963m2 |
100% |
22-03-21 |
26-03-21 |
13-04-21 |
13-04-21 |
-18 |
|
10.2.1 |
9th Floor-North Tower-Column |
11nos |
100% |
20-03-21 |
26-03-21 |
09-04-21 |
09-04-21 |
-14 |
|
10.2.2 |
9th Floor-North Tower-Lift Core |
2nos |
100% |
20-03-21 |
26-03-21 |
12-04-21 |
16-04-21 |
-21 |
|
10.2.3 |
9th Floor-North Tower-Stair |
2nos |
100% |
27-03-21 |
31-03-21 |
23-04-21 |
23-04-21 |
-23 |
|
10.2.4 |
9th Floor-North Tower-Roof Slab |
958m2 |
100% |
27-03-21 |
31-03-21 |
23-04-21 |
23-04-21 |
-23 |
|
11.1.1 |
10th Floor-South Tower-Column |
14nos |
100% |
27-03-21 |
02-04-21 |
17-04-21 |
17-04-21 |
-15 |
|
11.1.2 |
10th Floor-South Tower-Lift Core |
2nos |
100% |
27-03-21 |
02-04-21 |
17-04-21 |
21-04-21 |
-19 |
|
11.1.3 |
10th Floor-South Tower-Stair |
2nos |
100% |
03-04-21 |
07-04-21 |
04-05-21 |
04-05-21 |
-27 |
|
11.1.4 |
10th Floor-South Tower-Roof Slab |
963m2 |
100% |
03-04-21 |
07-04-21 |
04-05-21 |
04-05-21 |
-27 |
|
11.2.1 |
10th Floor-North Tower-Column |
11nos |
100% |
01-04-21 |
07-04-21 |
27-04-21 |
27-04-21 |
-20 |
|
11.2.2 |
10th Floor-North Tower-Lift Core |
2nos |
100% |
01-04-21 |
07-04-21 |
29-04-21 |
02-05-21 |
-25 |
|
11.2.3 |
10th Floor-North Tower-Stair |
2nos |
100% |
08-04-21 |
12-04-21 |
10-05-21 |
10-05-21 |
-28 |
|
11.2.4 |
10th Floor-North Tower-Roof Slab |
958m2 |
100% |
08-04-21 |
12-04-21 |
10-05-21 |
10-05-21 |
-28 |
|
12.1.1 |
11th Floor-South Tower-Column |
14nos |
100% |
08-04-21 |
14-04-21 |
09-05-21 |
09-05-21 |
-25 |
|
12.1.2 |
11th Floor-South Tower-Lift Core |
2nos |
100% |
08-04-21 |
14-04-21 |
09-05-21 |
12-06-21 |
-59 |
|
12.1.3 |
11th Floor-South Tower-Stair |
2nos |
100% |
15-04-21 |
19-04-21 |
02-09-21 |
02-09-21 |
-136 |
|
12.1.4 |
11th Floor-South Tower-Roof Slab |
963m2 |
100% |
15-04-21 |
19-04-21 |
02-09-21 |
02-09-21 |
-136 |
|
12.2.1 |
11th Floor-North Tower-Column |
11nos |
100% |
13-04-21 |
19-04-21 |
31-05-21 |
04-06-21 |
-46 |
|
12.2.2 |
11th Floor-North Tower-Lift Core |
2nos |
50% |
13-04-21 |
19-04-21 |
15-06-21 |
15-06-21 |
-57 |
Completed |
12.2.3 |
11th Floor-North Tower-Stair |
2nos |
0% |
20-04-21 |
24-04-21 |
|
|
0 |
Started |
12.2.4 |
11th Floor-North Tower-Roof Slab |
958m2 |
0% |
20-04-21 |
24-04-21 |
|
|
0 |
Started |
13.1.1 |
12th Floor-South Tower-Column |
13nos |
% |
20-04-21 |
26-04-21 |
|
|
0 |
Started |
13.1.2 |
12th Floor-South Tower-Lift Core |
2nos |
% |
20-04-21 |
26-04-21 |
|
|
0 |
Started |
13.2.1 |
12th Floor-North Tower-Column |
11nos |
% |
25-04-21 |
01-05-21 |
|
|
0 |
Started |
13.2.2 |
12th Floor-North Tower-Lift Core |
2nos |
% |
25-04-21 |
01-05-21 |
|
|
0 |
Started |
Site Photographs |
|
3rd Floor South Tower-Column Complete on 6-01-21 |
|
3rd Floor South Tower Lift Core Complete on 6-01-21 |
|
|
|
3rd Floor South Tower-Stair Complete on 11-01-21 |
|
3rd Floor South Tower Slab Complete on 11-01-21 |
|
|
|
Lift Core Wall Shttering on 14-01-21 |
|
Re-bar Lifting by Roof Hoist on 14-01-21 |
|
|
|
Night Shift Working on 16-01-21 |
|
