Progress as on: 30-April-2022 |
WBS | Work Description |
Total Quantity | Upto 31-03-22 | This Month | Total Done |
Schedule Start | Schedule Finish | Actual Finish |
01.2.2 |
Other-Excavation upto 2nd Bracing |
0 |
0% |
100% |
100% |
21-03-22 |
27-03-22 |
30-04-22 |
01.2.3 |
Other-Excavation upto Mat |
0 |
0% |
100% |
100% |
04-04-22 |
10-04-22 |
30-04-22 |
01.3.1.1 |
Bracing-1st Layer-Bracket Fixing |
52nos |
80% |
20% |
100% |
14-03-22 |
15-03-22 |
02-04-22 |
01.3.1.2 |
Bracing-1st Layer Installation |
488m2 |
30% |
70% |
100% |
16-03-22 |
20-03-22 |
30-04-22 |
01.3.2.1 |
Bracing-2nd Layer-Bracket Fixing |
52nos |
0% |
100% |
100% |
28-03-22 |
29-03-22 |
30-04-22 |
01.3.2.2 |
Bracing-2nd Layer Installation |
488m2 |
0% |
100% |
100% |
30-03-22 |
03-04-22 |
30-04-22 |
01.4.2 |
Pile Gap Filling upto 2nd Bracing |
154gap |
0% |
100% |
100% |
28-03-22 |
03-04-22 |
30-04-22 |
01.4.3 |
Pile Gap Filling upto Mat |
154gap |
0% |
100% |
100% |
11-04-22 |
17-04-22 |
30-04-22 |
01.5.1 |
Bracing Gap Filling-1st Bracing |
106m |
0% |
100% |
100% |
01-04-22 |
03-04-22 |
02-04-22 |