MONTHLY PROGRESS REPORT

From 1-September-2021 to 2-September-2021
Project Code: 42Name:NBL Tower-Superstucure
Client: National Bank Limited Contractor:Cityscape International Ltd.
Progress as on: 2-September-2021
WBSWork Description
Total QuantityUpto 31-08-21This MonthTotal Done Schedule StartSchedule FinishActual Finish
12.1.3 11th Floor-South Tower-Stair 2nos 0% 100% 100% 15-04-21 19-04-21 02-09-21
12.1.4 11th Floor-South Tower-Roof Slab 963m2 0% 100% 100% 15-04-21 19-04-21 02-09-21


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
South Tower 11th Floor Slab Concreting on 2-09-21South Tower 11th Floor Slab Concretingon 2-09-21