DAILY PROGRES REPORT

Project:NBL Tower-Superstucure Project Code: 42 Date2-September-2021
Client: National Bank Limited Report061 DayThursday
Contractor:Cityscape International Ltd. ClimateSunny
Temperature28-34C
Manpower
SNDescriptionNos
01Cityscape Staff-NBL25
02Elite Force Security-NBL12
03Abu Sayed50
04Cityscape Civil Worker10
TOTAL 97
WBSWork Description Progress as on: 2-September-2021
Total QtyToday Done (%)Total Done (%)StartFinish
12.1.3 11th Floor-South Tower-Stair 2nos 100 100 15-04-21 19-04-21
12.1.4 11th Floor-South Tower-Roof Slab 963m2 100 100 15-04-21 19-04-21
Site Photographs
South Tower 11th Floor Slab ConcretingSouth Tower 11th Floor Slab Concreting