Lift Core Wall Shuttering on 16-01-21 |
|
|
|
Lift Core Wall Shuttering on 17-01-21 |
|
Re-bar Lifting by Roof Hoist on 17-01-21 |
|
|
|
Re-bar Work on 18-01-21 |
|
on 18-01-21 |
|
|
|
on 19-01-21 |
|
on 19-01-21 |
|
|
|
South Tower 4th Floor Roof Slab Running on 20-01-21 |
|
North Tower 4th Floor Lift Core Running on 20-01-21 |
|
|
|
South Tower 4th Floor Roof Slab Concreti on 21-01-21 |
|
Night Shift Working on 21-01-21 |
|
|
|
Curing after 4F South Tower Slab Concret on 22-01-21 |
|
Re-bar Work on 22-01-21 |
|
|
|
Project Picture on 24-01-21 |
|
Project Picture on 24-01-21 |
|
|
|
Slab Re-bar Work on 27-01-21 |
|
Slab Shuttering on 27-01-21 |
|
|
|
Project Picture on 29-01-21 |
|
Inside Building on 29-01-21 |
|
|
|
Slab Re-bar Work on 30-01-21 |
|
Work Inspection on 30-01-21 |
|
|
|
Roof Slab on 1-02-21 |
|
Inside on 1-02-21 |
|
|
|
Safety Railing on 3-02-21 |
|
Project Picture on 3-02-21 |
|
|
|
Night Shift Working on 4-02-21 |
|
Night Shift Working on 4-02-21 |
|
|
|
Project View from East Side on 6-02-21 |
|
Project View from West Side on 6-02-21 |
|
|
|
View from East Side on 8-02-21 |
|
View from West Side on 8-02-21 |
|
|
|
Project was closed 11-14 Feb 2021 due to on 15-02-21 |
|
on 15-02-21 |
|
|
|
on 16-02-21 |
|
on 16-02-21 |
|
|
|
on 18-02-21 |
|
on 18-02-21 |
|
|
|
on 19-02-21 |
|
on 19-02-21 |
|
|
|
on 20-02-21 |
|
on 20-02-21 |
|
|
|
on 21-02-21 |
|
on 21-02-21 |
|
|
|
on 22-02-21 |
|
on 22-02-21 |
|
|
|
on 23-02-21 |
|
on 23-02-21 |
|
|
|
on 25-02-21 |
|
on 25-02-21 |
|
|
|
on 26-02-21 |
|
on 26-02-21 |
|
|
|
on 1-03-21 |
|
on 1-03-21 |
|
|
|
on 2-03-21 |
|
on 2-03-21 |
|
|
|
on 5-03-21 |
|
on 5-03-21 |
|
|
|
on 8-03-21 |
|
on 8-03-21 |
|
|
|
on 11-03-21 |
|
on 11-03-21 |
|
|
|
on 12-03-21 |
|
on 12-03-21 |
|
|
|
on 14-03-21 |
|
on 14-03-21 |
|
|
|
on 17-03-21 |
|
on 17-03-21 |
|
|
|
on 20-03-21 |
|
on 20-03-21 |
|
|
|
View from East Side on 28-03-21 |
|
View from East Side on 28-03-21 |
|
|
|
View from East Side on 31-03-21 |
|
Night Shift Working on 31-03-21 |
|
|
|
8th Floor North Tower Roof Slab Casting on 5-04-21 |
|
8th Floor North Tower Roof Slab Casting on 5-04-21 |
|
|
|
on 6-04-21 |
|
on 6-04-21 |
|
|
|
on 9-04-21 |
|
on 9-04-21 |
|
|
|
on 12-04-21 |
|
on 12-04-21 |
|
|
|
on 13-04-21 |
|
South Tower 10th Floor Slab Concreting on 13-04-21 |
|
|
|
on 16-04-21 |
|
on 16-04-21 |
|
|
|
on 17-04-21 |
|
on 17-04-21 |
|
|
|
on 21-04-21 |
|
on 21-04-21 |
|
|
|
on 23-04-21 |
|
on 23-04-21 |
|
|
|
on 27-04-21 |
|
on 27-04-21 |
|
|
|
on 29-04-21 |
|
on 29-04-21 |
|
|
|
on 30-04-21 |
|
on 30-04-21 |
|
|
|
on 2-05-21 |
|
on 2-05-21 |
|
|
|
on 9-05-21 |
|
on 9-05-21 |
|
|
|
on 10-05-21 |
|
on 10-05-21 |
|
|
|
on 31-05-21 |
|
on 31-05-21 |
Project Closed 11-22 May due to Eid-ul Fitre Vacation |
|
|
on 4-06-21 |
|
on 4-06-21 |
|
|
|
on 12-06-21 |
|
on 12-06-21 |
|
|
|
on 15-06-21 |
|
on 15-06-21 |
|
|
|
South Tower 11th Floor Slab Concreting on 2-09-21 |
|
South Tower 11th Floor Slab Concreting on 2-09-21 |
|
|