MONTHLY PROGRESS REPORT

From 1-April-2022 to 30-April-2022
Project Code: 19Name:DPDC Sub-Station at Goran Dhaka
Client: DPDC Contractor:
Progress as on: 30-April-2022
WBSWork Description
Total QuantityUpto 31-03-22This MonthTotal Done Schedule StartSchedule FinishActual Finish
01.2.2 Other-Excavation upto 2nd Bracing 0 0% 100% 100% 21-03-22 27-03-22 30-04-22
01.2.3 Other-Excavation upto Mat 0 0% 100% 100% 04-04-22 10-04-22 30-04-22
01.3.1.1 Bracing-1st Layer-Bracket Fixing 52nos 80% 20% 100% 14-03-22 15-03-22 02-04-22
01.3.1.2 Bracing-1st Layer Installation 488m2 30% 70% 100% 16-03-22 20-03-22 30-04-22
01.3.2.1 Bracing-2nd Layer-Bracket Fixing 52nos 0% 100% 100% 28-03-22 29-03-22 30-04-22
01.3.2.2 Bracing-2nd Layer Installation 488m2 0% 100% 100% 30-03-22 03-04-22 30-04-22
01.4.2 Pile Gap Filling upto 2nd Bracing 154gap 0% 100% 100% 28-03-22 03-04-22 30-04-22
01.4.3 Pile Gap Filling upto Mat 154gap 0% 100% 100% 11-04-22 17-04-22 30-04-22
01.5.1 Bracing Gap Filling-1st Bracing 106m 0% 100% 100% 01-04-22 03-04-22 02-04-22


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Gap filling inbetween joist and cap beam on 2-04-22Gap filling by mortering on 2-04-22
Water proofing work on 30-04-22Pile gap water proofing on 30-04-22