Total Duration: |
45 |
days |
Total Working Days: |
3 |
Total Manpower: |
61 |
|
|
Planning Progress = 95.8% |
Acual Progress = 95.8% |
SPI: 1 |
Ahead Schedule |
Progress as on: 30-April-2022
WBS |
Work Description |
Total Quantity |
Total Done |
Schedule Start
| Schedule Finish |
Actual Start |
Actual Finish |
Lead-Lag(day) |
Not Yet |
01.1.1 |
Mobilization-Pile Gap Filling-Material |
|
100% |
09-03-22 |
09-03-22 |
16-03-22 |
16-03-22 |
-7 |
|
01.1.2 |
Mobilization-Pile Gap Filling-Labor |
|
100% |
10-03-22 |
10-03-22 |
16-03-22 |
16-03-22 |
-6 |
|
01.2.1 |
Other-Excavation upto 1st Bracing |
0 |
100% |
09-03-22 |
13-03-22 |
16-03-22 |
16-03-22 |
-3 |
|
01.2.2 |
Other-Excavation upto 2nd Bracing |
0 |
100% |
21-03-22 |
27-03-22 |
02-04-22 |
30-04-22 |
-34 |
|
01.2.3 |
Other-Excavation upto Mat |
0 |
100% |
04-04-22 |
10-04-22 |
30-04-22 |
30-04-22 |
-20 |
|
01.3.1.1 |
Bracing-1st Layer-Bracket Fixing |
52nos |
100% |
14-03-22 |
15-03-22 |
16-03-22 |
02-04-22 |
-18 |
|
01.3.1.2 |
Bracing-1st Layer Installation |
488m2 |
100% |
16-03-22 |
20-03-22 |
16-03-22 |
30-04-22 |
-41 |
|
01.3.2.1 |
Bracing-2nd Layer-Bracket Fixing |
52nos |
100% |
28-03-22 |
29-03-22 |
30-04-22 |
30-04-22 |
-32 |
|
01.3.2.2 |
Bracing-2nd Layer Installation |
488m2 |
100% |
30-03-22 |
03-04-22 |
30-04-22 |
30-04-22 |
-27 |
|
01.4.1 |
Pile Gap Filling upto 1st Bracing |
154gap |
100% |
10-03-22 |
16-03-22 |
16-03-22 |
16-03-22 |
0 |
|
01.4.2 |
Pile Gap Filling upto 2nd Bracing |
154gap |
100% |
28-03-22 |
03-04-22 |
30-04-22 |
30-04-22 |
-27 |
|
01.4.3 |
Pile Gap Filling upto Mat |
154gap |
100% |
11-04-22 |
17-04-22 |
30-04-22 |
30-04-22 |
-13 |
|
01.5.1 |
Bracing Gap Filling-1st Bracing |
106m |
100% |
01-04-22 |
03-04-22 |
02-04-22 |
02-04-22 |
1 |
|
01.5.2 |
Bracing Gap Filling-2nd Bracing |
106m |
0% |
04-04-22 |
06-04-22 |
|
30-11--1 |
|
Started |